In: Finance
Use the following information to answer the next three questions.
Consider the cash flows from two mutually exclusive projects:
Cash Flow
Year | Project A | Project B |
---|---|---|
0 | -$420,000 | -$420,000 |
1 | $140,000 | $400,000 |
2 | $230,000 | $110,000 |
3 | $331,000 | $140,000 |
The appropriate discount rate is 8.5%.
Calculate the internal rate of return (IRR) for both projects, and determine which project should be accepted based on IRR.
Project A
Internal rate of return can be calculated using a financial calculator by inputting the below:
The IRR of the project is 26.20%.
Project B
Internal rate of return can be calculated using a financial calculator by inputting the below:
The IRR of the project is 33.54%.
Project B should be selected since it generates the largest internal rate of return.
In case of any query, kindly comment on the solution.