Question

In: Finance

A project that costs $24,500 today will generate cash flows of $8,400 per year for seven...

A project that costs $24,500 today will generate cash flows of $8,400 per year for seven years. What is the project's payback period?

  • 2.33 years

  • 2.92 years

  • 3.00 years

  • 2.43 years

  • .34 years

Solutions

Expert Solution

Solution :

The Project's Payback period = 2.92 years.

The solution is Option 2 = 2.92 years

Please find the attached screenshot of the excel sheet containing the detailed calculation for the solution.


Related Solutions

1. A project that costs $26,000 today will generate cash flows of $9,000 per year for...
1. A project that costs $26,000 today will generate cash flows of $9,000 per year for seven years. What is the project's payback period? 2.Living Colour Co. has a project available with the following cash flows: Year Cash Flow 0 −$35,230 1 7,940 2 9,530 3 13,490 4 15,570 5 10,280 If the required return for the project is 7.8 percent, what is the project's NPV?
You are considering a project that costs $17,000 today and will generate cash flows of $7,250...
You are considering a project that costs $17,000 today and will generate cash flows of $7,250 per year for 3 years. Calculate the IRR for this project. Question 2 options: 13.00% 13.41% 14.02% 15.01%
A project requires $1000 to be invested today, and is expects to generate cash flows in...
A project requires $1000 to be invested today, and is expects to generate cash flows in the future years: CF1=$500, CF2=$400, CF3=$200. What is the REGULAR payback period of this project? a) 2.5 years b) 3 years c) 1.25 years d) 0.5 years e) Never pay back the cost
Project X is expected to generate cash flows of $5,000 per year for 5 years and...
Project X is expected to generate cash flows of $5,000 per year for 5 years and its initial cost is $17,000. Project Y is mutually exclusive to Project S. Project Y costs $30,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, what is the IRR of the better project? a)12.00% b)14.85% c)13.65% d)14.05% e)14.40%
A company is considering a project that costs $150,000 and is expected to generate cash flows...
A company is considering a project that costs $150,000 and is expected to generate cash flows of $50,000, $52,000, $53,000 in the coming three years. Which of the following is correct? A. The project must have a postive net present value. B. The project must be accepted by the payback rule. C. The project must be accepted by the discounted payback rule. D The project must have an internal rate of return lower than 2% E. None of the above....
Project P costs $10,400 and is expected to produce cash flows of $3,650 per year for...
Project P costs $10,400 and is expected to produce cash flows of $3,650 per year for five years. Project Q costs $30,000 and is expected to produce cash flows of $9,250 per year for five years. a. Calculate the NPV, IRR, MIRR, and traditional payback period for each project, assuming a required rate of return of 8 percent. b. If the projects are independent, which project(s) should be selected? If they are mutually exclusive, which project should be selected?
A project costs $1000 today and will generate a cash flow of $3173 three years from...
A project costs $1000 today and will generate a cash flow of $3173 three years from now. If the interest rate is 3%, what is the net present value of the project?
Project A has cash flows of −$92,000, $49,400, $27,200, $24,500, and $30,690 for Years 0 to...
Project A has cash flows of −$92,000, $49,400, $27,200, $24,500, and $30,690 for Years 0 to 4, respectively. Project B has an initial cost of $50,000 and an annual cash inflow of $20,500 for four years. The required rate of return is 18 percent. These are mutually exclusive projects. Which project(s) should be accepted or rejected?
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) modified internal rate of return (MIRR). The firm’s required rate of return is 14 percent. If the projects are independent, which project (s) should be selected? If...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) mod- ified internal rate of return (MIRR). The firm’s required rate of return is 14 percent.  Compute the (a) NPV, (b) IRR, (c) MIRR, and (d) discounted payback...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT