Question

In: Operations Management

A project manager, in preparation for the construction of roads, has identified the activities and their...

A project manager, in preparation for the construction of roads, has identified the activities and their durations to prepare a difficult stretch of motorway (as in the following table).

Activity

Duration (days)

Preceding activities

A

5

B

10

C

1

D

8

B

E

10

B

F

9

B

G

3

A, D

H

7

A, D

J

3

F

K

8

E, H

L

4

C, J

  1. How long the project will take?   
  2. State the critical activities.   
  3. If activity A is delayed for 10 days, what is the effect on the project duration?   

Solutions

Expert Solution

Project network

Formula

a. Project duration = Duration of critical path = sum of duration of critical activities (i.e whose skack is 0) = 33 days

b. Critical activities = B,D,H,K

c. There won't be any change in project duration as activity A has slack of 13 days


Related Solutions

Roads Ltd is a construction company that builds roads and related civil projects. The company recently...
Roads Ltd is a construction company that builds roads and related civil projects. The company recently faced increased calls from investors to pay dividends due to the perceived lack of new profitable projects in a low growth economy. The company has, in spite of weak business sentiment, maintained a stable profit margin. At a recent meeting, the board resolved to adopt a residual approach to dividend payments. You have been tasked with recommending the dividend that should be paid at...
Compare a Healthcare project you’ve identified or worked on that was limited mostly by activities with...
Compare a Healthcare project you’ve identified or worked on that was limited mostly by activities with another Healthcare project that was limited mostly by resources. Which did you find more challenging? Why? Please answer this question with at least 300 words and add references.
In a soil investigation for a construction project, two soil types were identified with the following...
In a soil investigation for a construction project, two soil types were identified with the following parameters (g = 9.81 m/s2): Soil Type Depth below ground level (m) Unit weights (kN/m3) Other parameters Soil 1 (sand) 6.5 g = 17 and gsat = 17.5 E =15000 kN/m2 Soil 2 (overconsolidated clay) 11.5 gsat = 20 e0=0.69, Cc=0.25, Cs=0.05 If the ground water level is at 2.5 m below the ground level, and the initial void ratio of the overconsolidated clay...
There is a new amusement park under construction in town and the manager of the project...
There is a new amusement park under construction in town and the manager of the project has hired you to design a "Zero-Gravity" room. (a) Based on your knowledge of nature of electric charge and electric forces, how will you design such a facility? Comment on components of the room, and explain how it will work for walk in customers? What would be the safety concerns and measures? (b) Assume that your design has been approved and facility has been...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
List and describe any five activities performed by the project manager during project planning.
List and describe any five activities performed by the project manager during project planning.
PERCENTAGE OF COMPLETION METHOD AttiK Construction Company currently has a long-term construction project. The project has...
PERCENTAGE OF COMPLETION METHOD AttiK Construction Company currently has a long-term construction project. The project has a contract price of $130,000,000 with total estimated costs of $100,000,000. AttiK appropriately uses the percentage of completion method. After 2 years of construction, the following costs have been accumulated: Actual cost incurred, Year 1 $30,000,000 Total estimated costs remaining after Year 1 70,000,000 Actual cost incurred, Year 2 50,000,000 Total estimated cost remaining after Year 2 20,000,000 Determine the gross profit for each...
Assignment title: Construction Project Planning Develop the List of Activities, encode, and describe them, of a...
Assignment title: Construction Project Planning Develop the List of Activities, encode, and describe them, of a Warehouse project
You are the project manager responsible for a new building construction in northern Virginia. The building...
You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections and...
Scenario: You are the project manager responsible for a new building construction in northern Virginia. The...
Scenario: You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT