In: Operations Management
For this assignment, create a Project Schedule, and list the 20+ activities required to complete the house that you identified in your Unit IV Project Budget. Assign a schedule to all identified activities. Please be sure to reserve two weeks for contingencies. In other words, you should schedule all the activities and set aside two weeks for contingencies. The entire project (including the two-week contingency period) should equal 24 months Unit 4 Project: |
|
Activity Description | Est $ |
Architectural Design | 50,000 |
Procurement of machinery | 60,000 |
Hiring Labor | 120,000 |
Interior Design | 15,000 |
Windows and Doors | 20,000 |
HVAC | 40,000 |
Framing | 130,000 |
Lumber | 80,000 |
Drywall | 45,000 |
Interior Decorator and Decorations | 20,000 |
Work and Environmental Permits | 25,000 |
Landscaping | 30,000 |
Scaffolding Rental | 25,000 |
Paint and Wood Finishing | 40,000 |
Plumbing | 30,000 |
Electrical | 30,000 |
Lighting Fixtures | 20,000 |
Site Security | 20,000 |
Roofing | 40,000 |
Flooring | 30,000 |
Exterior Rock | 50,000 |
Plumbing Fixtures | 20,000 |
Cabinetry | 40,000 |
Concrete | 80,000 |
Material Storage | 10,000 |
Cost of Construction | 1,070,000 |
Contingency (2%) | 20,400 |
Total | 1,090,400 |
Activity Description | Start Date | End Date | Days to complete | Est $ |
Architectural Design | 01-05-2018 | 15-05-2018 | 14 | 50,000 |
Procurement of machinery | 15-05-2018 | 30-05-2018 | 15 | 60,000 |
Hiring Labor | 31-05-2018 | 10-06-2018 | 10 | 1,20,000 |
Interior Design | 11-06-2018 | 26-07-2018 | 45 | 15,000 |
Windows and Doors | 25-07-2018 | 23-09-2018 | 60 | 20,000 |
HVAC | 20-09-2018 | 30-10-2018 | 40 | 40,000 |
Framing | 31-10-2018 | 28-02-2019 | 120 | 1,30,000 |
Lumber | 10-02-2019 | 12-03-2019 | 30 | 80,000 |
Drywall | 15-03-2019 | 29-04-2019 | 45 | 45,000 |
Interior Decorator and Decorations | 30-04-2019 | 29-07-2019 | 90 | 20,000 |
Work and Environmental Permits | 16-05-2018 | 26-05-2018 | 10 | 25,000 |
Landscaping | 20-05-2018 | 27-05-2018 | 7 | 30,000 |
Scaffolding Rental | 30-07-2019 | 06-08-2019 | 7 | 25,000 |
Paint and Wood Finishing | 06-08-2019 | 20-10-2019 | 75 | 40,000 |
Plumbing | 15-10-2019 | 14-11-2019 | 30 | 30,000 |
Electrical | 10-11-2019 | 10-12-2019 | 30 | 30,000 |
Lighting Fixtures | 01-12-2019 | 16-12-2019 | 15 | 20,000 |
Site Security | 15-12-2019 | 25-12-2019 | 10 | 20,000 |
Roofing | 26-12-2019 | 09-02-2020 | 45 | 40,000 |
Flooring | 10-02-2020 | 25-02-2020 | 15 | 30,000 |
Exterior Rock | 05-02-2020 | 20-02-2020 | 15 | 50,000 |
Plumbing Fixtures | 20-02-2020 | 27-02-2020 | 7 | 20,000 |
Cabinetry | 25-02-2020 | 06-03-2020 | 10 | 40,000 |
Concrete | 05-03-2020 | 20-03-2020 | 15 | 80,000 |
Material Storage | 21-03-2020 | 15-04-2020 | 25 | 10,000 |
Cost of Construction | 10,70,000 | |||
Contingency (2%) | 16-04-2020 | 30-04-2020 | 14 | 20,400 |
Total Below is the PROJECT SCHEDULE Project Start Date-1-05-2018 Project End Date-30-4-2018 The overall time of completion (24 months) includes the contingency time (2 weeks) as well |
10,90,400 |