Question

In: Finance

Project P costs $10,400 and is expected to produce cash flows of $3,650 per year for...

Project P costs $10,400 and is expected to produce cash flows of $3,650 per year for five years.

Project Q costs $30,000 and is expected to produce cash flows of $9,250 per year for five years.

a. Calculate the NPV, IRR, MIRR, and traditional payback period for each project, assuming a required rate of return of 8 percent.

b. If the projects are independent, which project(s) should be selected? If they are mutually exclusive, which project should be selected?

Solutions

Expert Solution

Project P:

NPV:

NPV = Present value of cash inflows - present value of cash outflows

NPV = Annuity * [1 - 1 / (1 + r)n] / r -Initial investment

NPV = 3,650 * [1 - 1 / (1 + 0.08)5] / 0.08 - 10,400

NPV = 3,650 * [1 - 0.68058] / 0.08 - 10,400

NPV = 3,650 * 3.99271 - 10,400

NPV = $4,713.39

IRR:

IRR is the rate of return that makes NPV equal to 0

NPV = 3,650 * [1 - 1 / (1 + R)5] / R - 10,400

Using trial and error method, i.e., after trying various values for R, lets try try R as 22.23%

NPV = 3,650 * [1 - 1 / (1 + 0.2223)5] / 0.2223 - 10,400

NPV = 0

Therefore, IRR is 22.23%

MIRR:

Future value = Annuity * [(1 + r)n - 1] / r

Future value = 3650 * [(1 + 0.08)5 - 1] / 0.08

Future value = 3650 * 5.8666

Future value = 21,413.09

MIRR = (FV / initial investment)1/n - 1

MIRR = (21,413.09 / 10,400)1/5 - 1

MIRR = 0.1554 - 1

MIRR = 0.1554 or 15.54%

Traditional payback:

Payback period = Initial investment / cash flow

Payback period = 10,400 / 3,650

Payback period = 2.85 years

Project Q:

NPV:

NPV = Present value of cash inflows - present value of cash outflows

NPV = Annuity * [1 - 1 / (1 + r)n] / r -Initial investment

NPV = 9,250 * [1 - 1 / (1 + 0.08)5] / 0.08 - 30,000

NPV = 9,250 * [1 - 0.68058] / 0.08 - 30,000

NPV = 9,250 * 3.99271 - 30,000

NPV = $6,932.57

IRR:

IRR is the rate of return that makes NPV equal to 0

NPV = 9,250 * [1 - 1 / (1 + R)5] / R - 30,000

Using trial and error method, i.e., after trying various values for R, lets try try R as 16.41%

NPV = 9,250 * [1 - 1 / (1 + 0.1641)5] / 0.1641 - 30,000

NPV = 0

Therefore, IRR is 16.41%

MIRR:

Future value = Annuity * [(1 + r)n - 1] / r

Future value = 9250 * [(1 + 0.08)5 - 1] / 0.08

Future value = 9250 * 5.8666

Future value = 54,266.06

MIRR = (FV / initial investment)1/n - 1

MIRR = (54,266.06 / 30,000)1/5 - 1

MIRR = 1.1259 - 1

MIRR = 0.1259 or 12.59%

Traditional payback:

Payback period = Initial investment / cash flow

Payback period = 30,000 / 9,250

Payback period = 3.24 years

2)

If projects are independent, both should be selected as the NPVs are positive and IRR & MIRR is greater than cost of capital.

When projects are mutually exclusive, we always choose the project with the higher NPV. Therefore, project Q should be accepted.


Related Solutions

Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) modified internal rate of return (MIRR). The firm’s required rate of return is 14 percent. If the projects are independent, which project (s) should be selected? If...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) mod- ified internal rate of return (MIRR). The firm’s required rate of return is 14 percent.  Compute the (a) NPV, (b) IRR, (c) MIRR, and (d) discounted payback...
You are evaluating a project that is expected to produce cash flows of $5,000 each year...
You are evaluating a project that is expected to produce cash flows of $5,000 each year for the next 3 years and $7,000 each year for the following 3 years. The IRR of this 6-year project is 12%. If the firm’s WACC is 10%, what is the project’s NPV?
Project S costs $11,000 and its expected cash flows would be $6,000 per year for 5...
Project S costs $11,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,500 and its expected cash flows would be $14,500 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's > 0. b. Both Projects S and L, since both projects have NPV's > 0. c....
Project S costs $19,000 and its expected cash flows would be $7,000 per year for 5...
Project S costs $19,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $43,500 and its expected cash flows would be $11,750 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Both Projects S and L, since both projects have IRR's > 0. c....
Project S costs $17,000 and its expected cash flows would be $4,000 per year for 5...
Project S costs $17,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $25,000 and its expected cash flows would be $10,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have NPV's > 0. c. Both Projects S and L,...
10) Project S costs $19,000 and its expected cash flows would be $6,000 per year for...
10) Project S costs $19,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $41,000 and its expected cash flows would be $8,550 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's > 0. b. Project L, since the NPVL > NPVS. c. Project S, since the...
Project S costs $18,000 and its expected cash flows would be $4,000 per year for 5 years
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $26,000 and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV < 0. b. Project S, since the NPVS > NPVL. c....
Machine A costs $850,000 and would produce cash flows of $220,000 per year for the first...
Machine A costs $850,000 and would produce cash flows of $220,000 per year for the first two years, $350,000 per year for the next two years, and $150,000 in the final year. Machine B costs $650,000 and would produce cash flows of $250,000 per year for the first two years, $200,000 the following year, $150,000 in its fourth year, and $140,000 in its final year. Your required return is 11%. What is the IRR of buying machine B?
You are evaluating a project that will cost $497,000​, but is expected to produce cash flows...
You are evaluating a project that will cost $497,000​, but is expected to produce cash flows of $123,000 per year for 10 ​years, with the first cash flow in one year. Your cost of capital is 11.2% and your​ company's preferred payback period is three years or less. a. What is the payback period of this​ project? b. Should you take the project if you want to increase the value of the​ company? a. What is the payback period of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT