Question

In: Operations Management

Problem 12-3: The following table lists the components needed to assemble an end item, lead times...

Problem 12-3:

The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.

Item Lead Time Amount
on Hand
Direct Components
End 3 0 L(2), C(1), K(3)
L 3 9 B(2), J(3)
C 4 14 G(2), B(2)
K 4 19 H(4), B(2)
B 3 27
J 4 32
G 4 5
H 2 0


a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.)

Additional units           

b. An order for the end item is scheduled to be shipped at the start of week 15. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.)

The latest week           

Solutions

Expert Solution

43 units of end items are to be shipped

Therefore , gross number of item L required = 43 x 2 = 86

Number of L items on hand = 9 units

Therefore , net amount of L items required = 86 – 9 = 77

Since 2 number of item B required for each unit of L , number of item B required = 77 x 2 = 154

Since 1 unit of item C is required for each unit of end items,

Gross number of item C required for 43 units of end item = 43 units

Amount of item C on hand = 14

Therefore, net number of item C required = 43 – 14 = 29 units

Since 2 number of item B required for each unit of C,

Number of item B required = 29 x 2 = 58 units

Since 3 units of item K required for each unit of end item,

Gross number of item K required for 43 units of end item = 43 x 3 = 129

Number of item K in hand = 19 numbers

Therefore, net requirement of item K = 129 – 19 = 110

Since 2 units of item B required for each unit of item K , gross number of item K required = 110 x 2 = 220

However, number of item B in hand = 27 units

Therefore , net number of item B required = 220 – 27 = 193 units

Hence, total number of item B required = 154 + 58 + 193 units = 405 units

ADDITIONAL UNITS OF ITEM B REQUIRED = 405 UNITS

Time lag in delivery time between end item and B

= Lead time of delivery of C/K + lead time of delivery item B

= 4 + 3 weeks

= 7 weeks

Time lag in delivery time between end item and G

= Lead time of delivery of C + Lead time of delivery of G

= 4 + 4

= 8 weeks

Time lag in delivery between end item and J

= Lead time of delivery of L    + Lead time of delivery of J

= 3 + 4

= 7 weeks

Time lag in delivery between end item and H

= Lead time of delivery of K + Lead time of delivery H

= 4 + 2

= 6 weeks

Therefore , highest lead time of delivery for first level inputs vis a vis delivery time of end product = 8 weeks ( item G )

Since end item is required at beginning of week 15 ,

Input item is to be delivered latest by = 15 - 8 = 7 weeks

THE LATEST WEEK = 7 WEEKS


Related Solutions

The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 1 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 17 G(2), B(2) K 4 23 H(4), B(2) B 3 34 J 3 25 G 3 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times, and quantities...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C D E F G H LT (wk) 2 2 2 2 2 2 2 2 Amount on hand 0 8 11 23 9 28 6 0 a. If 22 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 16 G(2), B(2) K 4 21 H(4), B(2) B 3 26 J 4 33 G 4 4 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
Chapter 12 Problem 3 (Excel functions needed) Consider the project contained in Problem 7 in Chapter...
Chapter 12 Problem 3 (Excel functions needed) Consider the project contained in Problem 7 in Chapter 11 (California Health Center). a. Perform a sensitivity analysis to see how NPV is affected by changes in the number of procedures per day, average collection amount, and salvage value. Remember supplies vary with number of procedures. b. Conduct a scenario analysis. Suppose that the hospital's staff concluded that the three most uncertain variables were number of procedures per day, average collection amount, and...
Fill in the table below so that it lists every reagent needed for a PCR reaction...
Fill in the table below so that it lists every reagent needed for a PCR reaction and give its purpose in the reaction. You may or may not need all the rows in this table. Reagent Purpose 5X Taq Buffer F and R primers Supplies co-factor for polymerase Building blocks for new DNA Water
The accompanying table lists a random selection of usual travel times to​ school, in​ minutes, for...
The accompanying table lists a random selection of usual travel times to​ school, in​ minutes, for 40 secondary school students in country A. A second selection of usual travel times to​ school, in​ minutes, was randomly selected for 40 students in country B. Complete parts​ a) and​ b). Sample Country A   Sample Country B 45   29 5   10 4   9 14   30 50   5 21   8 21   7 19   15 21   10 21   36 24   16 36   10 14   24...
A statisitcs instructor participates in triathalons. the table lists the times in minutes and seconds, he...
A statisitcs instructor participates in triathalons. the table lists the times in minutes and seconds, he recorded while riding five laps through each mile of a 3-mile loop. Use a .05 significance level to test the claim that is takes the same time to ride each of the miles. Mile 1 3:15 3:25 3:23 3:22 3:22 Mile 2 3:19 3:23 3:20 3:17 3:19 Mile 3 3:34 3:30 3:29 3:30 3:29 Determine the null and alternate hypotheses. Find the F statistic...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT