Question

In: Mechanical Engineering

As part of the Project Scope Statement of a house construction project, prepare the detailed Milestone...

As part of the Project Scope Statement of a house construction project, prepare the detailed
Milestone Schedule (Baseline Milestone – Date) by arranging the following activity
items/milestones in a proper sequence from No. 1 to 15, assuming the first milestone date as 05-
01-2020 and the last as 30-09-2020. Assume the dates in between corresponding to the various
milestones which are given in no particular order: Foundation complete, Excavation complete,
Permits approved & construction begins, Contract signed, Design complete, Framing complete,
Roofing complete, Architectural design started, Final inspection and acceptance by Owners,

Interior finish, Exterior finish, Landscaping complete, HVAC system installed, Plumbing-
electrical-mechanical passed, Plumbing-electrical-mechanical installed.

Solutions

Expert Solution

Note: I'm not sure about excavation. It can be 2nd activity as below or 7th activity. Usually, during excavation soil testing, load bearing capacity of site is studied and building is designed accordingly. This step may vary country to country as per regulation. Also, few activities can be done simultaneously.

The very first thing will be contract signing between land owner and architect, engineers, labour contractor etc. Then excavation and land evaluation followed by design by architecture team. The Plumbing, electrical and Mechanical designs must be according to architectural design. If all are satisfied ie passed, design is completed. The next stage should be buoding foundation followed by framing and roofing. Once these are completed, plumbing, electrical and mechanical services must be installed. These services require cutout into walls, floor etc and thus interier and exterior finishing must be done only after satisfactory performance of plumbing, electrical, mechanical and HVAC services. General interior finishing and exterior finishing are done simultaneously. Landscaping is last finishing touch before final inspection and acceptance by owner.

Sr.No. Date Activity
1 5/1/2020 Contract signed
2 6/1/2020 Excavation started
3 10/1/2020 Architecture design started
4 10/2/2020 Plumbing-Electrical-Mechanical passed
5 20/2/2020 Design complete
6 25/2/2020 Permit approved and construction started
7 20/4/2020 Foundation complete
8 20/5/2020 Framing completed
9 20/6/2020 Roofing completed
10 30/6/2020 Plumbing-Electrical-Mechanical installed
11 30/7/2020 HVAC installed
12 30/8/2020 Interior finish
13 15/9/2020 Exterior finish
14 25/9/2020 Landscape complete
15 30/9/2020 Final inspection and acceptance by owner


Note: Please upvote if this helps you. In case of doubts, comment below. Good luck!


Related Solutions

Please provide an example of a Project Scope of a house construction
Please provide an example of a Project Scope of a house construction
Define rework in construction project and milestone in construction project and give example .
Define rework in construction project and milestone in construction project and give example .
Project Scope Statement: The scope statement is the “top-level document for articulating the overall project goals,...
Project Scope Statement: The scope statement is the “top-level document for articulating the overall project goals, objectives, and mission-critical parameters, such as overall timing and resource constraints. It defines the project baseline for all other documentation and management actions.” (Thamhain, 2005, p. 148) The scope of a project defines what is included in and excluded from the project. Based on your project proposal and the information provided in the project charter, submit a list of what will be included in...
In Defining Project(Scope) : 1 -what are Scope statement and Statement of work 2 - explain...
In Defining Project(Scope) : 1 -what are Scope statement and Statement of work 2 - explain what are WBS/OBS 3 - Project Responsibility Matrix ? 4 - what Project Priority Matrix ? 5 - What / how Communication Plan ?
how is the scope statement affected by the complexity of the project?
how is the scope statement affected by the complexity of the project?
Prepare a scope statement for a computer company that will be upgrading PCs. Remember to be...
Prepare a scope statement for a computer company that will be upgrading PCs. Remember to be tangible, measurable, and specific. The components: Project Objective, Deliverables, Milestones, Technical Requirements, Limits and Exclusions. Using info above Post a one-page Project Scope Statement that: Describes the product or service Specifies the acceptance criteria Defines the project deliverables Explains the project exclusions, constraints and assumptions
Changes in project scope might affect the project’s schedule. Discuss this statement. How would a project...
Changes in project scope might affect the project’s schedule. Discuss this statement. How would a project manager formally can inform and communicate such adjustments to project stakeholders? need to state and discuss PM will inform and communicate.
Draft a project scope statement for the TIMS system and describe the constraints. Please be specific....
Draft a project scope statement for the TIMS system and describe the constraints. Please be specific. Use Microsoft Office Word to write your project scope statement. Submit the Microsoft Office Word document in this drop box as an attachment
Why is it important for a project to have a clearly defined scope statement all parties...
Why is it important for a project to have a clearly defined scope statement all parties agree with? What can happen if the project scope is not clearly defined and not agreed to by all parties? Give us examples in which project scope was not clearly defined and explain what could be done differently.
Milestone #2 – Systems Planning: Systems Request Purpose In this milestone, the project has now made...
Milestone #2 – Systems Planning: Systems Request Purpose In this milestone, the project has now made it through the pre-planning phase and you are ready to make a formal request for the new system. In order to formally kick-off the request, you will be working on completing the request for systems services document. This document is the first formal request for the new system. The request is short, but it provides a high-level overview of the need for the system...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT