Question

In: Operations Management

Gordon Rivers, the City Manager of Saratoga, Florida and Jay Andrews, the project manager for Major...

Gordon Rivers, the City Manager of Saratoga, Florida and Jay Andrews, the project manager for Major Design Corporation (MDC), must manage this project. ?We need the ?intake and transmission main? designed, bid, and completed in 35 weeks. The City of Saratoga has a future $2 million dollar federal grantriding on the project getting done on time,? Mr. Rivers said. Jay nodded in agreement. Mr. Rivers continued by saying, ?Jay, the project needs to come in on-schedule and within the budget. Now take this schedule back and figure out how we are going to do it.? Notice that the case does not provide how long the current project takes (which is 40 weeks). Therefore, the student needs to do a basic CPM analysis and compute the total normal costs, critical path, activity slacks, and current project completion time. Then they must crash the project from 40 to 35 weeks and eventually two paths become critical and require the crashing of both CPs.

Project Description

The objective of the project is to design a fully functional surface water intake that is protective of the environment, will last at least 30 years, and will have a low life cycle cost (i.e. capital, maintenance, and energy consumption). For this type of project, engineering design accounts for 20 percent of total project cost. The design stage is also important because the decisions made during design lock in 80 percent or more of the life cycle costs of the project. The case describes each project activity and provides the data below.

Alternative Water Supply (AWS) ? Single Project

Activity ID

Description

Precedence

Regular Time (weeks)

Crash Time (weeks)

Normal Cost Estimate

Crash Cost Estimate

A

Conceptual Design

none

4

3

$30,000

$33,500

B

Preliminary Design

A

12

10

$52,000

$58,000

C

Final Design

B

19

16

$59,000

$76,000

D

Environmental Permit Application Preparation

B

8

5

$48,000

$58,200

E

Environmental Permit Review and Approval

D

4

4

$38,000

$38,000

F

Building Permit Application Preparation

E

2

1

$35,000

$38,000

G

Building Permit Review and Approval

F

4

4

$6,000

$6,000

H

Property Acquisition

B

20

18

$90,000

$115,000

I

Bid Project

C, H

4

4

$6,000

$6,000

J

Construction Start (Dummy Activity)

G, I

0

0

$0

$0

Decisions and Analysis

Jay manages about a half dozen engineering projects at any one time so he asks you to analyze this project for ways to complete the project in 35 weeks. Jay would like to meet with you tomorrow to discuss the results of your analysis. To organize your analysis you outline the following steps.

1.) What are your final recommendations?

Solutions

Expert Solution

We can arrange the data in the following form and calculate the total normal cost along with additional cost requirement to crash the particilar activity.

the solution will be as follows:


Related Solutions

Alternative Water Supply Gordon Rivers, the city manager of Saratoga, Florida, pitched the proposed design schedule...
Alternative Water Supply Gordon Rivers, the city manager of Saratoga, Florida, pitched the proposed design schedule back at Jay Andrews. Jay Andrews is the Project Manager for Major Design Corporation (MDC). The city of Saratoga selected MDC for this project. As project manager, it is Jay’s responsibility to assemble the technical team necessary to complete the project, develop and track the budget, establish and maintain the schedule, allocate resources as required, and manage the project until completion. “We need the...
You are the Project Manager for a major software development project.
a.You are the Project Manager for a major software development project. You are concerned that one of the project constraints is going unbalanced, but the project sponsor is unable to understand your concern since he is not familiar with the concept of project constraints. How would you explain this concept and its significance in project success, to the project sponsor? You can use the Iron Triangle to illustrate the concept.b. Saudi Railways has announced a project to add a new...
1. Houston as a major metropolitan city, as a business development manager for Diakin, explain why...
1. Houston as a major metropolitan city, as a business development manager for Diakin, explain why and when does manufacturing become concentrated in a few regions, leaving others relatively undeveloped? 2. Explain the effects of manufacturing become concentrated in a few regions o the land rent and office bid rent?
Project Description: Roger Harding, the manager of Thunder City Bookstore, wants to improve the appearance of...
Project Description: Roger Harding, the manager of Thunder City Bookstore, wants to improve the appearance of the workbook created to review the store inventory. Roger has a workbook started with the inventory, backorder, and documentation sheets already created. This project will require you to use your Excel skills to improve Roger's workbook. Some of the actions needed include copying the promotions worksheet from the marketing director's workbook and pasting it into Roger's workbook, enhancing the appearance of the worksheets by applying...
Case Six   Power/Influence    You have just been hired as the project manager on a major project...
Case Six   Power/Influence    You have just been hired as the project manager on a major project that is critical to the company’s success.  Eight people from different functional specialties have been assigned to your project team.  About forty percent of their time will be devoted to the project.  They take their direction from you with respect to the project but are not under your direct authority as they continue to do other work and continue to report to their current manager.   Question: Describe...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT