Question

In: Accounting

Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $594,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period.

2017
2018
2019
Costs to date $267,300 $463,320 $606,000
Estimated costs to complete 326,700 130,680 –0–
Progress billings to date 268,000 547,000 896,000
Cash collected to date 238,000 497,000

896,000

(a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period. (If answer is 0, please enter 0. Do not leave any fields blank.)

(b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period. (If answer is 0, please enter 0. Do not leave any fields blank.)

please show work!!

Solutions

Expert Solution

a 2017 2018 2019
Contract Price          896,000          896,000          896,000
Less Estimated Cost:
Cost to date          267,300          463,320          606,000
Estimated cost to complete          326,700          130,680                     -  
Estimated total Cost          594,000          594,000          606,000
Estimated total gross profit          302,000          302,000          290,000
Gross profit recognized in-
Cost to date / Estimated total Cost *Estimated total gross profit          135,900          235,560          290,000
Less:Recognised in PY                     -            135,900          235,560
GP to be recognised in CY          135,900            99,660            54,440
b
Total Billing          896,000
Total Cost          606,000
Gross profit to be recognised in 2019          290,000

No Gross profit is recognised in 2017 and 2018


Related Solutions

Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $597,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $908,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $286,560 $453,720 $609,000 Estimated costs to complete 310,440 143,280 –0– Progress billings to date 273,000 548,000 908,000 Cash collected to date...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $595,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $279,650 $487,900 $606,000 Estimated costs to complete 315,350 107,100 –0– Progress billings to date 272,000 545,000 903,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $246,000 $432,000 $612,000 Estimated costs to complete 354,000 168,000 –0– Progress billings to date 270,000 546,000 901,000 Cash collected to date...
A construction company has entered into a contract to build a parking complex. It hsa been...
A construction company has entered into a contract to build a parking complex. It hsa been estimated the complex will cost 700,000 and will take three years to construct. The complex will be billed to the purchasing company at 1,200,000. Information is as follows. X1 YEAR. X2 YEAR X3 YEAR cost incurrect to date 350,000 490,000 700,000 estimated cost yet to be incurrect 350,000. 210,000. 0 customer billings to date 300,000. 650,000 1,200,000 collections of billings to date 250,000. 600,000....
Problem #2 Pedroni Construction Company has entered into a contract beginning January 1, 2107, to build...
Problem #2 Pedroni Construction Company has entered into a contract beginning January 1, 2107, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period. 2017                2018                2019 Costs to date                                    $270,000          $450,000          $610,000 Estimated costs to complete             330,000             150,000               0 Progress billing to date                       270,000             550,000            900,000 Cash...
Problem 18-09 Concord Construction Company has entered into a contract beginning January 1, 2020, to build...
Problem 18-09 Concord Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $891,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $260,580 $466,620 $618,000 Estimated costs to complete 345,420 139,380 –0– Progress billings to date 272,000 551,000 891,000 Cash collected...
At the beginning of 2017, the Mini Construction Company received a contract to build an office...
At the beginning of 2017, the Mini Construction Company received a contract to build an office building for $1.2 million. Mini will construct the building according to specifications provided by the buyer, and the project is estimated to take four years to complete. The cost breakdown is as follows. Determine the amount of revenue and gross profit to be recognized each year. (do not include $ in your answer, round to 4 decimal places). 2017 2018 2019 2020 cost incurred...
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road...
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road for the government. Construction will take 3 years. The following information as of December 31st, 2012 is available for the contract: Total revenue according to contract $15,000 Updated estimated cost in 2013-2014 period $7,200,000 Cost incurred during 2012 $4,800,000 Assume that the company estimates percentage complete based on costs incurred as a percentage of total estimated costs. Under the Percentage-of-Completion method, how much revenue...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT