Question

In: Finance

Brick Ltd is a building construction company. On 1July 2017, Brick Ltd signed a contract with...

Brick Ltd is a building construction company. On 1July 2017, Brick Ltd signed a contract with Pear Ltd to build a factory. The contract price was $ 12,000,000. The relevant information is as follows:

Financial year ending 30 June:

Construction costs for year

Billings and payments for year

2018

$ 3,500,000

$ 3,000,000

2019

$ 5,000,000

$ 5,000,000

2020

$ 1,500,000

$ 4,000,000

Pear Ltd will be in control of the asset throughout the construction process. The contract is completed on 30 June 2020. Brick Ltd has a financial year ending 30 June. Assume that the actual costs and cash collections are in line with expectations and the stage of completion can be reliably estimated.

Required:

  1. Calculate the total profit that will be recognised in the books of Brick Ltd for the year ended 30 June 2018, 2019 and 2020.                                                                                                                   

The profit that you have calculated in Part (a) above, is it based on input method or output method? Justify your answer based on AASB 15 “Revenue from Contracts with Customer

Solutions

Expert Solution

Explaination

Above calculated answer is based on the outflow method. As we consider our cost as outflow. Since we have calculated revenue based on the Percentage of completion ie. as much as contractor is completing the project, Revenue will be recognised in his books of accounts as per AASB 15 “Revenue from Contracts with Customer.


Dear Learner,

"I hope, i've resolved your problem. If you find any issue feel free to comment. Please give it a thumbs up, if your issue get resolved, it motivates me alot."

Thanks


Related Solutions

ABC Construction Co. signed a $2,000,000 contract to construct an office building for the State of...
ABC Construction Co. signed a $2,000,000 contract to construct an office building for the State of Arizona. The project will begin in 2017 and be completed in 2018. The cost of construction is expected to be $1,875,000. Below is a summary of events for 2017 and 2018: 2017 2018 Costs incurred during the year $ 712,500 $1,138,250 Estimated costs to complete 1,037,500 0 Billings during the year 850,000 1,150,000 Cash collections during the year 750,000 1,000,000 ABC Construction Co. recognizes...
Stone Age Construction Pte Ltd entered into a construction contract to build a commercial building for Bintang Ltd for $9,200,000.
Stone Age Construction Pte Ltd entered into a construction contract to build a commercial building for Bintang Ltd for $9,200,000. Construction commenced on 1 January 2021. The following details relate to the construction project as at 31 December 2021:                                                   S'000Progress billing to-date             5,520Cash receipt to-date                  5,120Costs incurred to-date               4,032Estimated total costs                  6,400Stone Age Construction Pte Ltd accounted for the contract using the percentage-of-completion method.Required:(a) For the year ended 2021, calculate the percentage of completion to-date, revenue recognised for the year...
A construction company signed a loan contract at 6.73​%compoundedannually​, with the provision to pay​ $785 at...
A construction company signed a loan contract at 6.73​%compoundedannually​, with the provision to pay​ $785 at the end of each month for three years. ​(a) What is the amount of the​ loan? ​(b) How much will be owed at the end of nineteen ​months? ​(c) How much of the principal will be repaid within the first nineteen ​months? ​(d) How much interest is paid during the first nineteen months
A construction company signed a loan contract at 4.07 % compounded semi-annually , with the provision...
A construction company signed a loan contract at 4.07 % compounded semi-annually , with the provision to pay $665 at the end of each month for three years. (a) What is amount of the loan? (b) How much will be owed at the end of seventeen months? (c) How much of the principal will be repaid within the first seventeen months? (d) How much interest is paid during the first seventeen months?
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office building for $40,000,000. The scheduled construction costs follow. Year Cost 2016 $9,000,000 2017 15,000,000 2018 6,000,000 Total $30,000,000 The building is completed in 2018. For each year, compute the revenue, expense, and gross profit reported for this construction project using each of the following methods. a. Percentage-of-completion method 2016 2017 2018 Revenue Answer Answer Answer Expense Answer Answer Answer Gross Profit Answer Answer Answer...
Waterway Construction Company began work on a $417,400 construction contract in 2017. During 2017, Waterway incurred...
Waterway Construction Company began work on a $417,400 construction contract in 2017. During 2017, Waterway incurred costs of $280,300, billed its customer for $216,200, and collected $176,500. At December 31, 2017, the estimated additional costs to complete the project total $162,000. Prepare Waterway’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.
Swifty Construction Company began work on a $416,400 construction contract in 2017. During 2017, Swifty incurred...
Swifty Construction Company began work on a $416,400 construction contract in 2017. During 2017, Swifty incurred costs of $277,100, billed its customer for $215,200, and collected $173,900. At December 31, 2017, the estimated additional costs to complete the project total $161,000. Prepare Swifty’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
In February 2020, Cullumber Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Cullumber Construction signed a contract and commenced construction on a parking garage. The total contract price was $89.4 million and was expected to be completed in July 2024 at a total estimated cost of $82.1 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.8 million and was expected to be completed in July 2024 at a total estimated cost of $83.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project...
n February 2020, Oriole Construction signed a contract and commenced construction on a parking garage. The...
n February 2020, Oriole Construction signed a contract and commenced construction on a parking garage. The total contract price was $91.0 million and was expected to be completed in July 2022 at a total estimated cost of $82.4 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage (i.e. ownership) does not transfer...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT