Question

In: Operations Management

Using the following information, create a network diagram. Calculate the total duration (days) of the project,...

  1. Using the following information, create a network diagram. Calculate the total duration (days) of the project, its early start, early finish, late start, and late finish times, and the slack for each activity. Finally, identify the project’s critical path. (4 pts.)

Activity

Duration

Predecessors

ES

EF

LS

LF

Free Slack

Total Slack

A

15

--

B

6

A

C

12

--

D

15

B, C

E

12

A

F

9

E

G

17

C, D, E

H

10

E, F

I

13

C, G

J

3

G, H

K

12

J, I

Now, assume that activity E has taken 10 days past its anticipated duration to complete. What happens to the project’s schedule? Has the duration changed? Is there a new critical path?

Solutions

Expert Solution

step 1 find early start, and early finish from the start of the project for each activity
step 2 Find Maximum EF and keep it as the LF of last activities. Max of EF's is 78
step 3 calculate LS for each activity after calculating its EF
Activity Duration, D Early start, ES=Max of early finish of preceding activities Early finish, EF = ES + D Late finish, LF= Min of LS of successor activities Late start, LS= LF - D Total slack= LF-EF Critical activity, activities with 0 slack time Free slack= Min(ES of Successor)- ES -Duration
A 15 0 15 15 0 0 Yes 0
B 6 15 21 21 15 0 Yes 0
C 12 0 12 21 9 9 No 9
D 15 21 36 36 21 0 Yes 0
E 12 15 27 36 24 9 No 0
F 9 27 36 53 44 17 No 0
G 17 36 53 53 36 0 Yes 0
H 10 36 46 63 53 17 No 7
I 13 53 66 66 53 0 Yes 0
J 3 53 56 66 63 10 No 10
K 12 66 78 78 66 0 Yes 0

Project duration is 78,

Critical path with 0 slack is A-B-D-G-I-K

If E takes 10 days more

Activity Duration, D Early start, ES=Max of early finish of preceding activities Early finish, EF = ES + D Late finish, LF= Min of LS of successor activities Late start, LS= LF - D Total slack= LF-EF Critical activity, activities with 0 slack time
A 15 0 15 15 0 0 Yes
B 6 15 21 22 16 1 No
C 12 0 12 22 10 10 No
D 15 21 36 37 22 1 No
E 12+10= 22 15 37 37 15 0 Yes
F 9 27 36 54 45 18 No
G 17 37 54 54 37 0 Yes
H 10 36 46 64 54 18 No
I 13 54 67 67 54 0 Yes
J 3 54 57 67 64 10 No
K 12 67 79 79 67 0 Yes

Project duration is 79,

NEW Critical path with 0 slack is A-E-G-I-K


Related Solutions

1. Create a network diagram and project schedule (illustrated in a Gantt chart) from the following...
1. Create a network diagram and project schedule (illustrated in a Gantt chart) from the following set of tasks. Use the task number, duration, and dependencies of each task given and construct a schedule so that the project is completed in the least number of days possible. Include a management reserve of approximately 10%. Task Subject Duration Dependencies Slack (3 pts) 1.0 Project Kickoff 2 none 2.1 Install & Test Database Software 2 1.0 2.2 Configure & Test Database Web...
Create a diagram of a Small/Medium size Business network Using Computer Network Defense and Defense in...
Create a diagram of a Small/Medium size Business network Using Computer Network Defense and Defense in Depth, Define what a secure network should look like on a modest budget. (Describe your diagram and why you placed your appliances where you chose to place them).
By using the WBS for contruscting a house, students will create a Network Diagram and Critical...
By using the WBS for contruscting a house, students will create a Network Diagram and Critical Path Analysis for the project. A network diagram is essentially a flow chart that includes all of the project elements and how they relate to one another. It depicts the sequence of activities in the project and also shows parallel activities and the links between each activity (PMBOK Guide). When outlined on a network diagram, the critical path is the longest path through the...
Consider the following network of a project consisting of 7 activities with a scheduled project duration...
Consider the following network of a project consisting of 7 activities with a scheduled project duration of 36 weeks. Direct cost $12,000 with 36 weeks Indirect cost of $ 150 per week and delay damages of $ 500 per week for project duration beyond 30 weeks, and no incentive plan. the following table of time-cost data. Suppose the project should be completed in 30 weeks, what is the total project cost? Activity Predecessor. Normal Time (weeks) Crash Time (weeks) Normal...
Use the following activities and their three duration estimates (in days) to do the following Calculate...
Use the following activities and their three duration estimates (in days) to do the following Calculate the probability that the project will take at least 19 days - use 2 decimals when determining the duration determining the duration Path Activity Optimistic Most Likely Pessimistic a-b-c A 4 5 6 B 7 8 10 C 3 5 9 d-e-f D 7 8 11 E 2 3 4 f 1 4 6
Assume a project information is given in the table below: Activity Immediate Processor Duration (Days) A...
Assume a project information is given in the table below: Activity Immediate Processor Duration (Days) A --- 5 B --- 5 C --- 5 D A, B 4 E B 3 F C 8 G D, E 6 What is the minimum number of activities that have to be delayed for the project to get delayed? 1 2 3 4 5 None of the above (What is your answer?) What is the minimum number of non-critical activities that have to...
Create a network diagram (graphical diagram) that shows thesequence and dependent relationships identified in the...
Create a network diagram (graphical diagram) that shows the sequence and dependent relationships identified in the Astin Martin project activity list and activity duration schedule.Provide a project objective associated with the Astin Martin Graphics project. Include a list of assumptions about the project. What is a work breakdown structure? What is a responsibility matrix? Using the Astin Martin project activity list and activity duration schedule, create a WBS and RAM.STATEMENT OF WORK SUMMARY  RFP awarded for specific web services which will...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
A project is represented by the activity duration (in days, estimated at 90% likelihood of completion)...
A project is represented by the activity duration (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many feeder buffers are needed if this project is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length A -- 18 E C, D 13 B -- 16 F C 9 C A 22 G E, F 15 D B 14 ​ ​ ​ Options: 0 1 2 3
Draw the schedule network diagram using Precedence Diagramming Method (PDM) and calculate Earliest Start (ES), Earliest...
Draw the schedule network diagram using Precedence Diagramming Method (PDM) and calculate Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), and Latest Finish (LF) for each activity. Activity Predecessor Duration A 2 B 3 C 3 D A 3 E D 3 F E 4 G F 3 H F 5 I G, H 6 J G 3 K H 4 L I, K 4 M J 2
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT