Question

In: Finance

Here are the cash flows for two mutually exclusive projects: Project                 C0              &n

Here are the cash flows for two mutually exclusive projects:

Project                 C0                           C1                           C2                           C3

A                             -20,000                 +8,000                   +8,000                   +8,000

B                             -20,000                 0                              0                              +25,000

              

At what interest rate would you prefer project A to B? (Hint: try drawing a NPV profile.)

                a)            If the discount rate is below 3%.

                b)            If the discount rate is above 3%.

                c)            If the discount rate is above 4%.

                d)            A is never preferred to B at any discount rate.

Which project has the highest IRR?

a.Project A

b. Project B

c. They have equal IRRs.

Solutions

Expert Solution

1: c

2: a

Year A B
0 -20000 -20000
1 8000 0
2 8000 0
3 8000 25000
NPV at 2% 3071.07 3558.06 Select B
NPV at 3.5% $2,413.10 $2,548.57 Select B
NPV at 4.5% $1,991.71 $1,907.42 Select A
IRR 9.70% 7.72% A has higher IRR

Workings


Related Solutions

Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 23,000 +$ 10,120 +$ 10,120 +$ 10,120 B − 23,000 0 0 + 31,050 What is the IRR of each project? (Round your answers to 2 decimal places.)
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 21,800 +$ 9,592 +$ 9,592 +$ 9,592 B − 21,800 0 0 + 29,430 What is the IRR of each project? (Round your answers to 2 decimal places.) PRoject A % Project B %
Consider the following two mutually exclusive projects withtheir expected Cash Flows ($)Project C0 C1...
Consider the following two mutually exclusive projects with their expected Cash Flows ($)Project C0 C1   C2 C3A –$100 +$60 +$60 +$60B –$100 ------ ------ +$208.35What is the cross-over rate for these two projects?a. unknown, because the discount rate is unkownb. 28%c. 36%d. 32%e. 15%
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A -$100 +$60 +$60 +$60 B -$100 ---- ---- +$208.35 Calculate the NPV of each project for a discount rate of 14%. What is approximately the IRR for each project individually? Use the IRR cross-over method to determine which of the projects you should accept (describe the correct decision rule describing when you pick A versus B based on what discount rate).
Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV...
Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 12% A −31,000 21,800 21,800 +$5,843 B −51,000 34,000 34,000 +6,462 a. Calculate IRRs for A and B. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places.)
Here are the cash-flow forecasts for two mutually exclusive projects: Cash Flows (dollars) Year Project A...
Here are the cash-flow forecasts for two mutually exclusive projects: Cash Flows (dollars) Year Project A Project B 0 ? 120 ? 120 1 50 69 2 70 69 3 90 69 a-1. What is the NPV of each project if the opportunity cost of capital is 2%? (Do not round intermediate calculations. Round your answers to 2 decimal places.) b-1. What is the NPV of each project if the opportunity cost of capital is 14%? (Do not round intermediate...
2. Consider the following cash flows on two mutually exclusive projects: The cash flows of project...
2. Consider the following cash flows on two mutually exclusive projects: The cash flows of project A are expressed in real terms while those of Popject B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 4 percent. Which project should you choose? Project A (real cash flow) Project B (nominal cash flow) Year 0            (67,000)                 (74,000) 1             34,000                  34,000 2             37,000                  45,000 3            ...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,200 -7,800 1 1,325 1,325 2 2,148 2,148 3 3,640 7,360 The required return for both projects is 8%. 1. What is the IRR for project A? 2. What is the IRR for project B? 3. Which project seems better according to the IRR method? 4. What is the NPV for project A? 5. What is the NPV for project B?...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,700 -8,550 1 1,325 1,325 2 2,148 2,148 3 4,325 8,384 The required return for both projects is 8%. What is the IRR for project A? What is the IRR for project B? Which project seems better according to the IRR method? Project A Project B What is the NPV for project A? What is the NPV for project B? Which...
Consider the following two mutually exclusive projects and their Cash Flows ($)
Consider the following two mutually exclusive projects and their Cash Flows ($)Project                                            C0                               C1                               C2                               C3K                                                       –$100                 +$45 +$45 +$60    W                                                     –$150                 +$45 +$45 +$125Which statement is correct based on the above information about Projects K and W?a. If the discount rate is 7.5%, accept project W because the cross-over rate is 9%b. Accept project K, because at a 9% discount rate K and W have the same net present value.c. If the discount rate is 9.5%, reject project K, because the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT