Question

In: Statistics and Probability

The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...

The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 92 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 40 17 25 75 85 20 60 200 87 Use the least total cost and the least unit cost lot-sizing methods to determine the quantity to order with the first order released with each method and which periods' requirements will be covered by that order. Quantity Ordered Periods Covered Least total cost Least unit cost

Solutions

Expert Solution

ANSWER:

First determine net requirement for each week:

WEEK

1

2

3

4

5

6

7

8

9

10

  Gross requirements

35

40

17

25

75

85

20

60

200

87

On-hand inventory = 92

92-35= 57

57-40 = 17

17-17 = 0

Net req.

0

0

0

25

75

85

20

60

200

87

Aggregate requirements of the subsequent periods and order them in first period such that cost change from first period to next is least.  

Weeks

Quantity Ordered

Carrying Cost

Ordering Cost

Total Cost

Total Cost change

Unit cost = Total cost/order qty

4

25

0

10

10

10/25 = 0.4

4 to 5

25 + 75 = 100

75 x 0.010 = 0.75

10

10.75

0.75

10.75/100 = 0.1075

4 to 6

100 + 85 = 185

(75+(2x85))x 0.01 = 2.45

10

12.45

1.7

12.45/185

= 0.0673

4 to 7

185 + 20 = 205

(75 + 2x85 + 3x20) x 0.01

= 3.05 or

2.45 + (3x20)x0.01 = 3.05

10

13.05

0.6

0.0637

4 to 8

205 + 60 = 265

3.05 + (4x60)x 0.01

= 5.45

10

15.45

2.4

0.0583

4 to 9

265 + 200 = 465

5.45 + (5x200x0.01)

= 15.45

10

25.45

10

0.0547

4 to 10

465 + 87 = 552

15.45 + (6 x 87x 0.01) = 20.67

10

30.67

5.22

0.055

According to least total cost lot sizing method: place first order in week 4 for periods 4, 5, 6, and 7 as the total cost change in week seven is least of all change.

Order quantity in week 4 = 205 units

Total cost of ordering and holding cost = $13.05

According to least unit cost lot sizing method: place first order in week 4 for periods 4 to 9 as the unit cost of order quantity till week 9 is least cost.

Order quantity in week 4 = 465 units

Total cost of ordering and holding cost = $25.45


Related Solutions

The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 1 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 17 G(2), B(2) K 4 23 H(4), B(2) B 3 34 J 3 25 G 3 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 16 G(2), B(2) K 4 21 H(4), B(2) B 3 26 J 4 33 G 4 4 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
Dumfries Industries is generating a materials requirement plan for the next six weeks. Here is its...
Dumfries Industries is generating a materials requirement plan for the next six weeks. Here is its most current information: Master Production Schedule Week 1 2 3 4 5 6 Item A 10 0 20 20 10 10 Other information Item Item’s Parent Lead time Lot size Current inventory A None 1 week LFL 20 B A 1 week 20 20 C B 1 week 50 20 How many levels does a product structure for Dumfries item A have? Using MRP...
The company with the common equity accounts shown here has declared a 10 percent stock dividend...
The company with the common equity accounts shown here has declared a 10 percent stock dividend when the market value of its stock is $38 per share.   Common stock ($1 par value) $ 440,000   Capital surplus 857,000   Retained earnings 3,830,800      Total owners' equity $ 5,127,800 What would be the number of shares outstanding, after the distribution of the stock dividend? (Do not round intermediate calculations.)   New shares outstanding    What would the equity accounts be after the stock dividend? (Do...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT