Question

In: Accounting

n February 2020, Oriole Construction signed a contract and commenced construction on a parking garage. The...

n February 2020, Oriole Construction signed a contract and commenced construction on a parking garage. The total contract price was $91.0 million and was expected to be completed in July 2022 at a total estimated cost of $82.4 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage (i.e. ownership) does not transfer to the customer until completion. Oriole’s year-end was September 30 and follows ASPE.

By the end of September, 2020, Oriole had incurred $8,240,000 in costs and had invoiced $10,600,000 in progress billings. $8,200,000 of the progress billings had been collected.

By September 30, 2021, Oriole had incurred $43,230,000 in total costs and had invoiced $45,400,000 in progress billings, including the progress billings in 2020. Of the total billings, $30,600,000 in total had been collected. Also, Oriole reviewed its cost estimates on the project, and now believed the parking garage would cost $78.6 million in total to complete.

Using the completed-contract method, prepare all journal entries required for the year ended September 30, 2020. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

No Account title Debit Credit
1
(to record 2020 cost of construction
2
to record the 2020 progress billings
3
to record the 2020 cash collection

Using the completed-contract method, prepare all journal entries required for the year ended September 30, 2021. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

No.

Account Titles and Explanation

Debit

Credit

1.

(To record the 2021 cost of construction)

2.

(To record the 2021 progress billings)

3.

(To record the 2021 cash collections)

Prepare the journal entry to record revenue and cost of construction on completion of the project, assuming all billings are completed and the total actual cost is the same as the 2021 estimate. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

Account Titles and Explanation

Debit

Credit

(To record the 2022 cost of construction)

(To record the 2022 progress billings)

(To record the 2022 cash collections)

(To record revenue, costs and gross profit of construction of parking garage)

Solutions

Expert Solution

In this question, we have to record the journal entries.

Using the completed-contract method, prepare all journal entries required for the year ended September 30, 2020. Use Materials, Cash, Payables for costs incurred to date.

Solution:-

No. Account Titles and Explanation Debit Credit
1. Construction in Process $8,240,000
Materials, Cash, Payable $8,240,000
(To record 2020 cost of construction)
2. Account Receivable $10,600,000
Billings on Construction $10,600,000
(To record the 2020 progress billings)
3. Cash $8,200,000
Account Receivable $8,200,000
(To record the 2020 cash collections)

Using the completed-contract method, prepare all journal entries required for the year ended September 30, 2021. Use Materials, Cash, Payables for costs incurred to date.

Solution:-

No. Account Titles and Explanation Debit Credit
1. Construction in Process ($43,230,000 - $8,240,000) $34,990,000
Materials, Cash, Payable $34,990,000
(To record 2021 cost of construction)
2. Account Receivable ($45,400,000 - $10,600,000) $34,800,000
Billings on Construction $34,800,000
(To record the 2021 progress billings)
3. Cash ($30,600,000 - $8,200,000) $22,400,000
Account Receivable $22,400,000
(To record the 2021 cash collections)

Prepare the journal entry to record revenue and cost of construction on completion of the project, assuming all billings are completed and the total actual cost is the same as the 2021 estimate. Use Materials, Cash, Payables for costs incurred to date.

Solution:-

No. Account Titles and Explanation Debit Credit
1. Construction in Process $35,370,000
Materials, Cash, Payable $35,370,000
($78,600,000 - $34,990,000 - $8,240,000)
(To record 2022 cost of construction)
2. Account Receivable ($45,400,000 - $10,600,000) $45,600,000
Billings on Construction $45,600,000
($91,000,000 - $34,800,000 - $10,600,000)
(To record the 2022 progress billings)
3. Cash ($30,600,000 - $8,200,000) $60,400,000
Account Receivable $60,400,000
($91,000,000 - $22,400,000 - $8,200,000)
(To record the 2022 cash collections)
4. Billings on Construction $91,000,000
Construction in process $78,600,000
Gross profit $12,400,000

Thank you!!

I hope I was able to help you..


Related Solutions

In February 2020, Cullumber Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Cullumber Construction signed a contract and commenced construction on a parking garage. The total contract price was $89.4 million and was expected to be completed in July 2024 at a total estimated cost of $82.1 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.8 million and was expected to be completed in July 2024 at a total estimated cost of $83.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $597,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $908,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $286,560 $453,720 $609,000 Estimated costs to complete 310,440 143,280 –0– Progress billings to date 273,000 548,000 908,000 Cash collected to date...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $595,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $279,650 $487,900 $606,000 Estimated costs to complete 315,350 107,100 –0– Progress billings to date 272,000 545,000 903,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $246,000 $432,000 $612,000 Estimated costs to complete 354,000 168,000 –0– Progress billings to date 270,000 546,000 901,000 Cash collected to date...
A construction company has entered into a contract to build a parking complex. It hsa been...
A construction company has entered into a contract to build a parking complex. It hsa been estimated the complex will cost 700,000 and will take three years to construct. The complex will be billed to the purchasing company at 1,200,000. Information is as follows. X1 YEAR. X2 YEAR X3 YEAR cost incurrect to date 350,000 490,000 700,000 estimated cost yet to be incurrect 350,000. 210,000. 0 customer billings to date 300,000. 650,000 1,200,000 collections of billings to date 250,000. 600,000....
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2018, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,990,000, and $2,675,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2018, costs of $2,050,000 were incurred with estimated costs of $4,050,000 yet to be incurred. Billings of $2,550,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,550,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,800,000 and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT