Question

In: Finance

Q3- For two mutually exclusive projects, the cash flows are given. If MARR is 10%, which...

Q3- For two mutually exclusive projects, the cash flows are given. If MARR is 10%, which project should we select? please show all steps and all work

N(year)

P1

P2

0

-$3000

-$12000

1

$1350

4200

2

1800

6225

3

1500

6330

Solutions

Expert Solution

The objective of investment is to create money.So, We will select project that has higher Net Present value.
Project P1:
Year Cash flows Discount factor Present value
a b c=1.10^-a d=b*c
0 $       -3,000      1.0000 $   -3,000.00
1 $         1,350      0.9091 $     1,227.27
2 $         1,800      0.8264 $     1,487.60
3 $         1,500      0.7513 $     1,126.97
Net Present value $         841.85
Project P2:
Year Cash flows Discount factor Present value
a b c=1.10^-a d=b*c
0 $     -12,000      1.0000 $ -12,000.00
1 $         4,200      0.9091 $     3,818.18
2 $         6,225      0.8264 $     5,144.63
3 $         6,330      0.7513 $     4,755.82
Net Present value $     1,718.63
So, on the basis of Net Present value, Project P2 should be selected.

Related Solutions

Consider the following two mutually exclusive projects and their Cash Flows ($)
Consider the following two mutually exclusive projects and their Cash Flows ($)Project                                            C0                               C1                               C2                               C3K                                                       –$100                 +$45 +$45 +$60    W                                                     –$150                 +$45 +$45 +$125Which statement is correct based on the above information about Projects K and W?a. If the discount rate is 7.5%, accept project W because the cross-over rate is 9%b. Accept project K, because at a 9% discount rate K and W have the same net present value.c. If the discount rate is 9.5%, reject project K, because the...
Consider the cash flows from two mutually exclusive projects
Use the following information to answer the next three questions. Consider the cash flows from two mutually exclusive projects: Cash FlowYearProject AProject B0-$420,000-$420,0001$140,000$400,0002$230,000$110,0003$331,000$140,000The appropriate discount rate is 8.5%.Calculate the internal rate of return (IRR) for both projects, and determine which project should be accepted based on IRR.
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost...
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost of capital; answer the next 2 questions: year Project A Project B 0 -5000 -1000 1 2500 600 2 2500 600 3 2500 600 1)  Which project should be accepted, if any and why? Project B; it has a higher IRR and PI Neither project should be accepted, they both have negative NPVs Both project should be accepted; they have IRRs greater than the cost...
You are evaluating two mutually exclusive projects. The cash flows for each are:
You are evaluating two mutually exclusive projects.  The cash flows for each are: Project A                      Project B             Year 0               ($60,000)                      ($85,000)             Year 1               $20,000                        $22,000             Year 2               $35,000                        $25,000             Year 3               $20,000                        $30,000             Year 4               $25,000                        $25,000             Year 5                                                   $15,000             Year 6                                                   $10,000             Year 7                                                   $10,000             Year 8                                                   $10,000 Assume that, if needed, each project is repeatable with no change in cash flows.  Your cost of capital is 13%. Using the replacement chain approach, which project would you chose to...
Two mutually exclusive projects have the following forecasted cash flows:
Two mutually exclusive projects have the following forecasted cash flows: Year           A                      B 0                -20,000             -20,000 1                10,000                          0 2                10,000                          0 3                10,000                          0 4                10,000                60,000 Compute the internal rate of return for each project. Compute the NPV for each project if the required rate is 10%. Which project should be accepted, and why?
Part A) Two projects are mutually exclusive if the cash flows of one are unaffected by...
Part A) Two projects are mutually exclusive if the cash flows of one are unaffected by the acceptance of the other, but independent if the cash flows of one can be adversely impacted by the acceptance of the other. True False Part B) Which of the following statements is correct? Capital rationing occurs when a company chooses to fund all positive NPV projects. A company typically sets no limit on the total amount of capital expenditures that it will make...
2) Given the following cash flows for two mutually exclusive projects (S and L), Answer each...
2) Given the following cash flows for two mutually exclusive projects (S and L), Answer each of the following questions.  To receive full credit you must show your work and clearly label your answers. Time               0 1 2 3 4 Project S -1,000 500 400 300 100 Project L -1,000 100 300 400 600 Calculate the IRR for both projects. Calculate the NPV for both projects using 0, 5, 10 and 15 percent discount rates Draw and label the complete NPV...
Jamison is considering two mutually exclusive projects with the following cash flows and the cost of...
Jamison is considering two mutually exclusive projects with the following cash flows and the cost of capital of 10%. Year XX YY 0 -$1,000 -$1,200 1 $800 $700 2 $800 $700 3 $700 a) Based on Annualized NPV, which project would you choose? Why ANPV is better than NPV in this case.?
Consider the following cash flows on two mutually exclusive projects for A- Z motorcars.Assuming both projects...
Consider the following cash flows on two mutually exclusive projects for A- Z motorcars.Assuming both projects require an annual return of 11 percent. year AZM Mini-Suv AFL Full-Suv 0 - 470000 - 820000 1 324000 354000 2 188000 428000 3 154000 294000 A    What is the pay back period for each projects B What is the NPV for each project C What is the IRR for each project Please note Do not do intermediate and run your answers to...
Using the cash flows given in the table below for mutually exclusive projects Alpha and Beta,...
Using the cash flows given in the table below for mutually exclusive projects Alpha and Beta, assist the Chief Financial Officer in finding the breakeven rate (the crossover point or the rate of indifference). Which project do you recommend if using a cost of capital of 9% and Why? YEAR PROJECT ALPHA PROJECT BETA 0 -175 000 -82 500 1 40 000 30 000 2 60 000 10 500 3 85 000 40 000 4 92 000 75 000 5...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT