Question

In: Accounting

A construction company has entered into a contract to build a parking complex. It hsa been...

A construction company has entered into a contract to build a parking complex. It hsa been estimated the complex will cost 700,000 and will take three years to construct. The complex will be billed to the purchasing company at 1,200,000. Information is as follows.

X1 YEAR. X2 YEAR X3 YEAR

cost incurrect to date 350,000 490,000 700,000

estimated cost yet to be incurrect 350,000. 210,000. 0

customer billings to date 300,000. 650,000 1,200,000

collections of billings to date 250,000. 600,000. 1,200,000

Prepare all journal entries s they realte to percentage of completion contract.

Solutions

Expert Solution


Related Solutions

Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $594,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $267,300 $463,320 $606,000 Estimated costs to complete 326,700 130,680 –0– Progress billings to date 268,000 547,000 896,000 Cash collected to date...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $597,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $908,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $286,560 $453,720 $609,000 Estimated costs to complete 310,440 143,280 –0– Progress billings to date 273,000 548,000 908,000 Cash collected to date...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $595,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $279,650 $487,900 $606,000 Estimated costs to complete 315,350 107,100 –0– Progress billings to date 272,000 545,000 903,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $246,000 $432,000 $612,000 Estimated costs to complete 354,000 168,000 –0– Progress billings to date 270,000 546,000 901,000 Cash collected to date...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2018, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,990,000, and $2,675,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2018, costs of $2,050,000 were incurred with estimated costs of $4,050,000 yet to be incurred. Billings of $2,550,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,550,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,800,000 and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...