Question

In: Accounting

Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $595,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period.

2020

2021

2022

Costs to date $279,650 $487,900 $606,000
Estimated costs to complete 315,350 107,100 –0–
Progress billings to date 272,000 545,000 903,000
Cash collected to date 242,000 495,000 903,000


(a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period. (If answer is 0, please enter 0. Do not leave any fields blank.)

Gross profit recognized in 2020 $
Gross profit recognized in 2021 $
Gross profit recognized in 2022 $

(b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period. (If answer is 0, please enter 0. Do not leave any fields blank.)

Gross profit recognized in 2020 $
Gross profit recognized in 2021 $
Gross profit recognized in 2022 $

  

Solutions

Expert Solution

(a)

Gross profit recognized in 2020 $                    144,760
Gross profit recognized in 2021 $                    107,800
Gross profit recognized in 2022 $ 44,440

Working:

Percentages of completion
Choose numerator ÷ Choose denominator = % complete to date
Actual costs to date Estimated total costs % complete to date
2020 279650 ÷ 595000 = 47.00%
2021 487900 ÷ 595000 = 82.00%
2022 606000 ÷ 606000 = 100.00%
2020
To date Recognized in prior years Recognized in 2020
Construction revenue 424410 0 424410
Construction expense 279650 0 279650
Gross profit (loss) 144760 0 144760
2021
To date Recognized in prior years Recognized in 2021
Construction revenue 740460 424410 316050
Construction expense 487900 279650 208250
Gross profit (loss) 252560 144760 107800
2022
To date Recognized in prior years Recognized in 2022
Construction revenue 903000 740460 162540
Construction expense 606000 487900 118100
Gross profit (loss) 297000 252560 44440

(b)

Gross profit recognized in 2020 $ 0
Gross profit recognized in 2021 $ 0
Gross profit recognized in 2022 $ 297,000

Under the completed contract method, the entire revenue and gross profit on the project will be recognized only on the completion of the project in 2022. Thus, the entire gross profit of $903000 - $606000 = $297000 is recognized in 2022.


Related Solutions

Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $597,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $908,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $286,560 $453,720 $609,000 Estimated costs to complete 310,440 143,280 –0– Progress billings to date 273,000 548,000 908,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $246,000 $432,000 $612,000 Estimated costs to complete 354,000 168,000 –0– Progress billings to date 270,000 546,000 901,000 Cash collected to date...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $594,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $267,300 $463,320 $606,000 Estimated costs to complete 326,700 130,680 –0– Progress billings to date 268,000 547,000 896,000 Cash collected to date...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Problem 18-09 Concord Construction Company has entered into a contract beginning January 1, 2020, to build...
Problem 18-09 Concord Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $891,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $260,580 $466,620 $618,000 Estimated costs to complete 345,420 139,380 –0– Progress billings to date 272,000 551,000 891,000 Cash collected...
A construction company has entered into a contract to build a parking complex. It hsa been...
A construction company has entered into a contract to build a parking complex. It hsa been estimated the complex will cost 700,000 and will take three years to construct. The complex will be billed to the purchasing company at 1,200,000. Information is as follows. X1 YEAR. X2 YEAR X3 YEAR cost incurrect to date 350,000 490,000 700,000 estimated cost yet to be incurrect 350,000. 210,000. 0 customer billings to date 300,000. 650,000 1,200,000 collections of billings to date 250,000. 600,000....
Problem #2 Pedroni Construction Company has entered into a contract beginning January 1, 2107, to build...
Problem #2 Pedroni Construction Company has entered into a contract beginning January 1, 2107, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period. 2017                2018                2019 Costs to date                                    $270,000          $450,000          $610,000 Estimated costs to complete             330,000             150,000               0 Progress billing to date                       270,000             550,000            900,000 Cash...
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road...
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road for the government. Construction will take 3 years. The following information as of December 31st, 2012 is available for the contract: Total revenue according to contract $15,000 Updated estimated cost in 2013-2014 period $7,200,000 Cost incurred during 2012 $4,800,000 Assume that the company estimates percentage complete based on costs incurred as a percentage of total estimated costs. Under the Percentage-of-Completion method, how much revenue...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2018, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,990,000, and $2,675,000 cash was collected. The project was completed in 2020 after additional costs of...