Question

In: Accounting

In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The...

In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.8 million and was expected to be completed in July 2024 at a total estimated cost of $83.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project during the construction process. Sandhill’s year-end was September 30.

By the end of September, 2020, Sandhill had incurred $20,750,000 in costs and had invoiced $10,400,000 in progress billings. $7,600,000 of the progress billings had been collected.

By September 30, 2021, Sandhill had incurred $40,200,000 in total costs and had invoiced $45,500,000 in progress billings, including the progress billings in 2020. Of the total billings, $30,500,000 in total had been collected. Also, Sandhill reviewed its cost estimates on the project, and now believed the parking garage would cost $80.4 million in total to complete.

Prepare all journal entries required for the year ended September 30, 2020. Use Materials, Cash, Payables for costs incurred to date.

Prepare all journal entries required for the year ended September 30, 2021. Use Materials, Cash, Payables for costs incurred to date.

Solutions

Expert Solution


Related Solutions

In February 2020, Cullumber Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Cullumber Construction signed a contract and commenced construction on a parking garage. The total contract price was $89.4 million and was expected to be completed in July 2024 at a total estimated cost of $82.1 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project...
n February 2020, Oriole Construction signed a contract and commenced construction on a parking garage. The...
n February 2020, Oriole Construction signed a contract and commenced construction on a parking garage. The total contract price was $91.0 million and was expected to be completed in July 2022 at a total estimated cost of $82.4 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage (i.e. ownership) does not transfer...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $424,200 $885,330 $1,060,000 Estimated costs to complete 585,800 207,670 –0– Billings to date 299,000 908,000 1,590,000 Collections to date 273,000 819,000 1,435,000 Part 1 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $597,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $908,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $286,560 $453,720 $609,000 Estimated costs to complete 310,440 143,280 –0– Progress billings to date 273,000 548,000 908,000 Cash collected to date...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $595,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $279,650 $487,900 $606,000 Estimated costs to complete 315,350 107,100 –0– Progress billings to date 272,000 545,000 903,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $246,000 $432,000 $612,000 Estimated costs to complete 354,000 168,000 –0– Progress billings to date 270,000 546,000 901,000 Cash collected to date...
Sandhill Company is constructing a building. Construction beganon February 1 and was completed on December...
Sandhill Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $2,700,000 on March 1, $1,800,000 on June 1, and $4,500,000 on December 31.Sandhill Company borrowed $1,500,000 on March 1 on a 5-year, 10% note to help finance construction of the building. In addition, the company had outstanding all year a 12%, 5-year, $3,000,000 note payable and an 11%, 4-year, $5,250,000 note payable. Compute avoidable interest for Sandhill Company. Use the weighted-average...
The parking superintendent is responsible for snow removal at his parking garage. The probabilities for the...
The parking superintendent is responsible for snow removal at his parking garage. The probabilities for the number of days per year requiring snow removal are shown in the chart below. These probabilities are independent from year to year. The superintendent can contract for snow removal at a cost of $500 per day. Alternatively, he can purchase a snow-removal machine for $40,000. It is expected to have a useful life of 10 years and no salvage value at that time. Annual...
A construction company has entered into a contract to build a parking complex. It hsa been...
A construction company has entered into a contract to build a parking complex. It hsa been estimated the complex will cost 700,000 and will take three years to construct. The complex will be billed to the purchasing company at 1,200,000. Information is as follows. X1 YEAR. X2 YEAR X3 YEAR cost incurrect to date 350,000 490,000 700,000 estimated cost yet to be incurrect 350,000. 210,000. 0 customer billings to date 300,000. 650,000 1,200,000 collections of billings to date 250,000. 600,000....
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT