In: Mechanical Engineering
As part of the Project Scope Statement of a house construction
project, prepare the detailed
Milestone Schedule (Baseline Milestone – Date) by arranging the
following activity
items/milestones in a proper sequence from No. 1 to 15, assuming
the first milestone date as 05-
01-2020 and the last as 30-09-2020. Assume the dates in between
corresponding to the various
milestones which are given in no particular order: Foundation
complete, Excavation complete,
Permits approved & construction begins, Contract signed, Design
complete, Framing complete,
Roofing complete, Architectural design started, Final inspection
and acceptance by Owners,
Interior finish, Exterior finish, Landscaping complete, HVAC
system installed, Plumbing-
electrical-mechanical passed, Plumbing-electrical-mechanical
installed.
Note: I'm not sure about excavation. It can be 2nd activity as
below or 7th activity. Usually, during excavation soil testing,
load bearing capacity of site is studied and building is designed
accordingly. This step may vary country to country as per
regulation. Also, few activities can be done simultaneously.
The very first thing will be contract signing between land owner
and architect, engineers, labour contractor etc. Then excavation
and land evaluation followed by design by architecture team. The
Plumbing, electrical and Mechanical designs must be according to
architectural design. If all are satisfied ie passed, design is
completed. The next stage should be buoding foundation followed by
framing and roofing. Once these are completed, plumbing, electrical
and mechanical services must be installed. These services require
cutout into walls, floor etc and thus interier and exterior
finishing must be done only after satisfactory performance of
plumbing, electrical, mechanical and HVAC services. General
interior finishing and exterior finishing are done simultaneously.
Landscaping is last finishing touch before final inspection and
acceptance by owner.
Sr.No. | Date | Activity |
1 | 5/1/2020 | Contract signed |
2 | 6/1/2020 | Excavation started |
3 | 10/1/2020 | Architecture design started |
4 | 10/2/2020 | Plumbing-Electrical-Mechanical passed |
5 | 20/2/2020 | Design complete |
6 | 25/2/2020 | Permit approved and construction started |
7 | 20/4/2020 | Foundation complete |
8 | 20/5/2020 | Framing completed |
9 | 20/6/2020 | Roofing completed |
10 | 30/6/2020 | Plumbing-Electrical-Mechanical installed |
11 | 30/7/2020 | HVAC installed |
12 | 30/8/2020 | Interior finish |
13 | 15/9/2020 | Exterior finish |
14 | 25/9/2020 | Landscape complete |
15 | 30/9/2020 | Final inspection and acceptance by owner |
Note: Please upvote if this helps you. In case of doubts, comment