In: Finance
Consider the following two mutually exclusive projects and their Cash Flows ($)
Project C0 C1 C2 C3
K –$100 +$45 +$45 +$60
W –$150 +$45 +$45 +$125
Which statement is correct based on the above information about Projects K and W?
a. If the discount rate is 7.5%, accept project W because the cross-over rate is 9%
b. Accept project K, because at a 9% discount rate K and W have the same net present value.
c. If the discount rate is 9.5%, reject project K, because the cross-over rate is 9%.
d. If the discount rate is 7.5%, accept project W because the IRR of W is 17%.
e. Accept project K because the IRR of K is larger than the IRR of W.
Given, The Cash Flows Of Project K
CF [email protected]% [email protected]%
Year 0 (100) (100) (100)
Year 1 45 45/1.075 45/1.095
Year 2 45 45/(1.075*1.075) 45/(1.095*1.095)
Year3 60 60/(1.075*1.075*1.075) 60/(1.095*1.095*1.095)
_____________________________________________________________________________
NPV 29.09 24.32
The Cash Flows Of Project W
CF [email protected]% [email protected]%
Year 0 (150) (150) (150)
Year 1 45 45/1.075 45/1.095
Year 2 45 45/(1.075*1.075) 45/(1.095*1.095)
Year3 125 125/(1.075*1.075*1.075) 125/(1.095*1.095*1.095)
_____________________________________________________________________________
NPV 24.32 23.83
Cross over rate
Equating NPV of K & W
NPV of K= NPV of W
45/(1+r)+45(1.r)^2+60/(1+r)^3-100=45/(1+r)+45(1.r)^2+125/(1+r)^3-150
=>r=9.14%
IRR of K
100=45/(1+r)+45(1.r)^2+60/(1+r)^3
r=>22%
IRR of W
150=45/(1+r)+45(1.r)^2+125/(1+r)^3
r=>17%
Therefore, Option (e), i.e Accept project K because the IRR of K is larger than the IRR of W.is correct