Question

In: Civil Engineering

Please provide an example of a Project Scope of a house construction

Please provide an example of a Project Scope of a house construction

Solutions

Expert Solution

  EXAMPLE OF PROJECT SCOPE STATEMENT

PROJECT OBJECTIVE:

To Construct a High- Quality, Custom Home within Duration( Ex 6 months) at cost not to exceed Particular Amount.( $200000).

DELIVERABLES :

  • A 2,200 square foot, 2 bath and 4 Bed Room and 1 kitchen,finished Home.
  • A finished garage insulated and sheetrocked.
  • Kitchen Appliances to include range, oven microwave and dishwater.
  • High- Efficiency gas furnace with Programmable thermostat.

MILESTONES:

  1. Permits approved--- Date ( May 5)
  2. Foundation poured--- Date ( May 14)
  3. Dry in . Farming sheating, plumbing electrical and mechanical inspection passed --- July 25.
  4. Final inspection ---- August 7

TECHNICAL REQUIREMENTS

  1. Home must meet local building codes.
  2. All windows and doors must pass NFRC class 40 energy ratings.
  3. Exterior wall insulation must meet an " A " factor of 21.
  4. Ceiling insulation must meet an " R " factor of 38.
  5. Floor insulation must meet an " R " factor of 25.
  6. Garage will accommodate two large-size cars and one 20-foot Winnebago.
  7. Structure must pass seismic stability codes.

LIMITS AND EXCLUSIONS

  1. The Home will be built to the specifications and design of the original blueprints provided by the customer.
  2. Owner responsible for landscaping.
  3. Refrigerator is not included among kitchen appliances.
  4. Air conditioning is not included but prewiring is included.
  5. Contractor reserves the right to contract out services.
  6. Contractor responsible for subcontracted work.
  7. Site work Daily, 8:00 A.M to 6:00 P.M.

Related Solutions

As part of the Project Scope Statement of a house construction project, prepare the detailed Milestone...
As part of the Project Scope Statement of a house construction project, prepare the detailed Milestone Schedule (Baseline Milestone – Date) by arranging the following activity items/milestones in a proper sequence from No. 1 to 15, assuming the first milestone date as 05- 01-2020 and the last as 30-09-2020. Assume the dates in between corresponding to the various milestones which are given in no particular order: Foundation complete, Excavation complete, Permits approved & construction begins, Contract signed, Design complete, Framing...
Project Management Analytics Exercise This is an example of a construction project. The construction for a...
Project Management Analytics Exercise This is an example of a construction project. The construction for a large corporate building must be started by February 19th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. This implies 315 days or 45 weeks for the expected project duration assuming a seven-day work schedule and no holidays in between! The details of the project activities...
Project Management Analytics Exercise This is an example of a construction project. The construction for a...
Project Management Analytics Exercise This is an example of a construction project. The construction for a large corporate building must be started by February 19th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. This implies 315 days or 45 weeks for the expected project duration assuming a seven-day work schedule and no holidays in between! The details of the project activities...
Define rework in construction project and milestone in construction project and give example .
Define rework in construction project and milestone in construction project and give example .
3. Please provide a case study about a construction project having serious problems because of excessive...
3. Please provide a case study about a construction project having serious problems because of excessive amounts of settlement due to consolidation (14 points). ***Note: Ten (10) bonus points will be given to those who can include a supporting article found for a case study. (A TITLE TO AN ARTICLE THAT COVERS THIS WOULD BE PERFECT! AND MORE THAN ENOUGH)
Draft a project scope statement for the TIMS system and describe the constraints. Please be specific....
Draft a project scope statement for the TIMS system and describe the constraints. Please be specific. Use Microsoft Office Word to write your project scope statement. Submit the Microsoft Office Word document in this drop box as an attachment
Project Scope Statement: The scope statement is the “top-level document for articulating the overall project goals,...
Project Scope Statement: The scope statement is the “top-level document for articulating the overall project goals, objectives, and mission-critical parameters, such as overall timing and resource constraints. It defines the project baseline for all other documentation and management actions.” (Thamhain, 2005, p. 148) The scope of a project defines what is included in and excluded from the project. Based on your project proposal and the information provided in the project charter, submit a list of what will be included in...
Please only provide feedback for this discussion: Please provide a specific example of a company you...
Please only provide feedback for this discussion: Please provide a specific example of a company you know or have read about, and how it has demonstrated social responsibility, and how this has benefited the company. Levi Strauss Co. has an initiative for worker well being. This initiative focuses on improving the life of their employees, and as such enables them to be more productive while at work. They also have a campaign called “Water<Less” in which the company is striving...
The project scope defines and describes what needs to be done during the course of the project. Identify and describe the contents and sections of a project scope document.
The project scope defines and describes what needs to be done during the course of the project. Identify and describe the contents and sections of a project scope document.  
what are the project priorities of a university construction project?? very URGENT please answer asap
what are the project priorities of a university construction project?? very URGENT please answer asap