Problem #2

Pedroni Construction Company has entered into a contract beginning January 1, 2107, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period.

2017                2018                2019

Costs to date                                    $270,000          $450,000          $610,000

Estimated costs to complete             330,000             150,000               0

Progress billing to date                       270,000             550,000            900,000

Cash collected to date                        240,000             500,000            900,000

Instructions:

  1. Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period
  2. Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period

Solutions

Expert Solution

Solution a:

Computation of % of completion, revenue recognition and Gross Profit - Pedroni Construction Company
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G-A)
2017 $270,000 $270,000 $600,000 45.00% $900,000 $405,000 $405,000 $135,000
2018 $180,000 $450,000 $600,000 75.00% $900,000 $675,000 $270,000 $90,000
2019 $160,000 $610,000 $610,000 100.00% $900,000 $900,000 $225,000 $65,000

Solution b:

Computation of Gross Profit - Revenue on completion - Pedroni Construction Company
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) Contract Price
(D)
Gross Profit
2017 $270,000 $270,000 $600,000 $900,000 $0
2018 $180,000 $450,000 $600,000 $900,000 $0
2019 $160,000 $610,000 $610,000 $900,000 $290,000.00

Related Solutions

Problem 18-09 Concord Construction Company has entered into a contract beginning January 1, 2020, to build...
Problem 18-09 Concord Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $891,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $260,580 $466,620 $618,000 Estimated costs to complete 345,420 139,380 –0– Progress billings to date 272,000 551,000 891,000 Cash collected...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $594,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $267,300 $463,320 $606,000 Estimated costs to complete 326,700 130,680 –0– Progress billings to date 268,000 547,000 896,000 Cash collected to date...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $597,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $908,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $286,560 $453,720 $609,000 Estimated costs to complete 310,440 143,280 –0– Progress billings to date 273,000 548,000 908,000 Cash collected to date...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $595,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $279,650 $487,900 $606,000 Estimated costs to complete 315,350 107,100 –0– Progress billings to date 272,000 545,000 903,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $246,000 $432,000 $612,000 Estimated costs to complete 354,000 168,000 –0– Progress billings to date 270,000 546,000 901,000 Cash collected to date...
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road...
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road for the government. Construction will take 3 years. The following information as of December 31st, 2012 is available for the contract: Total revenue according to contract $15,000 Updated estimated cost in 2013-2014 period $7,200,000 Cost incurred during 2012 $4,800,000 Assume that the company estimates percentage complete based on costs incurred as a percentage of total estimated costs. Under the Percentage-of-Completion method, how much revenue...
Problem 3 An entity entered into a construction contract to build a condo building at a...
Problem 3 An entity entered into a construction contract to build a condo building at a fixed price of $54,000,000. Construction started in 20x0 and ended in 20x3. Data on the contract is as follows (in ‘000’s): 20x0 20x1 20x2 20x3 Costs incurred during the year $ 6500 19500 25000 5800 Estimated costs to complete 38500 26000 6500 - Billings 18000 18000 - 18000 For each of the parts below, prepare the ‘mini’ income statement for the project for each...
A construction company has entered into a contract to build a parking complex. It hsa been...
A construction company has entered into a contract to build a parking complex. It hsa been estimated the complex will cost 700,000 and will take three years to construct. The complex will be billed to the purchasing company at 1,200,000. Information is as follows. X1 YEAR. X2 YEAR X3 YEAR cost incurrect to date 350,000 490,000 700,000 estimated cost yet to be incurrect 350,000. 210,000. 0 customer billings to date 300,000. 650,000 1,200,000 collections of billings to date 250,000. 600,000....
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT