Question

In: Operations Management

A project manager has compiled a list of major activities that will be required to install...

A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.
Use standard deviation table.

Activity Immediate
Predecessor
Estimated Times
(weeks)
A 2-4-6
D A 6-8-10
E D 7-9-12
H E 2-3-5
F A 3-4-8
G F 5-7-9
B 2-2-3
I B 2-3-6
J I 3-4-5
K J 4-5-8
C 5-8-12
M C 1-1-1
N M 6-7-11
O N 8-9-13
End H, G, K, O   

  
If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus. (Round Mean, Standard Deviation, z-value to 2 decimal places and Probability to 4 decimal places.)

Path Mean Std. Dev.
a-d-e-h
a-f-g
b-i-j-k
c-m-n-o

  
Probability ($1,000)   

Probability ($500)            

Solutions

Expert Solution

We find the expected time and Standard Deviation for each activity as shown below;

Path A-D-E-H:

Expected duration = 4 + 8 + 9.17 + 3.17 = 24.34

Mean Standard Deviation = = = 1.35

Path A-F-G:

Expected duration = 4 + 4.50 + 7 = 15.5

Mean Standard Deviation = = = 1.26

Path B-I-J-K:

Expected duration = 2.17 + 3.33 + 4 + 5.33 = 14.83

Mean Standard Deviation = = = 1.01

Path C-M-N-O:

Expected duration = 8.17 + 1.00 + 7.50 + 9.50 = 26.17

Mean Standard Deviation = = = 1.66

As seen from above, path C-M-N-O are critical. Duration = 26.17 weeks Standard Deviation = 1.66

Hence, we find Z value in comparison to this path as :

For 26 weeks:

Z = = = (-0.102)

For Z = (-0.102), Probability = 0.45220= 45.22%

Probability ($1,000) = 45.22%

For 27 weeks:

Z = = = 0.5

For Z = 0.5, Probability = 0.6915 = 69.15%

Probability ($5,000) = 69.15%

-----------------------------------------------------------------------------------------------------------------------

In case of any doubt, please ask through the comment section before Upvote/downvote.


Related Solutions

For this assignment, create a Project Schedule, and list the 20+ activities required to complete the...
For this assignment, create a Project Schedule, and list the 20+ activities required to complete the house that you identified in your Unit IV Project Budget. Assign a schedule to all identified activities. Please be sure to reserve two weeks for contingencies. In other words, you should schedule all the activities and set aside two weeks for contingencies. The entire project (including the two-week contingency period) should equal 24 months Unit 4 Project: Activity Description Est $ Architectural Design 50,000...
List and describe any five activities performed by the project manager during project planning.
List and describe any five activities performed by the project manager during project planning.
Scenario 2: You are the project manager of a project to install stone fireplaces at an...
Scenario 2: You are the project manager of a project to install stone fireplaces at an new condo development. A total of 24 fireplaces are planned to be installed over a 4-month period. The total budget for the project is $144,000. The project is at the end of the 1st month and 5 fireplaces have been installed and $28,000 has been spent. What is the project’s PV? What is the project’s EV? What is the project’s AC? What is Cost...
A project manager, in preparation for the construction of roads, has identified the activities and their...
A project manager, in preparation for the construction of roads, has identified the activities and their durations to prepare a difficult stretch of motorway (as in the following table). Activity Duration (days) Preceding activities A 5 – B 10 – C 1 – D 8 B E 10 B F 9 B G 3 A, D H 7 A, D J 3 F K 8 E, H L 4 C, J How long the project will take?    State the...
A construction project has indirect costs totaling $40,000 per week. Major activities of the project, their...
A construction project has indirect costs totaling $40,000 per week. Major activities of the project, their expected time, and crashing costs per week are: Crashing costs ($000) Activity Expected time (week) Predecessor First week Second week Third week A 5 - 18 22 - B 4 - 12 24 26 C 3 - 10 15 25 D 8 A 24 25 25 E 12 B - - - F 12 C 8 13 - G 6 B 3 10 12...
You are the Project Manager for a major software development project.
a.You are the Project Manager for a major software development project. You are concerned that one of the project constraints is going unbalanced, but the project sponsor is unable to understand your concern since he is not familiar with the concept of project constraints. How would you explain this concept and its significance in project success, to the project sponsor? You can use the Iron Triangle to illustrate the concept.b. Saudi Railways has announced a project to add a new...
For the project with the five activities given below, you are required to crash the project...
For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily indirect cost of $100, what is the total cost of the project with a duration of 14 days. For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily...
Gordon Rivers, the City Manager of Saratoga, Florida and Jay Andrews, the project manager for Major...
Gordon Rivers, the City Manager of Saratoga, Florida and Jay Andrews, the project manager for Major Design Corporation (MDC), must manage this project. ?We need the ?intake and transmission main? designed, bid, and completed in 35 weeks. The City of Saratoga has a future $2 million dollar federal grantriding on the project getting done on time,? Mr. Rivers said. Jay nodded in agreement. Mr. Rivers continued by saying, ?Jay, the project needs to come in on-schedule and within the budget....
The following table contains information related to the major activities of a research project. Use the...
The following table contains information related to the major activities of a research project. Use the information to do the following: a. Compute the expected duration, variance, and standard deviation for each activity b. What is the probability that the project finishes in less than 60 days? Activity Predecessor To Tm Tp A - 3 7 12 B A 8 11 17 C B 7 13 16 D B 7 10 13 E C 14 17 23 F D 12...
Problem # 10. NPV: A project costs 3,000 to install will provide to install will provide...
Problem # 10. NPV: A project costs 3,000 to install will provide to install will provide annual cash flows of 800 for each of the next 6 years. A. What is the NPV if the discount rate is 10% B. How high can the discount rate be before you would reject the project? How to do in excel also
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT