The following CPM network has estimates of the normal time in weeks listed for the activities:...

The following CPM network has estimates of the normal time in weeks listed for the activities:

Activity

Immediate Pred

Weeks

A

-

7

B

A

2

C

A

4

D

B, C

5

E

B, C

2

F

D, E

4

G

F

5

Activity

Normal

Time

Crash

Time

Normal

Cost

Crash

Cost

A

7

6

$7,000

$8,000

B

2

1

5,000

7,000

C

4

3

9,000

10,200

D

5

4

3,000

4,500

E

2

1

2,000

3,000

F

4

2

4,000

7,000

G

5

4

5,000

8,000

  1. Please identify the critical path.
  2. What is the length of time to complete the project?
  3. Which activities have slack, and how much?
  4. Based on the table of normal and crash times and costs, which activities would you shorten to cut two weeks off the expected completion time? Does this change the critical path—if so, what is(are) the new path(s).

USE AN EXCEL FILE

Solutions

Expert Solution

Given

activity required time cost time available for crashing= normal duration-crashed duration cost of crashing per period= (crashing cost-normal cost)/periods available for crashing
normal duration crashed duration normal cost crashing cost
A 7 6                 7,000               8,000 1 $1,000
B 2 1                 5,000               7,000 1 $2,000
C 4 3                 9,000             10,200 1 $1,200
D 5 4                 3,000               4,500 1 $1,500
E 2 1                 2,000               3,000 1 $1,000
F 4 2                 4,000               7,000 2 $1,500
G 5 4                 5,000               8,000 1 $3,000

paths

PATH normal duration
ABDFG 28
ABEFG 20
ACDFG 25
ACEFG 22

a. Critical path is the longest path: ABDFG

b. duration: 28

c:

Steps for crashing a project
1 select the critical path and find the process with the least cost of crashing per week
2 If there are multiple critical paths, look for processes that are common, common processes may have low effective cost as common process crashes more than 1 path at once
3 you can only crash an activity depending on the time available for crashing. If an activity is only crashed that much time, choose another activity
4 add the cost of crashing later

Crashing

PATH normal duration crash A by 1 periods crash D by 1 period
ABDFG 28 27 26
ABEFG 20 19 19
ACDFG 25 24 24
ACEFG 22 21 21

No it does not change the critical path.


Related Solutions

A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
Use the following project information: Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time...
Use the following project information: Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 2 7 11 none B 2 5 9 A C 4 6 12 A D 5 6 10 B E 6 10 17 C F 3 4 6 D,E G 3 6 10 D,E H 5 7 10 F I 5 8 11 G J 3 3 3 H,I (a) Calculate the expected completion time for this project. (Round...
Q1) Five critical path activities are candidates for crashing on a CPM network. Activity details are...
Q1) Five critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. Activity Normal Time Normal Cost Crash Duration Crash Cost A 14 days $7,000 10 days $9,800 B 10 days $6,000 7 days $8,700 C 6 days $6,800 4 days $7,800 D 8 days $4,500 6 days $6,700 E 5 days $2,500 4 days $3,300 What is the crash cost per unit time for each of the activities? Which activity should...
For the following network determine: a) The activities on the critical path b) The time for...
For the following network determine: a) The activities on the critical path b) The time for the critical path c) The slack for EVERY activity Activity Immediate Predecessors Time A - 5 B - 4 C A,B 3 D A,B 6 E A,B 2 F C,D,E 8 G C,D,E 5
4). Eight maintenance activities, their normal durations in weeks, and the crew sizes for the normal...
4). Eight maintenance activities, their normal durations in weeks, and the crew sizes for the normal condition are as follows: Activity Duration in Weeks Crew size AC 6 8 BC 6 7 BE 2 6 CD 3 2 CE 4 1 DF 7 4 EF 4 6 FG 5 10 Extra crew members can be used to expedite activities BC, CE, DF, and EF at a cost given below: Extra Crew Weeks Saved Crash cost per week 1 1 $100...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A ---...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A --- 3 B --- 4 C A 6 D B 9 E B 6 F C, D 6 G D, E 8 H G, F 9 Draw the network corresponding to the above information. Using a table format, identify the critical path. What is the project completion time?
The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal...
The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal cost Crash cost Possible number of weeks to crash Cost/week to expedite A -- 7 6 $7,000 $8,000 B A 2 1 5,000 7,000 C A 4 3 9,000 10,200 D B,C 5 4 3,000 4,500 E D 2 1 2,000 3,000 F D 4 2 4,000 7,000 G E,F 5 4 5,000 8,000 a)    Draw the AOA (Activity-On-Arc) diagram as shown in...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT