Question

In: Accounting

1. A project that costs $26,000 today will generate cash flows of $9,000 per year for...

1. A project that costs $26,000 today will generate cash flows of $9,000 per year for seven years. What is the project's payback period?

2.Living Colour Co. has a project available with the following cash flows:

Year Cash Flow
0 −$35,230
1 7,940
2 9,530
3 13,490
4 15,570
5 10,280

If the required return for the project is 7.8 percent, what is the project's NPV?

Solutions

Expert Solution

1. Payback Period = ( Last Year with a Negative Cash Flow ) + [( Absolute Value of negative Cash Flow in that year)/ Total Cash Flow in the following year)]

= 2 +( 8,000 / 9,000)

= 2.89 Years

Hence the correct answer is 2.89 Years

Note :

Year Investment Cash Inflow Net Cash Flow
0 -26,000 -    -26,000 (Investment + Cash Inflow)
1 -    9,000 -17,000 (Net Cash Flow + Cash Inflow)
2 -    9,000 -8,000 (Net Cash Flow + Cash Inflow)
3 -    9,000 1,000 (Net Cash Flow + Cash Inflow)
4 -    9,000 10,000 (Net Cash Flow + Cash Inflow)
5 -    9,000 19,000 (Net Cash Flow + Cash Inflow)
6 -    9,000 28,000 (Net Cash Flow + Cash Inflow)
7 -    9,000 37,000 (Net Cash Flow + Cash Inflow)

2. Net Present Value = Present Value of Cash Inflows - Present Value of Cash Outflows

= [ $ 7,940 * 1/(1.078) ^ 1 + 9,530* 1/(1.078) ^ 2 +$ 13,490* 1/(1.078) ^ 3 +$ 15,570* 1/(1.078) ^ 4 +$ 10,280* 1/(1.078) ^ 5 ] - $ 35,230

= $ 9,695.91

Hence the correct answer is $ 9,695.91


Related Solutions

A project that costs $24,500 today will generate cash flows of $8,400 per year for seven...
A project that costs $24,500 today will generate cash flows of $8,400 per year for seven years. What is the project's payback period? 2.33 years 2.92 years 3.00 years 2.43 years .34 years
You are considering a project that costs $17,000 today and will generate cash flows of $7,250...
You are considering a project that costs $17,000 today and will generate cash flows of $7,250 per year for 3 years. Calculate the IRR for this project. Question 2 options: 13.00% 13.41% 14.02% 15.01%
A project has the following cash flows: Year Cash Flow 0 $ 47,000 1 – 26,000...
A project has the following cash flows: Year Cash Flow 0 $ 47,000 1 – 26,000 2 – 37,000 What is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)   IRR % What is the NPV of this project, if the required return is 12 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2...
A project has an initial cost of $40,000, expected net cash flows of $9,000 per year...
A project has an initial cost of $40,000, expected net cash flows of $9,000 per year for 7 years, and a cost of capital of 11% Calculate in excel NPV, IRR, PB, DPB?
The Renn project costs $26,000, and its expected net cash inflows are $7,800 per year for...
The Renn project costs $26,000, and its expected net cash inflows are $7,800 per year for 8 years. What is the project's payback period? What is the project's net present value (NPV), profitability index (PI), and internal rate of return (IRR) assuming a cost of capital of 10%? Calculate the project's modified internal rate of return (MIRR) assuming a cost of capital of 10%. What is the payback period of the Renn project?
A project requires $1000 to be invested today, and is expects to generate cash flows in...
A project requires $1000 to be invested today, and is expects to generate cash flows in the future years: CF1=$500, CF2=$400, CF3=$200. What is the REGULAR payback period of this project? a) 2.5 years b) 3 years c) 1.25 years d) 0.5 years e) Never pay back the cost
Project X is expected to generate cash flows of $5,000 per year for 5 years and...
Project X is expected to generate cash flows of $5,000 per year for 5 years and its initial cost is $17,000. Project Y is mutually exclusive to Project S. Project Y costs $30,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, what is the IRR of the better project? a)12.00% b)14.85% c)13.65% d)14.05% e)14.40%
A company is considering a project that costs $150,000 and is expected to generate cash flows...
A company is considering a project that costs $150,000 and is expected to generate cash flows of $50,000, $52,000, $53,000 in the coming three years. Which of the following is correct? A. The project must have a postive net present value. B. The project must be accepted by the payback rule. C. The project must be accepted by the discounted payback rule. D The project must have an internal rate of return lower than 2% E. None of the above....
Project L costs $45,000, its expected cash inflows are $9,000 per year for 8 years, and...
Project L costs $45,000, its expected cash inflows are $9,000 per year for 8 years, and its WACC is 11%. What is the project's payback? Round your answer to two decimal places.   years
Project L costs $40,000, its expected cash inflows are $9,000 per year for 8 years, and...
Project L costs $40,000, its expected cash inflows are $9,000 per year for 8 years, and its WACC is 11%. What is the project's discounted payback? Round your answer to two decimal places.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT