Question

In: Finance

Two mutually exclusive projects have the following forecasted cash flows:

  1. Two mutually exclusive projects have the following forecasted cash flows:

Year           A                      B

0                -20,000             -20,000

1                10,000                          0

2                10,000                          0

3                10,000                          0

4                10,000                60,000

  1. Compute the internal rate of return for each project.
  1. Compute the NPV for each project if the required rate is 10%.
  1. Which project should be accepted, and why?

Solutions

Expert Solution

Answer:

 


Related Solutions

Two mutually exclusive projects have the following forecasted cash flows: Year   A            B 0        -20,000      &nbsp
Two mutually exclusive projects have the following forecasted cash flows: Year   A            B 0        -20,000          -20,000 1        10,000                       0 2        10,000                       0 3        10,000                       0 4        10,000           60,000 Compute the internal rate of return for each project. Compute the NPV for each project if the required rate is 10%. Which project should be accepted, and why?
Consider the following two mutually exclusive projects and their Cash Flows ($)
Consider the following two mutually exclusive projects and their Cash Flows ($)Project                                            C0                               C1                               C2                               C3K                                                       –$100                 +$45 +$45 +$60    W                                                     –$150                 +$45 +$45 +$125Which statement is correct based on the above information about Projects K and W?a. If the discount rate is 7.5%, accept project W because the cross-over rate is 9%b. Accept project K, because at a 9% discount rate K and W have the same net present value.c. If the discount rate is 9.5%, reject project K, because the...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A Project B Year Cash Flow Cash Flow 0 -$10,000 -$8,000 1 4,000 7,000 2 2,000 3,000 3 6,000 1,000 4 8,000 3,000 At what cost of capital do the two projects have the same net present value? (That is, what is the crossover rate?) Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A Project B 0 -$50,000 -$50,000 1    15,000 0 2    15,000 0 3    15,000 0 4    15,000 0 5    15,000 90,000 1) Calculate NPV of each project if the required rate of return on these projects is 8 percent. 2) which would be chosen and why?
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A Project B Year Cash Flow Cash Flow 0 -$11,000 -$9,000 1 3,500 6,000 2 3,000 4,000 3 5,000 3,000 4 9,000 2,000 At what cost of capital do the two projects have the same net present value? (That is, what is the crossover rate?) Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A Project B Year Cash Flow Cash Flow 0 -$11,000 -$9,000 1 3,500 6,000 2 3,000 4,000 3 5,000 3,000 4 9,000 2,000 At what cost of capital do the two projects have the same net present value? (That is, what is the crossover rate?) Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A Project B Year Cash Flow Cash Flow 0 -$11,000 -$9,000 1 4,500 6,000 2 3,000 4,000 3 5,000 3,000 4 9,000 2,000 At what cost of capital do the two projects have the same net present value? (That is, what is the crossover rate?) Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your...
A company is considering two mutually exclusive projects that have the following cash flows: Year                       Project...
A company is considering two mutually exclusive projects that have the following cash flows: Year                       Project A Cash Flow                      Project B Cash Flow 0                              -$10,000                                             -$8,000 1                                   1000                                                7000 2                                   2000                                                1000             3                                   6000                                                1000 4                                   6000                                                1000 If the company’s required rate of return is 10%, find the project’s NPV, IRR, PI, and payback period. Which project they should invest in?
Consider the cash flows from two mutually exclusive projects
Use the following information to answer the next three questions. Consider the cash flows from two mutually exclusive projects: Cash FlowYearProject AProject B0-$420,000-$420,0001$140,000$400,0002$230,000$110,0003$331,000$140,000The appropriate discount rate is 8.5%.Calculate the internal rate of return (IRR) for both projects, and determine which project should be accepted based on IRR.
Jamison is considering two mutually exclusive projects with the following cash flows and the cost of...
Jamison is considering two mutually exclusive projects with the following cash flows and the cost of capital of 10%. Year XX YY 0 -$1,000 -$1,200 1 $800 $700 2 $800 $700 3 $700 a) Based on Annualized NPV, which project would you choose? Why ANPV is better than NPV in this case.?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT