In: Finance
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road for the government. Construction will take 3 years. The following information as of December 31st, 2012 is available for the contract:
Total revenue according to contract |
$15,000 |
Updated estimated cost in 2013-2014 period |
$7,200,000 |
Cost incurred during 2012 |
$4,800,000 |
Assume that the company estimates percentage complete based on costs incurred as a percentage of total estimated costs. Under the Percentage-of-Completion method, how much revenue will be reported in 2012?
$6,000,000
To find out revenue to be recognised under Percentage of Completion method we will follow the steps shown below
Step 1 : Calculation of Degree of Completion
(Cost Incurred/ Total Cost) * 100
Total Cost = Cost Incurred + Cost Yet to be incurred
Therefore Total Cost = $4,800,000 + $7,200,000
=$12,000,000
Therefore Degree of Completion
=$4,800,000 / $12,000,000
= 40%
Step 2 : Revenue to be Recognised
= Degree of Completion * Total Revenue according to Contract
As per data given in the sum the Revenue to be Reported in 2012 would be
40% of $15,000
= $6000
Thus Revenue of $6000 would be reported as revenue in 2012.
Note : At the end of the sum $6,000,000 is given which might imply that the Total Revenue according to Contract would be $15,000,000 and not $15,000 (might be due to typing error)
Then Revenue to be Recognised as per above Note would be
40% of $15,000,000
= $6,000,000
Revenue of $6,000,000 would be reported as revenue in 2012.