Question

In: Operations Management

A construction project has indirect costs totaling $40,000 per week. Major activities of the project, their...

A construction project has indirect costs totaling $40,000 per week. Major activities of the project, their expected time, and crashing costs per week are:

Crashing costs ($000)

Activity

Expected time (week)

Predecessor

First week

Second week

Third week

A

5

-

18

22

-

B

4

-

12

24

26

C

3

-

10

15

25

D

8

A

24

25

25

E

12

B

-

-

-

F

12

C

8

13

-

G

6

B

3

10

12

H

7

D

30

30

35

I

4

H

15

20

-

J

5

E

40

40

40

K

9

G

2

7

10

L

9

F

5

12

-

M

8

L

14

15

-

N

1

K,M

26

-

-

P

11

I,J

30

33

36

What would be your recommended lowest cost duration for this project? Show your work. For each step specify what activity is crashed and show why.

Solutions

Expert Solution

SOLUTION:

Network Diagram:

Possible Paths:

Start-A-D-H-I-P-End = 35 weeks .... Critical Path

Start-B-E-J-P-End = 32 weeks

Start-B-G-K-N-End = 20 weeks

Start-C-F-L-M-N-End = 33 weeks

The critical path is Start-A-D-H-I-P-End with duration 35 weeks.

Total Indirect Cost = 35 * 40000 = $1,400,000

Crashing:

Below table shows the activities to be crashed weekwise, and the total resulting project cost.

- Activity with lowest crash cost shoud be considered for crashing. In case of multiple critical paths, activities with lowest cost on each of these critical path should be crashed.

1 2 3 4
Crashed Activity I A I,L A,F,B
Crashing Cost 15000 18000 25000 42000
Total Crashing Cost 15000 33000 58000 100000
Indirect cost/week 40000 40000 40000 40000
Critical Path A-D-H-I-P A-D-H-I-P
C-F-L-M-N
A-D-H-I-P
C-F-L-M-N
A-D-H-I-P
B-E-J-P
C-F-L-M-N
TPT 34 33 32 31

Total Project Cost

(TPT * Indirect cost/week + Total Crashing Cost)

1375000 1353000 1338000 1340000

From the above table, we observe post the 3rd crashing, the total project cost is increasing.

Thus, the lowest cost duration is 32 weeks, and the resulting project cost is $1338000


Related Solutions

A project manager, in preparation for the construction of roads, has identified the activities and their...
A project manager, in preparation for the construction of roads, has identified the activities and their durations to prepare a difficult stretch of motorway (as in the following table). Activity Duration (days) Preceding activities A 5 – B 10 – C 1 – D 8 B E 10 B F 9 B G 3 A, D H 7 A, D J 3 F K 8 E, H L 4 C, J How long the project will take?    State the...
Metal Industries has monthly fixed costs totaling $90,000 and variable costs of $5 per unit. Each...
Metal Industries has monthly fixed costs totaling $90,000 and variable costs of $5 per unit. Each unit of product is sold for $20. Assume the company expects to sell 11,850 units of product this coming month. What is the margin of safety in units? Group of answer choices 8,850 6,600 5,850 7,350 Photos Inc. produces two different products with the following monthly data for June: Digital Camera Cameras Cases Total Selling price per unit $300 $100 Variable cost per unit...
WITH PROCESS: A construction project has the following data: initial disbursement $ 40,000. The required rate...
WITH PROCESS: A construction project has the following data: initial disbursement $ 40,000. The required rate of return is 9% per year. Net cash income for the following years: 1st. Year $ 8,000 = 2nd. Year $ 10,500 = 3rd. Year $ 19,000 = 4th. Year $ 18,800 = 5th. Year $ 18,800 = Net Present Value _____________ Determine the payback present value _______ PREPA is offering a $ 45 Bonus, payable semi-annually, for the next 20 years. The prevailing...
A project manager has compiled a list of major activities that will be required to install...
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships. Use standard deviation table. Activity Immediate Predecessor Estimated Times (weeks) A — 2-4-6 D A 6-8-10 E D 7-9-12 H E 2-3-5 F A 3-4-8 G F 5-7-9 B — 2-2-3 I B 2-3-6 J I 3-4-5 K J 4-5-8 C — 5-8-12 M C 1-1-1...
Project L costs $40,000, its expected cash inflows are $9,000 per year for 8 years, and...
Project L costs $40,000, its expected cash inflows are $9,000 per year for 8 years, and its WACC is 11%. What is the project's discounted payback? Round your answer to two decimal places.
Project L costs $40,000, its expected cash inflows are $9,000 per year for 8 years, and...
Project L costs $40,000, its expected cash inflows are $9,000 per year for 8 years, and its WACC is 11%. What is the project's discounted payback? Round your answer to two decimal places. years
Project L costs $40,000, its expected cash inflows are $10,000 per year for 10 years, and...
Project L costs $40,000, its expected cash inflows are $10,000 per year for 10 years, and its WACC is 10%. What is the project's payback? Round your answer to two decimal places.
NPV Project K costs $40,000, its expected cash inflows are $13,000 per year for 12 years,...
NPV Project K costs $40,000, its expected cash inflows are $13,000 per year for 12 years, and its WACC is 11%. What is the project's NPV? Round your answer to the nearest cent. $   
A value stream has three activities and two products. The units produced and shipped per week...
A value stream has three activities and two products. The units produced and shipped per week are 50 of the deluxe model (Model A) and 150 of the basic model (Model B). The resource consumption patterns are shown as follows: Model A Model B Costs of Value- Stream Activities Cell manufacturing 2,380 min. 7,140 min. $ 57,120 Engineering 65 hrs. 234 hrs. 26,013 Testing 95 hrs. 247 hrs. 27,360    Total $ 110,493 Required: 1. Calculate the ABC product cost for...
A project has an initial cost of $40,000, expected net cash inflows of $9,000 per year...
A project has an initial cost of $40,000, expected net cash inflows of $9,000 per year for 7 years, and a cost of capital of 11%. What is the project’s NPV? (Hint: Begin by constructing a time line.) (10-2) Refer to Problem 10-1. What is the project’s IRR? (10-3) Refer to Problem 10-1. What is the project’s MIRR? (10-4) Refer to Problem 10-1. What is the project’s PI? (10-5) Refer to Problem 10-1. What is the project’s payback period? (10-6)...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT