In: Accounting
In February 2020, Cullumber Construction signed a contract and
commenced construction on a parking garage. The total contract
price was $89.4 million and was expected to be completed in July
2024 at a total estimated cost of $82.1 million. Payment by the
customer was to be made in several stages, based on significant
events and dates throughout the construction timeline. The customer
was to have control over the parking garage and was able to make
major changes to the project during the construction process.
Cullumber’s year-end was September 30.
By the end of September, 2020, Cullumber had incurred $20,525,000
in costs and had invoiced $10,000,000 in progress billings.
$7,700,000 of the progress billings had been collected.
By September 30, 2021, Cullumber had incurred $35,190,000 in total costs and had invoiced $45,900,000 in progress billings, including the progress billings in 2020. Of the total billings, $30,700,000 in total had been collected. Also, Cullumber reviewed its cost estimates on the project, and now believed the parking garage would cost $78.2 million in total to complete.
Prepare all journal entries required for the year ended
September 30, 2020. Use Materials, Cash, Payables for costs
incurred to date. (Credit account titles are
automatically indented when the amount is entered. Do not indent
manually. If no entry is required, select "No Entry" for the
account titles and enter 0 for the
amounts.)
No. |
Account Titles and Explanation |
Debit |
Credit |
1. |
|||
(To record the 2020 cost of construction) |
|||
2. |
|||
(To record the 2020 progress billings) |
|||
3. |
|||
(To record the 2020 cash collections) |
|||
4. |
|||
(To record the 2020 revenue) |
|||
5. |
|||
(To record the construction expenses) |
Prepare all journal entries required for the year ended
September 30, 2021. Use Materials, Cash, Payables for costs
incurred to date. (Credit account titles are
automatically indented when the amount is entered. Do not indent
manually. If no entry is required, select "No Entry" for the
account titles and enter 0 for the
amounts.)
No |
Account Titles and Explanation |
Debit |
Credit |
1. |
|||
(To record the 2021 cost of construction) |
|||
2. |
|||
(To record the 2021 progress billings) |
|||
3. |
|||
(To record the 2021 cash collections) |
|||
4. |
|||
(To record the 2021 revenue) |
|||
5. |
|||
(To record the 2021 expenses) |