Question

In: Operations Management

An IT project requires 6 activities. The table below displays the expected time and budgeted cost...

  1. An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity.

Activity

Expected time (weeks)

Budgeted

Cost

Immediate Predecessors

A

3

$3,000

None

B

4

$6,000

None

C

2

$7,000

A

D

5

$9,000

B

E

3

$3,000

C

F

6

$8,000

B,D

Develop a budget for the 15 weeks of the project using ES times.

  1. The following represents a project with four activities. All times are in weeks.

Activity

Immediate

Predecessor

Optimistic

Time

Most

Likely

Time

Pessimistic

Time

A

-

2

8

14

B

-

8

8

8

C

A

6

9

18

D

B

5

11

17

The critical path is BàD. The expected completion time is 19 days.   Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time. What is the probability that the project is finished in 22 weeks or more? (Round to two decimals.)

Solutions

Expert Solution

Problem 1:

Activity

A

B

C

D

E

F

Activity time

3

4

2

5

3

6

Predecessor

-

-

A

B

C

B, D

Activity Cost

3000

6000

7000

9000

3000

8000

Activity Cost per day

1000

1500

3500

1800

1000

1333.333

Earliest Start Time

0

0

3

4

5

9

Period

Cost schedule according to ES time

Total in Period

Cumulative from start

1

1000

1500

2500

2500

2

1000

1500

2500

5000

3

1000

1500

2500

7500

4

1500

3500

5000

12500

5

3500

1800

5300

17800

6

1800

1000

2800

20600

7

1800

1000

2800

23400

8

1800

1000

2800

26200

9

1800

1800

28000

10

1333.33

1333.33

29333.33

11

1333.33

1333.33

30666.67

12

1333.33

1333.33

32000

13

1333.33

1333.33

33333.34

14

1333.33

1333.33

34666.67

15

1333.33

1333.33

36000

Problem 2:

Critical Path: B – D

Critical Path Duration = 19 days

Variance of activity = σ2 = [(p-o)/6]2

Time Variance of B = ((8 -8) / 6)2 = 0

Time Variance of D = ((17 - 5) / 6)2 = 4

Variance of critical path = sum of variance of the critical activities = 0 + 4 = 4

Standard Deviation of Critical Path = σ = √variance = √4 = 2

Expected completion time of project = T = 19 weeks

Desired completion duration of project = X = 22 weeks

Considering the project completion time follows normal distribution,

The z-score for X = 22 is calculated as follows:

z = (X – T)/σ or

z = (22 – 19)/2 = 1.5

From Normal distribution table:

P(z <= 1.5) = [=NORMSDIST(1.5) = 0.9332

Thus, P(X <= 22) = P(z <= 1.5) = 0.9332

There is 93.32% chance that the critical path will finish in 22 weeks.


Related Solutions

The expected times and variances for the project activities are given below. Complete the table showing...
The expected times and variances for the project activities are given below. Complete the table showing which activities are critical. ID Description Predecessor Te Variance Critical? 1 Pilot Production None 6 3 ? 2 Select Channels of Distribution None 20 4 ? 3 Develope Mktg. Program None 18 2 ? 4 Test Market 1 4 2 ? 5 Patent 1 17 5 ? 6 Full production 4 9 10 ? 7 Ad Promotion 3 16 2 ? 8 Release 2,5,6,7...
The table below defines number of working activities needed to accomplish a House project. The relationships...
The table below defines number of working activities needed to accomplish a House project. The relationships or dependencies between predecessors and successors activities are all defined as "finish to start" type. Dependency Duration in days I.D Activity name ................................ 20 A Excavation work A 5 B Plain concrete work A 6 C Reinforced concrete work B & C 2 D Install grass C 10 E Build walls E 8 F Build roof E 7 G Plaster work F & G...
Q1) A project requires an initial investment of $5,000. It is expected that the project will...
Q1) A project requires an initial investment of $5,000. It is expected that the project will last 3 years and generate net cash flows of $3,500 for each of these years. If the discount rate for the project is 10%, the discounted payback period for the project.is: Select one: a. 1.63 years b. 2.55 years c. 1 year d. More than 3 years Q2) Capital rationing refers to the limiting of capital resources to under-performing divisions. Select one: True False...
Suppose that the table below displays the results of a pregnancy test administered to a sample...
Suppose that the table below displays the results of a pregnancy test administered to a sample of 150 females that are either pregnant or not pregnant. Please answer the questions that follow based on the sample taken from a population. Note that every probability is an approximation of the population probabilities. What is the prevalence of pregnancy, i.e., P(S)? What is the probability that a randomly selected individual will be pregnant, i.e., P(Preg)? What is the probability that a randomly...
6. A project with an initial cost of $58,050 is expected to generate annual cash flows...
6. A project with an initial cost of $58,050 is expected to generate annual cash flows of $15,480 for the next 7 years. What is the project's internal rate of return? 9. Rossdale Flowers has a new greenhouse project with an initial cost of $365,000 that is expected to generate cash flows of $48,600 for 10 years and a cash flow of $64,000 in Year 11. If the required return is 8.4 percent, what is the project's NPV?
A 6-year project has expected sales of 2,000 units, ±4 percent. The expected variable cost per...
A 6-year project has expected sales of 2,000 units, ±4 percent. The expected variable cost per unit is $8, and the expected fixed costs are $9,800. The fixed and variable cost estimates are considered accurate within a range of ±2 percent. The sales price is estimated at $22 a unit, ±3 percent. The project requires an initial investment of $42,000 for equipment that will be depreciated straight-line to zero over the project's life. The equipment has a pretax salvage value...
Consider the table below, which includes time and activity data for a Small IT Project. All...
Consider the table below, which includes time and activity data for a Small IT Project. All duration estimates or estimated times are in days. Perform a critical path analysis for this project. Activity Duration (Days) Predecessor A 8 - B 10 A C 18 A D 4 A E 28 B, D F 2 C, E G 32 E H 18 B I 12 F J 2 H, G, I Draw a network diagram representing the project. MS PowerPoint or...
A proposed cost-saving project requires a device with an installed cost of $540,000. The project will...
A proposed cost-saving project requires a device with an installed cost of $540,000. The project will last for five years. The device has a CCA rate of 20%. The required initial net working capital investment is $20,000, the marginal tax rate is 37%, and the required return on the project is 11%. The device has an estimated salvage value of $95,000 at the end of Year 5, and the net working capital investment will also be recovered at the end...
ATT is considering a project. The project requires to purchase an equipment with a cost of...
ATT is considering a project. The project requires to purchase an equipment with a cost of $1.55 million. The equipment will be depreciated straight-line to a zero book value over the 9-year life of the project. At the end of the project it will be sold for a market value of $240,000. The project will not change sales but will reduce operating costs by $399,000 per year. The project also requires an initial investment of $52,000 in net working capital,...
For the project with the five activities given below, you are required to crash the project...
For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily indirect cost of $100, what is the total cost of the project with a duration of 14 days. For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT