In: Accounting
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date 240,000 501,000 905,000
Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.
Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period.
2017 |
2018 |
2019 |
|
Gross Profits (Loss) |
$131,580 |
$79,560 |
$84,860 |
Working |
2017 |
2018 |
2019 |
|
A |
Contract Price |
$905,000 |
$905,000 |
$905,000 |
B |
Cost Incurred to Date |
$257,570 |
$413,310 |
$609,000 |
C |
Estimated cost yet to be incurred to complete the contract |
$341,430 |
$185,690 |
$0 |
D = B+C |
Total Cost |
$599,000 |
$599,000 |
$609,000 |
E = (B/D) x 100 |
% of Completion |
43.00% |
69.00% |
100.00% |
F = A x E |
Revenue to date |
$389,150 |
$624,450 |
$905,000 |
G |
Revenue of Previous year |
$0 |
$389,150 |
$624,450 |
H = F - G |
Net Revenue this year |
$389,150 |
$235,300 |
$280,550 |
I (=B) |
Cost to date |
$257,570 |
$413,310 |
$609,000 |
J |
Cost to date of previous year |
$0 |
$257,570 |
$413,310 |
K = I - J |
Net Cost for the year |
$257,570 |
$155,740 |
$195,690 |
L = H - K |
Gross Profits |
$131,580 |
$79,560 |
$84,860 |