Question

In: Finance

CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would...

CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $42,500 and its expected cash flows would be $8,900 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer.

a. Neither Project S nor L, since each project's NPV < 0.

b. Project L, since the NPVL > NPVS.

c. Both Projects S and L, since both projects have NPV's > 0.

d. Both Projects S and L, since both projects have IRR's > 0.

e. Project S, since the NPVS > NPVL.

Solutions

Expert Solution

Ans e. Project S, since the NPVS > NPVL.

NPV of project S is positive and NPV of Project L is negative, So project S is better.

NPV of Project S $ 436.85

Year Project Cash Flows (i) DF@ 15% (ii) PV of Project S ( (i) * (ii) )
0 -18000 1                    (18,000.00)
1 5500 0.870                       4,782.61
2 5500 0.756                       4,158.79
3 5500 0.658                       3,616.34
4 5500 0.572                       3,144.64
5 5500 0.497                       2,734.47
NPV                           436.85

NPV of Project L -$12665.82    (Negative)

Year Project Cash Flows (i) DF@ 15% (ii) PV of Project L ( (i) * (ii) )
0 -42500 1                    (42,500.00)
1 8900 0.870                       7,739.13
2 8900 0.756                       6,729.68
3 8900 0.658                       5,851.89
4 8900 0.572                       5,088.60
5 8900 0.497                       4,424.87
NPV                    (12,665.82)

Related Solutions

Capital budgeting criteria: mutually exclusive projects Project S costs $17,000 and its expected cash flows would...
Capital budgeting criteria: mutually exclusive projects Project S costs $17,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $49,000 and its expected cash flows would be $15,000 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Neither S or L, since each project's NPV < 0. III. Both...
Capital Budgeting BioMed Engineering is considering two mutually exclusive investments. The projects' expected net cash flows...
Capital Budgeting BioMed Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as follows:                                                                                                                                                                                                                                            Expected Net Cash Flows                                                                                                Time     Project A          Project B                                                                                    0          ($405)                ($705)                                                                            1          ($285)              $200                                                                              2          ($205)              $205                                                                              3          ($105)              $210                                                                              4          $605                 $215                                                                              5          $650                 $220                                                                              6          $925                 $225                                                                              7          ($200)              $230                                                                  In your report, identify which project would be selected (assuming they are mutually exclusive) for each investment criterion. Note that cash outflows (costs) are given in parenthesis. Employ the Excel file to answer the following questions. Part 1: Net Present Value C. Construct NPV profiles...
Capital Budgeting BioMed Engineering is considering two mutually exclusive investments. The projects' expected net cash flows...
Capital Budgeting BioMed Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as follows:                                                                                                                                                                                                                                            Expected Net Cash Flows                                                                                                Time     Project A          Project B                                                                                    0          ($405)                ($705)                                                                            1          ($285)              $200                                                                              2          ($205)              $205                                                                              3          ($105)              $210                                                                              4          $605                 $215                                                                              5          $650                 $220                                                                              6          $925                 $225                                                                              7          ($200)              $230                                                                  In your report, identify which project would be selected (assuming they are mutually exclusive) for each investment criterion. Note that cash outflows (costs) are given in parenthesis. Employ the Excel file to answer the following questions. Part 2: Internal Rate of Return E. Use the...
Capital Budgeting BioMed Engineering is considering two mutually exclusive investments. The projects' expected net cash flows...
Capital Budgeting BioMed Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as follows:                                                                                                                                                                                                                                            Expected Net Cash Flows                                                                                                Time     Project A          Project B                                                                                    0          ($405)                ($705)                                                                            1          ($285)              $200                                                                              2          ($205)              $205                                                                              3          ($105)              $210                                                                              4          $605                 $215                                                                              5          $650                 $220                                                                              6          $925                 $225                                                                              7          ($200)              $230                                                                  In your report, identify which project would be selected (assuming they are mutually exclusive) for each investment criterion. Note that cash outflows (costs) are given in parenthesis. Employ the Excel file to answer the following questions. Part 3: Payback and PI G. Calculate the cumulative...
Project S costs $18,000 and its expected cash flows would be $4,000 per year for 5 years
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $26,000 and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV < 0. b. Project S, since the NPVS > NPVL. c....
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project A -$250 $50 $50 $50 $200 $200 Project B -$600 $300 $300 $70 $70 $70 Which project would you recommend? Select the correct answer. I. Both Projects A and B, since both projects have IRR's > 0. II. Project A, since the NPVA > NPVB. III. Both Projects A and B, since both...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: Project A -$300 $75 $75 $75 $220 $220 Project B -$550 $250 $250 $80 $80 $80 Which project would you recommend? Select the correct answer. I. Both Projects A and B, since both projects have IRR's > 0. II. Project A, since the NPVA > NPVB. III. Project B, since the NPVB > NPVA. IV. Neither A or B, since...
The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows...
The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows are given in the following table. The appropriate discount rate is 11.5% per annum. Years Project X Project Y 0 -$300,000 -$350,000 1 $150,000 $150,000 2 $150,000 $150,000 3 $250,000 $200,000 4 $80,000 $200,000 5 $80,000 $200,000 IRR 42.2% 39.3% Calculate the crossover rate/incremental IRR, at which the NPV profiles for Projects A and B intersect. 2.Which project should be accepted based on your...
The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows...
The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows are given in the following table. The appropriate discount rate is 11.5% per annum. Years Project X Project Y 0 -$300,000 -$350,000 1 $150,000 $150,000 2 $150,000 $150,000 3 $250,000 $200,000 4 $80,000 $200,000 5 $80,000 $200,000 IRR 42.2% 39.3% 1. Calculate the projects’ net present value (NPV). Identify which project should be accepted under the rule of NPV. Explain your answer.       2. What...
Capital Budgeting Question: You are considering two mutually exclusive projects for potential investment. The cash flows...
Capital Budgeting Question: You are considering two mutually exclusive projects for potential investment. The cash flows for the two projects are given. For both projects, the required rate of return is 12%. Year Project A Project B 0 ($40,000) ($40,000) 1 $14,400 $0 2 $14,400 $0 3 $14,400 $0 4 $14,400 $70,000 Find the following: 1. The Net Present Value (NPV) . 2. The Internal Rate of Return (IRR) . 3. Use Excel to draw a graph of the NPV...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT