Question

In: Accounting

In February 2017, Sheridan Construction signed a contract and commenced construction on a parking garage. The...

In February 2017, Sheridan Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.9 million, and was expected to be completed in July 2021 at a total estimated cost of $82.9 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project during the construction process. Sheridan’s year-end was September 30.

By the end of September, 2017, Sheridan had incurred $12,435,000 in costs and had invoiced $10,100,000 in progress billings. $9,100,000 of the progress billings had been collected.

By September 30, 2018, Sheridan had incurred $51,415,000 in total costs and had invoiced $45,200,000 in progress billings, including the progress billings in 2017. Of the total billings, $30,400,000 in total had been collected. Also, Sheridan reviewed its cost estimates on the project, and now believed the parking garage would cost $79.1 million in total to complete.

Prepare all journal entries required for the year ended September 30, 2017. Use Accounts Payable for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

(To record the 2017 cost of construction)

(To record the 2017 progress billings)

(To record the 2017 cash collections)

(To record the 2017 revenue)

(To record the construction expenses)


Prepare all journal entries required for the year ended September 30, 2018. Use Accounts Payable for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

(To record the 2018 cost of construction)

(To record the 2018 progress billings)

(To record the 2018 cash collections)

(To record the 2018 revenue)

(To record the 2018 expenses)

Solutions

Expert Solution

Journal entries for the year ended 30th Sep 2017 assuming Percentage of Completion Method
S No Account Debit Credit
1 Construction in progress account          12,435,000
To Accounts Payable          12,435,000
(Being Cost of construction recorded)
2 Accounts Receivable          10,100,000
To Progress Billings          10,100,000
(Being progress billing recorded)
3 Cash            9,100,000
To Accounts Receivable            9,100,000
(Being cash collections)
4 Construction in progress account            1,200,000
Construction expense account          12,435,000
To Revenue          13,635,000
(Being expense and revenue recorded*)
Notes
*Revenue to be recognized in 2017
Estimated cost A          82,900,000
Cost incurred till Sep 2017 B          12,435,000
% of completion as at 30th Sep 2017 C=B/A 15%
Contract price D          90,900,000
Revenue to be recognized E=C*D          13,635,000
Net income E-B            1,200,000
Journal entries for the year ended 30th Sep 2018 assuming Percentage of Completion Method
1 Construction in progress account*          38,980,000
To Accounts Payable          38,980,000
(Being Cost of construction recorded)
2 Accounts Receivable          35,100,000
To Progress Billings          35,100,000
(Being progress billing recorded)
3 Cash          21,300,000
To Accounts Receivable          21,300,000
(Being cash collections)
4 Construction in progress account****            6,470,000
Construction expense account          38,980,000
To Revenue          45,450,000
(Being expense and revenue recorded*)
Notes:
* Total cost incurred till 2018          51,415,000
Less: Already incurred in 2017          12,435,000
Construction in Progress account for 2018          38,980,000
** Total Progress Billings till 2018          45,200,000
Less: Progress Billings in 2017          10,100,000
Progress billings for 2018          35,100,000
*** Cash collectios till 2018          30,400,000
Less: Collected in 2017            9,100,000
Cash Collection in 2018          21,300,000
**** Revenue to be recognized in 2018
Estimated cost A          79,100,000
Cost incurred till Sep 2018 B          51,415,000
% of completion as at 30th Sep 2017 C=B/A 65%
Contract price D          90,900,000
Revenue to be recognized E=C*D          59,085,000
Less: already recognized in 2017 F          13,635,000
Revenue to be recognized in 2018 G          45,450,000

Related Solutions

In February 2020, Cullumber Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Cullumber Construction signed a contract and commenced construction on a parking garage. The total contract price was $89.4 million and was expected to be completed in July 2024 at a total estimated cost of $82.1 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.8 million and was expected to be completed in July 2024 at a total estimated cost of $83.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project...
n February 2020, Oriole Construction signed a contract and commenced construction on a parking garage. The...
n February 2020, Oriole Construction signed a contract and commenced construction on a parking garage. The total contract price was $91.0 million and was expected to be completed in July 2022 at a total estimated cost of $82.4 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage (i.e. ownership) does not transfer...
Brick Ltd is a building construction company. On 1July 2017, Brick Ltd signed a contract with...
Brick Ltd is a building construction company. On 1July 2017, Brick Ltd signed a contract with Pear Ltd to build a factory. The contract price was $ 12,000,000. The relevant information is as follows: Financial year ending 30 June: Construction costs for year Billings and payments for year 2018 $ 3,500,000 $ 3,000,000 2019 $ 5,000,000 $ 5,000,000 2020 $ 1,500,000 $ 4,000,000 Pear Ltd will be in control of the asset throughout the construction process. The contract is completed...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $594,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $267,300 $463,320 $606,000 Estimated costs to complete 326,700 130,680 –0– Progress billings to date 268,000 547,000 896,000 Cash collected to date...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Sheridan Company is constructing a building. Construction began on February 1 and was completed on December...
Sheridan Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $2,004,000 on March 1, $1,284,000 on June 1, and $3,039,450 on December 31. Compute Sheridan’s weighted-average accumulated expenditures for interest capitalization purposes.
using java and use stack library java Bashemin Parking garage The Bashemin Parking Garage contains a...
using java and use stack library java Bashemin Parking garage The Bashemin Parking Garage contains a single lane that holds up to ten cars. There is only a single entrance/exit to the garage at one end of the lane. If a customer arrives to pick up a car that is not nearest the exit, all cars blocking its path. are moved out, the customer's car is driven out and the other cars are restored in the same order that they...
The parking superintendent is responsible for snow removal at his parking garage. The probabilities for the...
The parking superintendent is responsible for snow removal at his parking garage. The probabilities for the number of days per year requiring snow removal are shown in the chart below. These probabilities are independent from year to year. The superintendent can contract for snow removal at a cost of $500 per day. Alternatively, he can purchase a snow-removal machine for $40,000. It is expected to have a useful life of 10 years and no salvage value at that time. Annual...
A construction company has entered into a contract to build a parking complex. It hsa been...
A construction company has entered into a contract to build a parking complex. It hsa been estimated the complex will cost 700,000 and will take three years to construct. The complex will be billed to the purchasing company at 1,200,000. Information is as follows. X1 YEAR. X2 YEAR X3 YEAR cost incurrect to date 350,000 490,000 700,000 estimated cost yet to be incurrect 350,000. 210,000. 0 customer billings to date 300,000. 650,000 1,200,000 collections of billings to date 250,000. 600,000....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT