Question

In: Finance

A project requires $1000 to be invested today, and is expects to generate cash flows in...

A project requires $1000 to be invested today, and is expects to generate cash flows in the future years: CF1=$500, CF2=$400, CF3=$200. What is the REGULAR payback period of this project?


a) 2.5 years b) 3 years c) 1.25 years d) 0.5 years e) Never pay back the cost

Solutions

Expert Solution

Solution:
Answer is a) 2.50 years
Working Notes:
Notes: The payback period shows the period at which the Project able to generate cash flows which will repays investment done in the Project at initial stage for the setup of new Project.
We calculate Payback , first of all we keep cumulative cash flows year wise and keep going till the cumulative cash flows becomes positive. Then we compute Payback period = one year period before the year in which cumulative cash flows becomes positive + (negative value of last negative value in cumulative cash flow column )/ Cash inflow of the year in which cumulative cash flows becomes positive.
Project
Year Cash Flow -Product line Cumulative cash In-Flow
0 -1,000 -1,000
1 500 -500
2 400 -100
3 200 100
Project payback period is between 2nd and 3rd period as cumulative cash flow becomes positive in 3rd year
Payback period = 2 years + Remaining balance/3rd year cash inflows
= 2 + 100/200
=2.50
=2.50 years
Hence
The Payback is 2.50 years
Please feel free to ask if anything about above solution in comment section of the question.

Related Solutions

A project requires an initial investment of $1.2 million. It expects to generate a perpetual cash...
A project requires an initial investment of $1.2 million. It expects to generate a perpetual cash flow. The first year cash flow is expected at $100,000. The cash flows are then expected to grow at 1.25% forever. If the cost of capital for this project is 11%, what is the project's NPV? Group of answer choices -$0.480 million $0.265 million $7,177 million -$0.174 million -$0.265 million $0.174 million
A project requires an initial investment of $1.2 million. It expects to generate a perpetual cash...
A project requires an initial investment of $1.2 million. It expects to generate a perpetual cash flow. The first year cash flow is expected at $100,000. The cash flows are then expected to grow at 1.25% forever. The appropriate cost of capital for this project is 11%. What is the project's IRR and should it be accepted based on the IRR rule? Group of answer choices IRR is 9.6%; project should not be accepted IRR is 9.6%; project should be...
A project requires an investment of 10500 today and it is expected to generate after-tax cash...
A project requires an investment of 10500 today and it is expected to generate after-tax cash flows of 2,500 per year for the next 6 years. The company’s weighted average cost of capital is 12.2% per year. What is the projects net present value?
You are considering a project that costs $17,000 today and will generate cash flows of $7,250...
You are considering a project that costs $17,000 today and will generate cash flows of $7,250 per year for 3 years. Calculate the IRR for this project. Question 2 options: 13.00% 13.41% 14.02% 15.01%
A project costs $1000 today and will generate a cash flow of $3173 three years from...
A project costs $1000 today and will generate a cash flow of $3173 three years from now. If the interest rate is 3%, what is the net present value of the project?
1. A project that costs $26,000 today will generate cash flows of $9,000 per year for...
1. A project that costs $26,000 today will generate cash flows of $9,000 per year for seven years. What is the project's payback period? 2.Living Colour Co. has a project available with the following cash flows: Year Cash Flow 0 −$35,230 1 7,940 2 9,530 3 13,490 4 15,570 5 10,280 If the required return for the project is 7.8 percent, what is the project's NPV?
A project that costs $24,500 today will generate cash flows of $8,400 per year for seven...
A project that costs $24,500 today will generate cash flows of $8,400 per year for seven years. What is the project's payback period? 2.33 years 2.92 years 3.00 years 2.43 years .34 years
A project has an initial outlay of $3,640. The project will generate cash flows of $4,565...
A project has an initial outlay of $3,640. The project will generate cash flows of $4,565 in Years 1-5. What is the Equivalent Annual Annuity (EAA) of this project? Assume an interest rate of 11%. Note: Enter your answer rounded off to two decimal points. Do not enter $ or comma in the answer box. If your answer is negative, enter your answer as a negative number rounded off to two decimal points.
A machine can be purchased today for $1 million. It will generate cash flows of $200,000...
A machine can be purchased today for $1 million. It will generate cash flows of $200,000 at the end of each year for 10 years. However, a $300,000 overhaul will be required at the end of year 5. At a 10% opportunity cost of money, compute the net present value of this investment.
Corporation has a project with the initial cost of $150. It will generate the cash flows...
Corporation has a project with the initial cost of $150. It will generate the cash flows of $50, $100, and $150 in years 1, 2 and 3, respectively, which is the internal rate of return (IRR) of project?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT