Question

In: Operations Management

The following table contains information related to the major activities of a research project. Use the...

The following table contains information related to the major activities of a research project. Use the information to do the following:

a. Compute the expected duration, variance, and standard deviation for each activity

b. What is the probability that the project finishes in less than 60 days?

Activity

Predecessor

To

Tm

Tp

A

-

3

7

12

B

A

8

11

17

C

B

7

13

16

D

B

7

10

13

E

C

14

17

23

F

D

12

16

19

G

E, F

5

7

9

Solutions

Expert Solution

Expected time = (To + 4*Tm + Tp)/6

Variance = (Tp-To)^2/36

Standard deviation = sqrt(Variance)

Activity To Tm Tp Expected Time Variance Standard deviation
A 3 7 12 7.17 2.25 1.50
B 8 11 17 11.50 2.25 1.50
C 7 13 16 12.50 2.25 1.50
D 7 10 13 10.00 1.00 1.00
E 14 17 23 17.50 2.25 1.50
F 12 16 19 15.83 1.36 1.17
G 5 7 9 7.00 0.44 0.67

Probability to complete in less than 60 days will be product of probability of two path to complete the project in 60 days

z value = (Estimated time - Expected time)/Standard deviation

Estimated time = 60

z value for path ABCEG = (60 - 55.67)/3.07 = 1.41

Probability for z value 1.41 is 0.9207

z value for path ABDFG = (60 - 51.50)/2.70 = 3.14

Probability for z value 3.14 is 0.9992

Probability for project = 0.9207*0.9992 = 0.9200


Related Solutions

The following table contains information on matched sample values whose differences are normally distributed. Use Table...
The following table contains information on matched sample values whose differences are normally distributed. Use Table 2. Number Sample 1 Sample 2 1          19        22        2          12        11        3          22        21        4          20        22        5          18        20        6          14        19        7          18        19        8          16        20        a. Construct the 95% confidence interval for the mean difference μD. (Negative values should be indicated by a minus sign. Round all intermediate calculations to at...
Use the information in the table above for the following 5 questions. A capital investment project...
Use the information in the table above for the following 5 questions. A capital investment project is estimated to have the following after-tax cash flows, by year: 0 1 2 3 4 -$30,000 $7,500 $12,500 $5,000 $15,000 The company utilizes a discount rate of 10% to evaluate capital projects. You may have rounding errors in your calculations so choose the closest answer.  Assume cash flows occur evenly over the year.    The PAYBACK for the project shown above is: 2.16 3.33 3.15...
Use the information in the table below for the following 5 questions. A capital investment project...
Use the information in the table below for the following 5 questions. A capital investment project is estimated to have the following after-tax cash flows, by year: 0 1 2 3 4 -$50,000 $15,000 $17,500 $17,500 $25,000 The company utilizes a discount rate of 20% to evaluate capital projects. You may have rounding errors in your calculations so choose the closest answer. Assume cash flows are received equally over the year. The NET PRESENT VALUE for the project shown above...
The following table contains projected cash flows for two mutually exclusive projects. Use the information for...
The following table contains projected cash flows for two mutually exclusive projects. Use the information for questions Part A-Part B. Year Project A Project B 0 -55000 -55000 1 10000 7500 2 9000 7500 3 8000 7500 4 8000 7500 5 7500 8000 6 7500 9000 7 7500 9000 8 7500 10000 Part A. Calculate NPVs for both project and for various interest rates. Annual Interest Rates NPVA NPVB Which Project is preferred 4.22% 3.59% 2.51% Part B. Calculate IRRs...
Research project: The impact of information technology on the revenue cycle activities, threats, and controls Search...
Research project: The impact of information technology on the revenue cycle activities, threats, and controls Search popular business and technology magazines (BusinessWeek, Forbes, Fortune, CIO, etc.) to find an article about innovative use of IT that can be used to improve one or more activities in the revenue cycle. Write a report that: A. Explains how IT can be used to change revenue cycle activities. B. Discusses the control implications. Refer to table 12.1(page 357) and explain how the new...
The table below contains economic cost information for aperfect competitor. Use it to answer the...
The table below contains economic cost information for a perfect competitor. Use it to answer the questions that follow. Q, ATC, AVC, and MC = quantity, average total cost, average variable cost, and marginal cost.QATCAVCMC10100.0080.00101195.4577.27501293.3376.67701392.3176.92801491.7977.50851591.6778.33901691.8879.38951792.3580.591001893.0681.941051993.9583.421102095.2585.25120What quantity maximizes profit when price = $101?Q = __What is the maximum profit when price = $101?Maximum profit = ___Would the maximum profit increase, decrease, or remain constant in the long run?The maximum profit would ____________________.Why?Would the firm produce output or shut down in the...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
Which of the following, if any, correctly describes the research activities credit? a.         The research activities...
Which of the following, if any, correctly describes the research activities credit? a.         The research activities credit is the greater of the incremental research credit, the basic research credit, or the energy research credit. b.         If the full research activities credit is claimed for a taxable year, the research and experimentation expenditures on which that credit is computed will not be fully deductible in that year. c.         The credit is not available for research conducted in Puerto Rico. d.         Personal...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT