Question

In: Finance

Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost...

Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost of capital; answer the next 2 questions:

year Project A Project B
0 -5000 -1000
1 2500 600
2 2500 600
3 2500 600

1)  Which project should be accepted, if any and why?

Project B; it has a higher IRR and PI

Neither project should be accepted, they both have negative NPVs

Both project should be accepted; they have IRRs greater than the cost of capital

Project A; it has the higher positive NPV

Not enough information to answer.

Solutions

Expert Solution

A:

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=2500/1.16+2500/1.16^2+2500/1.16^3

=5614.72

NPV=Present value of inflows-Present value of outflows  

=5614.72-5000

=$614.72(Approx)

B:

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=600/1.16+600/1.16^2+600/1.16^3

=1347.53

NPV=Present value of inflows-Present value of outflows  

=1347.53-1000

=$347.53(Approx)

Hence since projects are mutually exclusive;project must be selected having higher NPV as it would lead to higher value addition to the firm(Project A)

Hence the correct option is:

Project A; it has the higher positive NPV


Related Solutions

Jamison is considering two mutually exclusive projects with the following cash flows and the cost of...
Jamison is considering two mutually exclusive projects with the following cash flows and the cost of capital of 10%. Year XX YY 0 -$1,000 -$1,200 1 $800 $700 2 $800 $700 3 $700 a) Based on Annualized NPV, which project would you choose? Why ANPV is better than NPV in this case.?
Consider the following two mutually exclusive projects and their Cash Flows ($)
Consider the following two mutually exclusive projects and their Cash Flows ($)Project                                            C0                               C1                               C2                               C3K                                                       –$100                 +$45 +$45 +$60    W                                                     –$150                 +$45 +$45 +$125Which statement is correct based on the above information about Projects K and W?a. If the discount rate is 7.5%, accept project W because the cross-over rate is 9%b. Accept project K, because at a 9% discount rate K and W have the same net present value.c. If the discount rate is 9.5%, reject project K, because the...
Two mutually exclusive projects have the following forecasted cash flows:
Two mutually exclusive projects have the following forecasted cash flows: Year           A                      B 0                -20,000             -20,000 1                10,000                          0 2                10,000                          0 3                10,000                          0 4                10,000                60,000 Compute the internal rate of return for each project. Compute the NPV for each project if the required rate is 10%. Which project should be accepted, and why?
Empire Manufacturing is considering two mutually exclusive projects with the following cash flows. Empire’s cost of...
Empire Manufacturing is considering two mutually exclusive projects with the following cash flows. Empire’s cost of capital is 10 percent. Year                   Project A               Project B                                     0          (485,000)                     (485,000)                                     1                     0                      155,000                                     2                     0                      152,000                                             3                     0                      131,000                                     4                     0                      110,000                                     5                     0                      108,000                                             6      1,000,000                           98,500 a) Compute the NPV, IRR and Payback Period for each project. Assuming the projects were mutually exclusive: b) If...
Q3- For two mutually exclusive projects, the cash flows are given. If MARR is 10%, which...
Q3- For two mutually exclusive projects, the cash flows are given. If MARR is 10%, which project should we select? please show all steps and all work N(year) P1 P2 0 -$3000 -$12000 1 $1350 4200 2 1800 6225 3 1500 6330
Consider the cash flows from two mutually exclusive projects
Use the following information to answer the next three questions. Consider the cash flows from two mutually exclusive projects: Cash FlowYearProject AProject B0-$420,000-$420,0001$140,000$400,0002$230,000$110,0003$331,000$140,000The appropriate discount rate is 8.5%.Calculate the internal rate of return (IRR) for both projects, and determine which project should be accepted based on IRR.
2) Given the following cash flows for two mutually exclusive projects (S and L), Answer each...
2) Given the following cash flows for two mutually exclusive projects (S and L), Answer each of the following questions.  To receive full credit you must show your work and clearly label your answers. Time               0 1 2 3 4 Project S -1,000 500 400 300 100 Project L -1,000 100 300 400 600 Calculate the IRR for both projects. Calculate the NPV for both projects using 0, 5, 10 and 15 percent discount rates Draw and label the complete NPV...
Two mutually exclusive projects have the following forecasted cash flows: Year   A            B 0        -20,000      &nbsp
Two mutually exclusive projects have the following forecasted cash flows: Year   A            B 0        -20,000          -20,000 1        10,000                       0 2        10,000                       0 3        10,000                       0 4        10,000           60,000 Compute the internal rate of return for each project. Compute the NPV for each project if the required rate is 10%. Which project should be accepted, and why?
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0   –$ 68,000   –$ 83,000 1 48,000 47,000 2 43,000 56,000 3 38,000 59,000 The cash flows of Project A are expressed in real terms, whereas those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 5 percent. Calculate the NPV for each project. (Do not round intermediate calculations and round your answers...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0 $ (200) $ (200) 1 80 100 2 80 100 3 80 100 4 80 Calculate the NPV for both projects if the discount rate is 11%(Do not intermediate calculations.Round your answer to 2 decimal places) Suppose that you can only choose one of the these projects. Which would you choose ? project A Project B Neither
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT