Question

In: Accounting

Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $597,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $908,000. The following data pertain to the construction period.

2020

2021

2022

Costs to date $286,560 $453,720 $609,000
Estimated costs to complete 310,440 143,280 –0–
Progress billings to date 273,000 548,000 908,000
Cash collected to date 243,000 498,000 908,000

(a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.

Gross profit recognized in 2020
Gross profit recognized in 2021

Gross profit recognized in 2022

(b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period

Gross profit recognized in 2020

Gross profit recognized in 2021

Gross profit recognized in 2022

Solutions

Expert Solution

  • Requirement [a]

2020

2021

2022

Gross Profits (Loss)

$           149,280.00

$             87,080.00

$                62,640.00

--Working

Working

2020

2021

2022

A

Contract Price

$           908,000.00

$          908,000.00

$              908,000.00

B

Cost Incurred to Date

$           286,560.00

$          453,720.00

$              609,000.00

C

Estimated cost yet to be incurred to complete the contract

$           310,440.00

$          143,280.00

$                                -  

D = B+C

Total Cost

$           597,000.00

$          597,000.00

$              609,000.00

E = (B/D) x 100

% of Completion

48.00%

76.00%

100.00%

F = A x E

Revenue to date

$           435,840.00

$          690,080.00

$             908,000.00

G

Revenue of Previous year

$                            -  

$          435,840.00

$              690,080.00

H = F - G

Net Revenue this year

$           435,840.00

$          254,240.00

$              217,920.00

I (=B)

Cost to date

$           286,560.00

$          453,720.00

$              609,000.00

J

Cost to date of previous year

$                            -  

$          286,560.00

$              453,720.00

K = I - J

Net Cost for the year

$           286,560.00

$          167,160.00

$              155,280.00

L = H - K

Gross Profits

$           149,280.00

$             87,080.00

$                62,640.00

  • Requirement [b]

Gross Profits in:
2020 = $ 0
2021 = $ 0
2022 = $908000 - $ 609000 = $ 299,000


Related Solutions

Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $595,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $279,650 $487,900 $606,000 Estimated costs to complete 315,350 107,100 –0– Progress billings to date 272,000 545,000 903,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $246,000 $432,000 $612,000 Estimated costs to complete 354,000 168,000 –0– Progress billings to date 270,000 546,000 901,000 Cash collected to date...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $594,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $267,300 $463,320 $606,000 Estimated costs to complete 326,700 130,680 –0– Progress billings to date 268,000 547,000 896,000 Cash collected to date...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Problem 18-09 Concord Construction Company has entered into a contract beginning January 1, 2020, to build...
Problem 18-09 Concord Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $891,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $260,580 $466,620 $618,000 Estimated costs to complete 345,420 139,380 –0– Progress billings to date 272,000 551,000 891,000 Cash collected...
A construction company has entered into a contract to build a parking complex. It hsa been...
A construction company has entered into a contract to build a parking complex. It hsa been estimated the complex will cost 700,000 and will take three years to construct. The complex will be billed to the purchasing company at 1,200,000. Information is as follows. X1 YEAR. X2 YEAR X3 YEAR cost incurrect to date 350,000 490,000 700,000 estimated cost yet to be incurrect 350,000. 210,000. 0 customer billings to date 300,000. 650,000 1,200,000 collections of billings to date 250,000. 600,000....
Problem #2 Pedroni Construction Company has entered into a contract beginning January 1, 2107, to build...
Problem #2 Pedroni Construction Company has entered into a contract beginning January 1, 2107, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period. 2017                2018                2019 Costs to date                                    $270,000          $450,000          $610,000 Estimated costs to complete             330,000             150,000               0 Progress billing to date                       270,000             550,000            900,000 Cash...
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road...
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road for the government. Construction will take 3 years. The following information as of December 31st, 2012 is available for the contract: Total revenue according to contract $15,000 Updated estimated cost in 2013-2014 period $7,200,000 Cost incurred during 2012 $4,800,000 Assume that the company estimates percentage complete based on costs incurred as a percentage of total estimated costs. Under the Percentage-of-Completion method, how much revenue...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2018, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,990,000, and $2,675,000 cash was collected. The project was completed in 2020 after additional costs of...