Question

In: Finance

You are considering a project that costs $17,000 today and will generate cash flows of $7,250...

You are considering a project that costs $17,000 today and will generate cash flows of $7,250 per year for 3 years. Calculate the IRR for this project.

Question 2 options:

13.00%

13.41%

14.02%

15.01%

Solutions

Expert Solution

Ans 13.41%

Year Project Cash Flows (i) DF@ 8% DF@ 8% (ii) PV of Project ( (i) * (ii) ) DF@ 18% (iii) PV of Project ( (i) * (iii) )
0 -17000 1 1                          (17,000.00) 1             (17,000.00)
1 7250 1/((1+8%)^1) 0.925926                               6,712.96 0.847                  6,144.07
2 7250 1/((1+8%)^2) 0.857339                               6,215.71 0.718                  5,206.84
3 7250 1/((1+8%)^3) 0.793832                               5,755.28 0.609                  4,412.57
NPV                               1,683.95 NPV               (1,236.52)
IRR = Ra + NPVa / (NPVa - NPVb) * (Rb - Ra)
8% + 1683.95 / (1683.95 + 1236.52)*10%
13.41%

Related Solutions

A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a....
A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a. If the required return is 10 percent, what is the NPV for this project? b. Determine the IRR for this project.
A company is considering a project that costs $150,000 and is expected to generate cash flows...
A company is considering a project that costs $150,000 and is expected to generate cash flows of $50,000, $52,000, $53,000 in the coming three years. Which of the following is correct? A. The project must have a postive net present value. B. The project must be accepted by the payback rule. C. The project must be accepted by the discounted payback rule. D The project must have an internal rate of return lower than 2% E. None of the above....
1. A project that costs $26,000 today will generate cash flows of $9,000 per year for...
1. A project that costs $26,000 today will generate cash flows of $9,000 per year for seven years. What is the project's payback period? 2.Living Colour Co. has a project available with the following cash flows: Year Cash Flow 0 −$35,230 1 7,940 2 9,530 3 13,490 4 15,570 5 10,280 If the required return for the project is 7.8 percent, what is the project's NPV?
A project requires $1000 to be invested today, and is expects to generate cash flows in...
A project requires $1000 to be invested today, and is expects to generate cash flows in the future years: CF1=$500, CF2=$400, CF3=$200. What is the REGULAR payback period of this project? a) 2.5 years b) 3 years c) 1.25 years d) 0.5 years e) Never pay back the cost
19) A firm is considering a project that is expected to generate annual cash flows of...
19) A firm is considering a project that is expected to generate annual cash flows of $24,000 for 15 years. The project requires an initial investment of $247,103.44. The cost of capital is 8.13%. What is the IRR of the project?
Project S costs $17,000 and its expected cash flows would be $4,000 per year for 5...
Project S costs $17,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $25,000 and its expected cash flows would be $10,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have NPV's > 0. c. Both Projects S and L,...
swf is considering a project that is expected to generate real cash flows of $10 million...
swf is considering a project that is expected to generate real cash flows of $10 million at the end of each year for 5 years. the intial outlay/investment required is $25 million. a nominal discount rate of 9.2% is appropriate for the risk level. inflation is 5% 1. you are company's financial analyst. the CFO has asked you to calculate the NPV using a schedule of future nominal cash flows. 2. justify the NPV will remain the same while rearranging...
A project costs $1000 today and will generate a cash flow of $3173 three years from...
A project costs $1000 today and will generate a cash flow of $3173 three years from now. If the interest rate is 3%, what is the net present value of the project?
Lotus Company is considering an investment project that is expected to generate after tax cash flows...
Lotus Company is considering an investment project that is expected to generate after tax cash flows $500 for the first year, $500 for the second year, $800 for the third year, and $800 for the fourth year. The initial investment is $1400. The firm has a cost of capital of 15%. (Keep your answer to only two decimals) a. What is the payback period for the investment ? (example of answer format: 15.42 years, or 15.42) b. What is the...
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW    ...
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW     0                         -60,000     1                         25,000     2                         25,000     3                         25,000     4                         25,000 If the appropriate discount rate is 11 ​percent, what is the​ project's discounted payback​ period in years?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT