The following CPM network has estimates of the normal time in weeks listed for the activities:
Activity |
Immediate Pred |
Weeks |
A |
- |
7 |
B |
A |
2 |
C |
A |
4 |
D |
B, C |
5 |
E |
B, C |
2 |
F |
D, E |
4 |
G |
F |
5 |
Activity |
Normal Time |
Crash Time |
Normal Cost |
Crash Cost |
A |
7 |
6 |
$7,000 |
$8,000 |
B |
2 |
1 |
5,000 |
7,000 |
C |
4 |
3 |
9,000 |
10,200 |
D |
5 |
4 |
3,000 |
4,500 |
E |
2 |
1 |
2,000 |
3,000 |
F |
4 |
2 |
4,000 |
7,000 |
G |
5 |
4 |
5,000 |
8,000 |
USE AN EXCEL FILE
Given
activity | required time | cost | time available for crashing= normal duration-crashed duration | cost of crashing per period= (crashing cost-normal cost)/periods available for crashing | ||
normal duration | crashed duration | normal cost | crashing cost | |||
A | 7 | 6 | 7,000 | 8,000 | 1 | $1,000 |
B | 2 | 1 | 5,000 | 7,000 | 1 | $2,000 |
C | 4 | 3 | 9,000 | 10,200 | 1 | $1,200 |
D | 5 | 4 | 3,000 | 4,500 | 1 | $1,500 |
E | 2 | 1 | 2,000 | 3,000 | 1 | $1,000 |
F | 4 | 2 | 4,000 | 7,000 | 2 | $1,500 |
G | 5 | 4 | 5,000 | 8,000 | 1 | $3,000 |
paths
PATH | normal duration |
ABDFG | 28 |
ABEFG | 20 |
ACDFG | 25 |
ACEFG | 22 |
a. Critical path is the longest path: ABDFG
b. duration: 28
c:
Steps for crashing a project | ||
1 | select the critical path and find the process with the least cost of crashing per week | |
2 | If there are multiple critical paths, look for processes that are common, common processes may have low effective cost as common process crashes more than 1 path at once | |
3 | you can only crash an activity depending on the time available for crashing. If an activity is only crashed that much time, choose another activity | |
4 | add the cost of crashing later |
Crashing
PATH | normal duration | crash A by 1 periods | crash D by 1 period |
ABDFG | 28 | 27 | 26 |
ABEFG | 20 | 19 | 19 |
ACDFG | 25 | 24 | 24 |
ACEFG | 22 | 21 | 21 |
No it does not change the critical path.