Questions
Explain why electrical, mechanical, and plumbing rough-in usually begins before framing is complete.

Explain why electrical, mechanical, and plumbing rough-in usually begins before framing is complete.

In: Civil Engineering

Give an example of a project where work sampling would be an appropriate productivity measuring technique.

Give an example of a project where work sampling would be an appropriate productivity measuring technique.

In: Civil Engineering

Wastewater from Taman Cenderawasih is treated through a bio tower. These are the data related to...

  1. Wastewater from Taman Cenderawasih is treated through a bio tower. These are the data related to the bio tower:

Flow rate

=

20 000 m3/day

Minimum temperature of the area

=

34C

Medium height

=

2 m

Influent BOD

=

300 mg/L

Effluent BOD

=

20 mg/L

Recirculation flow rate to the tower

=

35 000 m3/day

Wastewater treatability constant

=

0.09 min-1 at temperature 20C

Medium coefficient

=

0.5

Compute:

  1. Ratio of recycled flow to the influent flow
  2. Hydraulic loading (m3/m2.min)
  3. Volume of the medium needed

In: Civil Engineering

Problem 2: A 3 ft x 5 ft (B x L) rectangular footing is shown in...

Problem 2: A 3 ft x 5 ft (B x L) rectangular footing is shown in following figure. Using generalized bearing equation (with shape, depth and inclination factors), determine the allowable (safe) load that the foundation carry. Given: gamma = 115 lb/ft3 , c’= 1100 lb/ft2 , phi’ = 35°, Df =3.5 ft, Ground water table is located at 5 ft below ground level. Assume factor of safety = 3. Assume gammasat = 127.4 lb/ft

In: Civil Engineering

Curve 2: A +7.00% grade meets a -6.00% grade at station 4+80 and elevation 705.70 ft,...

Curve 2: A +7.00% grade meets a -6.00% grade at station 4+80 and elevation 705.70 ft, 80-ft curve, staked 10ft apart. Get a rough estimate in cubic yards of how much soil that must be brought in (fill) and/or removed (cut) to create a 14-foot wide roadway that starts at your PVC/BVC, ends at your PVT/EVC, and follows your curve elevations. Make sure to state which curve your group was assigned in the calculations. Trapezoidal Area Estimation is key. ground has the following elevations starting from the PC and ending at the PT; 702ft, 703ft, 704ft, 705ft, 706ft, 705ft, 704ft, 703ft,and 702ft.

In: Civil Engineering

Why did the chicken cross the road?

Why did the chicken cross the road?

In: Civil Engineering

what are some failure types of unconfined compression test? how do sample disturbance and soil remolding...

what are some failure types of unconfined compression test? how do sample disturbance and soil remolding change the results of the unconfined compression test? and does the moisture content affect the unconfined compression strength and shear strength of clay?

In: Civil Engineering

Describe the cost values of desalination concentrate management, find the calculations and Show in detail in...

Describe the cost values of desalination concentrate management, find the calculations and Show in detail in kWh / m3 and $ / m3 for each method.

(please don't take copy paste on others answers on chegg. .)

In: Civil Engineering

Discuss the changes that happen when a culvert is put into a channel

Discuss the changes that happen when a culvert is put into a channel

In: Civil Engineering

Mr. Paul has been working as a mechanical engineer in a well-known oil and gas firm,...

Mr. Paul has been working as a mechanical engineer in a well-known oil and gas firm, Toyo Engineering, for 15 years. Toyo Engineering has been awarded with a project to design and build a ship for use in offshore installation works in Terengganu, Malaysia. Due to Mr. Paul’s excellent project management skills, the company has appointed him as the Project Manager for this particular project. As a Project Manager, Mr. Paul has to deal with various vendors who are bidding to be the potential suppliers of the various items in the to-be-built ship. He has to keep close relation with all vendors to ensure that the supply of equipment and materials are on schedule for the timely delivery of the ship. Since Mr. Paul has been working in the oil and gas field for about 15 years, it happens that some of the vendors are his friends who have been working with him previously in various projects.  

  1. Identify THREE (3) most relevant BEM codes of professional conduct applicable in this case.

  

  1. Identify TWO (2) possible ethical dilemmas that will be faced by Mr. Paul in his work as a Project Manager.

(c)       Analyze how Mr. Paul should respond and act in the ethical dilemmas that you have identified in Q1(b) above.

(d)       Outline the action to be taken by Paul in protecting his company interest while complying with BEM codes of professional conduct.

                                               

In: Civil Engineering

The driver of an automobile, which travels with a velocity of 110 km/h on an a...

The driver of an automobile, which travels with a velocity of 110 km/h on an a 8% graded
descending section of an asphalt paved straigth highway on a rainy day, recognizes a
pedestrian crossing the street 100 meters away and applies the brake.
a) Determine whether the accident occurs or not.
b)If the driver is crashing with the pedestrian, what would be the maximum velocity to
avoid the accident ?
Given: Pavement sliding friction coefficient, f= 0,30; detection-response time, tr= 1 sec.

In: Civil Engineering

How is the PDS product design specifications developed your product?.

How is the PDS product design specifications developed your product?.

In: Civil Engineering

A concrete mix is required for reinforced concrete wave breaker at seashore where frequent mild freezing...

A concrete mix is required for reinforced concrete wave breaker at seashore where frequent mild freezing and thawing is dominant.
A specified compressive strength of 25 MPa is required at the age of 28 days, and the size of the section and reinforcement dictate using a maximum aggregate size of 19 mm.
The company had no history of testing concrete used.
The coarse aggregate meets the ASTM grading requirements. It has absorption of 2%, a BSG (D) of 2.70 and a unit weight of 1550 kg/m3. The fine aggregates have absorption of 1%, a BSG (D) of 2.7 and a fineness modulus of 2.7.
Both coarse and fine aggregates are used while dry. For each bag of cement (50 kg); calculate the number of containers of coarse and fine aggregate equivalent to required mass quantities.
The volume of each container is 20 liters; and the loose density of the coarse and fine aggregates are 1250 and 1200 kg/m3, respectively.

In: Civil Engineering

Q1: what do we do with the sludge resulted from waste water treatment process ? Can...

Q1: what do we do with the sludge resulted from waste water treatment process ? Can we use it to make mony ? How?

Q2: Do you support treated waste water and treated sludge to be used in agriculture to grow crops? Why?

In: Civil Engineering

Case Scenario Analysis: Managing risks in construction projects has been recognized as a very important management...

Case Scenario Analysis:

Managing risks in construction projects has been recognized as a very important management process in order to achieve the project objectives in terms of time, cost, quality, safety and environmental sustainability. A study aims to identify and analyze the risks associated with the development of construction projects from project stakeholder and life cycle perspectives. The study identified following risk factors.

1.Tight project schedule

2.High performance/quality expectations

3.Low management competency of subcontractors

4.Incomplete or inaccurate cost estimate

5.Lack of coordination between project team members

6.Unavailability of sufficient professionals and managers

7.Serious air pollution and noise caused by construction activities

Develop understanding on how and on what level three factors of your choice can generate risk in achieving project objectives. Finally, identify a set of measures that you as a project manager would like to plan and implement to reduce risk and ensure achievement of project objectives and contribute in business development.

Hint: Your answer should include the way the factor develop risk in the achievement of project objectives and its level. Finally, you need to develop measures or actions you would like to implement to manage and/or minimize the risk.

In: Civil Engineering