In: Operations Management
Problem 12-3:
The following table lists the components needed to assemble an
end item, lead times (in weeks), and quantities on hand.
Item | Lead Time | Amount on Hand |
Direct Components | |||
End | 3 | 0 | L(2), C(1), K(3) | |||
L | 3 | 9 | B(2), J(3) | |||
C | 4 | 14 | G(2), B(2) | |||
K | 4 | 19 | H(4), B(2) | |||
B | 3 | 27 | ||||
J | 4 | 32 | ||||
G | 4 | 5 | ||||
H | 2 | 0 | ||||
a. If 43 units of the end item are to be
assembled, how many additional units of B are needed?
(Hint: You don’t need to develop an MRP plan.)
Additional units
b. An order for the end item is scheduled to be
shipped at the start of week 15. What is the latest week that the
order can be started and still be ready to ship on time?
(Hint: You don’t need to develop an MRP plan.)
The latest week
43 units of end items are to be shipped
Therefore , gross number of item L required = 43 x 2 = 86
Number of L items on hand = 9 units
Therefore , net amount of L items required = 86 – 9 = 77
Since 2 number of item B required for each unit of L , number of item B required = 77 x 2 = 154
Since 1 unit of item C is required for each unit of end items,
Gross number of item C required for 43 units of end item = 43 units
Amount of item C on hand = 14
Therefore, net number of item C required = 43 – 14 = 29 units
Since 2 number of item B required for each unit of C,
Number of item B required = 29 x 2 = 58 units
Since 3 units of item K required for each unit of end item,
Gross number of item K required for 43 units of end item = 43 x 3 = 129
Number of item K in hand = 19 numbers
Therefore, net requirement of item K = 129 – 19 = 110
Since 2 units of item B required for each unit of item K , gross number of item K required = 110 x 2 = 220
However, number of item B in hand = 27 units
Therefore , net number of item B required = 220 – 27 = 193 units
Hence, total number of item B required = 154 + 58 + 193 units = 405 units
ADDITIONAL UNITS OF ITEM B REQUIRED = 405 UNITS |
Time lag in delivery time between end item and B
= Lead time of delivery of C/K + lead time of delivery item B
= 4 + 3 weeks
= 7 weeks
Time lag in delivery time between end item and G
= Lead time of delivery of C + Lead time of delivery of G
= 4 + 4
= 8 weeks
Time lag in delivery between end item and J
= Lead time of delivery of L + Lead time of delivery of J
= 3 + 4
= 7 weeks
Time lag in delivery between end item and H
= Lead time of delivery of K + Lead time of delivery H
= 4 + 2
= 6 weeks
Therefore , highest lead time of delivery for first level inputs vis a vis delivery time of end product = 8 weeks ( item G )
Since end item is required at beginning of week 15 ,
Input item is to be delivered latest by = 15 - 8 = 7 weeks
THE LATEST WEEK = 7 WEEKS |