Question

In: Operations Management

For this assignment, create a Project Schedule, and list the 20+ activities required to complete the...

For this assignment, create a Project Schedule, and list the 20+ activities required to complete the house that you identified in your Unit IV Project Budget. Assign a schedule to all identified activities. Please be sure to reserve two weeks for contingencies. In other words, you should schedule all the activities and set aside two weeks for contingencies. The entire project (including the two-week contingency period) should equal 24 months

Unit 4 Project:

Activity Description Est $
Architectural Design 50,000
Procurement of machinery 60,000
Hiring Labor 120,000
Interior Design 15,000
Windows and Doors 20,000
HVAC 40,000
Framing 130,000
Lumber 80,000
Drywall 45,000
Interior Decorator and Decorations 20,000
Work and Environmental Permits 25,000
Landscaping 30,000
Scaffolding Rental 25,000
Paint and Wood Finishing 40,000
Plumbing 30,000
Electrical 30,000
Lighting Fixtures 20,000
Site Security 20,000
Roofing 40,000
Flooring 30,000
Exterior Rock 50,000
Plumbing Fixtures 20,000
Cabinetry 40,000
Concrete 80,000
Material Storage 10,000
Cost of Construction 1,070,000
Contingency (2%) 20,400
Total 1,090,400

Solutions

Expert Solution

Activity Description Start Date End Date Days to complete Est $
Architectural Design 01-05-2018 15-05-2018 14 50,000
Procurement of machinery 15-05-2018 30-05-2018 15 60,000
Hiring Labor 31-05-2018 10-06-2018 10 1,20,000
Interior Design 11-06-2018 26-07-2018 45 15,000
Windows and Doors 25-07-2018 23-09-2018 60 20,000
HVAC 20-09-2018 30-10-2018 40 40,000
Framing 31-10-2018 28-02-2019 120 1,30,000
Lumber 10-02-2019 12-03-2019 30 80,000
Drywall 15-03-2019 29-04-2019 45 45,000
Interior Decorator and Decorations 30-04-2019 29-07-2019 90 20,000
Work and Environmental Permits 16-05-2018 26-05-2018 10 25,000
Landscaping 20-05-2018 27-05-2018 7 30,000
Scaffolding Rental 30-07-2019 06-08-2019 7 25,000
Paint and Wood Finishing 06-08-2019 20-10-2019 75 40,000
Plumbing 15-10-2019 14-11-2019 30 30,000
Electrical 10-11-2019 10-12-2019 30 30,000
Lighting Fixtures 01-12-2019 16-12-2019 15 20,000
Site Security 15-12-2019 25-12-2019 10 20,000
Roofing 26-12-2019 09-02-2020 45 40,000
Flooring 10-02-2020 25-02-2020 15 30,000
Exterior Rock 05-02-2020 20-02-2020 15 50,000
Plumbing Fixtures 20-02-2020 27-02-2020 7 20,000
Cabinetry 25-02-2020 06-03-2020 10 40,000
Concrete 05-03-2020 20-03-2020 15 80,000
Material Storage 21-03-2020 15-04-2020 25 10,000
Cost of Construction 10,70,000
Contingency (2%) 16-04-2020 30-04-2020 14 20,400

Total

Below is the PROJECT SCHEDULE

Project Start Date-1-05-2018

Project End Date-30-4-2018

The overall time of completion (24 months) includes the contingency time (2 weeks) as well

10,90,400

Related Solutions

For the case study above, create a PERT schedule with the key activities for the $20...
For the case study above, create a PERT schedule with the key activities for the $20 million contract negotiation project. There should be between to activities identified from the case study. Additional relevant activities may be included. Create an AON network diagram and find the critical path using slack once estimated activity time is established.
Assignment title: Construction Project Planning Develop the List of Activities, encode, and describe them, of a...
Assignment title: Construction Project Planning Develop the List of Activities, encode, and describe them, of a Warehouse project
Assignment: The Ordered List In this assignment, you will create an ordered list of movies. The...
Assignment: The Ordered List In this assignment, you will create an ordered list of movies. The list will always be maintained in sorted order (ascending order, by movie title) by assuring that all new movies are inserted in the correct location in the list. Create a new project to hold your implementation of an ordered singly-linked list. You will need a main.cppto use as a test driver, as well as header and implementation files as described below. Movie To represent...
In this assignment, you will create a schedule for the month of December of this year...
In this assignment, you will create a schedule for the month of December of this year for your team members—John, Sally, Pedro, and Eunice. While creating the schedule, keep in mind the following conditions: Every employee in the company needs to work for 45 hours per week. John works from Saturdays to Wednesdays in the 6:00 a.m. to 4:00 p.m. shift, with a 1-hour lunch break. Sally works from Mondays to Thursdays in the 3:00 p.m. to 3:00 a.m. shift,...
For the project with the five activities given below, you are required to crash the project...
For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily indirect cost of $100, what is the total cost of the project with a duration of 14 days. For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily...
Create a project schedule based on task dependencies and resource constraints
Create a project schedule based on task dependencies and resource constraints
In this assignment, you will be required to use the Heart Rate Dataset to complete the...
In this assignment, you will be required to use the Heart Rate Dataset to complete the following: Identify the types of data represented by variables The range or types of values for each variable Give a brief written description of the variables, and how they are used in the data set. Steps Open the Heart Rate Dataset in Excel Identify each of the variables contained in the dataset by type Identify the type of data each variable represents (e.g., qualitative...
Create an Amortization Schedule for a home that cost $259,000 with 20% down for a down-payment....
Create an Amortization Schedule for a home that cost $259,000 with 20% down for a down-payment. Do not use an online amortization schedule. Note the textbook amortization schedule is using an annual payment. Please complete a schedule for both 180 months (15 years) and 360 months (30 years). The interest rate for the year is 2.75% according to Bankrate for the area the home is in. Remember to divide your interest by 12 to get a monthly rate. How much...
Corporate Tax Return Required: Complete Alvin’s Music Inc.’s (AMI) 2019 Form 1120, Schedule D, and Schedule...
Corporate Tax Return Required: Complete Alvin’s Music Inc.’s (AMI) 2019 Form 1120, Schedule D, and Schedule G (if applicable) using the information provided below. Neither Form 4562 for depreciation nor Form 4797 for the sale of the equipment is required. Include the amount of tax depreciation and the tax gain on the equipment sale given in the problem (or determined from information given in the problem) on the appropriate lines on the first page of Form 1120. If any information...
/* Assignment : Complete this javascript file according instructions in comments. */ // 1) Create a...
/* Assignment : Complete this javascript file according instructions in comments. */ // 1) Create a for loop that loops through its code block 10 times // In the first statement, set the variable i equal to zero // In the second statement, tell the loop to execute while i is less than ten // In the third statement, increment i by one each time the loop executes // In the code block of the loop, print the variable i...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT