Question

In: Accounting

In February 2020, Cullumber Construction signed a contract and commenced construction on a parking garage. The...

In February 2020, Cullumber Construction signed a contract and commenced construction on a parking garage. The total contract price was $89.4 million and was expected to be completed in July 2024 at a total estimated cost of $82.1 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project during the construction process. Cullumber’s year-end was September 30.
By the end of September, 2020, Cullumber had incurred $20,525,000 in costs and had invoiced $10,000,000 in progress billings. $7,700,000 of the progress billings had been collected.

By September 30, 2021, Cullumber had incurred $35,190,000 in total costs and had invoiced $45,900,000 in progress billings, including the progress billings in 2020. Of the total billings, $30,700,000 in total had been collected. Also, Cullumber reviewed its cost estimates on the project, and now believed the parking garage would cost $78.2 million in total to complete.

Prepare all journal entries required for the year ended September 30, 2020. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

No.

Account Titles and Explanation

Debit

Credit

1.

(To record the 2020 cost of construction)

2.

(To record the 2020 progress billings)

3.

(To record the 2020 cash collections)

4.

(To record the 2020 revenue)

5.

(To record the construction expenses)

Prepare all journal entries required for the year ended September 30, 2021. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

No

Account Titles and Explanation

Debit

Credit

1.

(To record the 2021 cost of construction)

2.

(To record the 2021 progress billings)

3.

(To record the 2021 cash collections)

4.

(To record the 2021 revenue)

5.

(To record the 2021 expenses)

Solutions

Expert Solution


Related Solutions

In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.8 million and was expected to be completed in July 2024 at a total estimated cost of $83.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project...
n February 2020, Oriole Construction signed a contract and commenced construction on a parking garage. The...
n February 2020, Oriole Construction signed a contract and commenced construction on a parking garage. The total contract price was $91.0 million and was expected to be completed in July 2022 at a total estimated cost of $82.4 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage (i.e. ownership) does not transfer...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred costs of $250,000, billed its customer for $200,000, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $178,890. Prepare Cullumber’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $597,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $908,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $286,560 $453,720 $609,000 Estimated costs to complete 310,440 143,280 –0– Progress billings to date 273,000 548,000 908,000 Cash collected to date...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $595,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $279,650 $487,900 $606,000 Estimated costs to complete 315,350 107,100 –0– Progress billings to date 272,000 545,000 903,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $246,000 $432,000 $612,000 Estimated costs to complete 354,000 168,000 –0– Progress billings to date 270,000 546,000 901,000 Cash collected to date...
Cullumber Construction enters into a contract with a customer to build a warehouse for $1070000 on...
Cullumber Construction enters into a contract with a customer to build a warehouse for $1070000 on March 30, 2021 with a performance bonus of $40000 if the building is completed by July 31, 2021. The bonus is reduced by $8000 each week that completion is delayed. Cullumber commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2021 70% August 7, 2021 20% August 14, 2021 5%...
Cullumber Construction enters into a contract with a customer to build a warehouse for $1070000 on...
Cullumber Construction enters into a contract with a customer to build a warehouse for $1070000 on March 30, 2021 with a performance bonus of $40000 if the building is completed by July 31, 2021. The bonus is reduced by $8000 each week that completion is delayed. Cullumber commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2021 70% August 7, 2021 20% August 14, 2021 5%...
Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a...
Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a non-cancellable contract #E2-D2, which provided for a contract price of $2,178,000. Other details follow: 2020 2021 Costs incurred during the year $706,640 $1,422,000 Estimated costs to complete, as at December 31 899,360 0 Billings during the year (non-refundable) 420,000 1,713,600 Collections during the year 352,000 1,481,000 How much revenue should be recognized in 2020 and in 2021? 2020 2021 Revenue to be recognized $enter...
The parking superintendent is responsible for snow removal at his parking garage. The probabilities for the...
The parking superintendent is responsible for snow removal at his parking garage. The probabilities for the number of days per year requiring snow removal are shown in the chart below. These probabilities are independent from year to year. The superintendent can contract for snow removal at a cost of $500 per day. Alternatively, he can purchase a snow-removal machine for $40,000. It is expected to have a useful life of 10 years and no salvage value at that time. Annual...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT