Question

In: Finance

Project A has cash flows of −$92,000, $49,400, $27,200, $24,500, and $30,690 for Years 0 to...

Project A has cash flows of −$92,000, $49,400, $27,200, $24,500, and $30,690 for Years 0 to 4, respectively. Project B has an initial cost of $50,000 and an annual cash inflow of $20,500 for four years. The required rate of return is 18 percent. These are mutually exclusive projects. Which project(s) should be accepted or rejected?

Solutions

Expert Solution

Mutually exclusive projects are a set of projects out of which only one project can be selected.
We need to calculate the NPV for both the projects and the project with higher NPV should be selected.

NPV=-Initial cost + Present value of future cash flows

Project A:

Present value of future cash flows when the required return is 18% is calculated as:
Present value=49400/(1+18%)^1+27200/(1+18%)^2+24500/(1+18%)^3+30690/(1+18%)^4
=49400/1.18+27200/1.3924+24500/1.643032+30690/1.93877776
=41864.40678+19534.61649+14911.45638+15829.56058
=92140.04
NPV=-92000+92140.04
=$140.04

Project B:

Present value of future cash flows when the required return is 18% is calculated as:
Present value=20500/(1+18%)^1+20500/(1+18%)^2+20500/(1+18%)^3+20500/(1+18%)^4
=20500/1.18+20500/1.3924+20500/1.643032+20500/1.93877776
=17372.88136+14722.78081+12476.93289+10573.67194
=55146.267
NPV=-50000+55146.267=5146.267

Now, as the NPV of project B is greater than project A, project B should be accepted.


Related Solutions

Project A has initial cost of $40,000, and annual cash flow of $49,400, $27,200, and $24,500...
Project A has initial cost of $40,000, and annual cash flow of $49,400, $27,200, and $24,500 in years 1, 2, and 3, respectively. Project B has same initial cost of $40,000 but an annual cash inflow of $18,500 for 4 years. These are mutually exclusive projects. What is the crossover rate?
A project has expected cash flows of -$1,000, $2,500, and -$1,540 in years 0, 1, and...
A project has expected cash flows of -$1,000, $2,500, and -$1,540 in years 0, 1, and 2, respectively. The cost of capital is 15%. a. Construct an NPV profile using interest rates of 0, 10, 20, 30, 40, 50, and 60%. b. What is the IRR of the project?
A project that costs $24,500 today will generate cash flows of $8,400 per year for seven...
A project that costs $24,500 today will generate cash flows of $8,400 per year for seven years. What is the project's payback period? 2.33 years 2.92 years 3.00 years 2.43 years .34 years
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as...
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as follows: Year 1 = $274,600; Year 2 = $298,000; Year 3 = $303,950; Year 4 = $312,875; and Year 5 = $374,600. Calculate the Traditional Payback. Assume cash flows are even throughout the year. Calculate the Net Present Value using the WACC = 8.28%.
A project has the following cash flows for years 0 through 2, respectively: -10,556, 9,776, 9,987....
A project has the following cash flows for years 0 through 2, respectively: -10,556, 9,776, 9,987. What is the internal rate of return on this project?
Q1.) A project has the following cash flows for years 0 through 2, respectively: -13,568, 9,415,...
Q1.) A project has the following cash flows for years 0 through 2, respectively: -13,568, 9,415, 9,983. What is the internal rate of return on this project? Q2.) GDebi Enterprises is thinking of building a chemical processing plant to produce 4-hydroxy-3-methoxybenzaldehyde. The firm estimates that the initial cost of the project will be $11.7 million, and the plant will produce cash inflows of $7.2 million for the next 5 years, after which time the project will terminate. In the 6th...
Q1/ A project has the following cash flows for years 0 through 3, respectively: -34,416, 15,926,...
Q1/ A project has the following cash flows for years 0 through 3, respectively: -34,416, 15,926, 21,329, 38,250. If the required return is 10.6 percent, what is the net present value of the project? Q2/ A project has the following cash flows for years 0 through 2, respectively: -11,062, 8,666, 8,313. What is the internal rate of return on this project? Q3/ A project has the following cash flows, for years 0 through 3 respectively: -27,084, 11,112, 8,232, 9,204. If...
A project has the following cash flows for years 0 through 2, respectively: -10,529, 8,541, 8,441....
A project has the following cash flows for years 0 through 2, respectively: -10,529, 8,541, 8,441. What is the internal rate of return on this project?
Yellow Day has a project with the following cash flows: Year Cash Flows 0 −$27,000 1...
Yellow Day has a project with the following cash flows: Year Cash Flows 0 −$27,000 1 10,550 2 20,300 3 9,720 4 −3,600 What is the MIRR for this project using the reinvestment approach? The interest rate is 7 percent
A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2...
A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2 7,630 3 5,040 4 −1,580 Assuming the appropriate interest rate is 10 percent, what is the MIRR for this project using the discounting approach? 19.21% 15.23% 13.96% 11.63% 17.77%
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT