Question

In: Finance

The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves...

The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves a cash outlay of $268,000 at the end of each of the next two years. At the end of the third year the company will receive payment of $620,000. Assume the IRR of this option exceeds the cost of capital.

The company can speed up construction by working an extra shift. In this case there will be a cash outlay of $580,000 at the end of the first year followed by a cash payment of $620,000 at the end of the second year. Use the IRR rule to show the (approximate) range of opportunity costs of capital at which the company should work the extra shift. (Enter your answers as a percent rounded to 2 decimal places. Enter the smallest percent first.)

The company should work the extra shift if the cost of capital is between _______% and _____%.

I know the first blank is 22.82%, I just can't figure out the second one.

Solutions

Expert Solution

Cash flow for scenario 1:

Year 1: -268,000
Year 2: -268,000
Year 3: +620,000

Cash flow for Scenario 2:

Year 1: -580,000
Year 2: +620,000
Year 3: 0

Now, let us calculate differential of the cashflow -

Year 1: -580,000 - (-268,000) = -312,000
Year 2: 620,000 -(-268,000) = +888,000
Year 3: 0 - 620,000 = -620,000

Assume that IRR for differential cash flow is r.
Setup the equation for IRR -

0 = -312,000 + 888,000/(1+r) - 620,000/(1+r)2

let us assume (1+r) = x

so equation becomes, after replacing 1+r and cancelling zero's
312 - 888/x + 620/x2 = 0

Multiply whole equation by x2
312x2 - 888x + 620 = 0

Solve the quadratic equation -
ax2 + bx + c = 0,

with two solutions -
x1 =
x2 =

in our case,
a = 312
b = -888
c = 620

so,
= = 121.5895
x1 = (888 - 121.5895)/(2*312) = 1.22822
x2 = (888 + 121.5895)/(2*312) = 1.61793

so,
1 + r = 1.22822 OR r = 22.82%
or 1 + r = 1.61793 OR r = 61.79%

So,

The company should work the extra shift if the cost of capital is between ___22.82____% and __61.79___%.

Important Note:
1. This is a classic case of multiple IRRs for a series of cashflow. When Cashflow changes sign more than once, multiple IRRs are possible. In this case sign of cashflow changed from negative to positive from 1st to 2nd year, then positive to negative again in 2nd to 3rd year. Because sign changed twice, we had a possibility of 2 IRRs.
2. It can be verified in excel that at cost of capital less than 22.82% and more than 61.79%, NPV of differential cashflow is negative, it is only positive when cost of capital is in between these values.
3. Curve between Cost of Capital and NPV looks like below in this case, where range of cost of capital for positive NPV can be seen -
(X-axis --> cost of capital)
(y-axis --> NPV)




Values in excel can be setup like below -


Values in excel look like below -


Screenshot shows value only till 27%, but formulas have been written till 80% of cost of capital.


Related Solutions

The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves a cash outlay of $270,000 at the end of each of the next two years. At the end of the third year the company will receive payment of $620,000. Assume the IRR of this option exceeds the cost of capital. The company can speed up construction by working an extra shift. In this case there will be a cash outlay of $584,000 at the...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves a cash outlay of $265,000 at the end of each of the next two years. At the end of the third year the company will receive payment of $625,000. Assume the IRR of this option exceeds the cost of capital. The company can speed up construction by working an extra shift. In this case, there will be a cash outlay of $575,000 at the...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves a cash outlay of $271,000 at the end of each of the next two years. At the end of the third year the company will receive payment of $640,000. Assume the IRR of this option exceeds the cost of capital. The company can speed up construction by working an extra shift. In this case, there will be a cash outlay of $592,000 at the...
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska....
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska. The project timeline is of the highest priority because work can only be completed during summer months due to adverse weather conditions. One of the suppliers of a key component has longer lead time than is required to complete the pipeline, but may be able to deliver if the construction company will pay fees to expedite. There are other suppliers, but these suppliers are...
A construction company has entered into a contract to build a parking complex. It hsa been...
A construction company has entered into a contract to build a parking complex. It hsa been estimated the complex will cost 700,000 and will take three years to construct. The complex will be billed to the purchasing company at 1,200,000. Information is as follows. X1 YEAR. X2 YEAR X3 YEAR cost incurrect to date 350,000 490,000 700,000 estimated cost yet to be incurrect 350,000. 210,000. 0 customer billings to date 300,000. 650,000 1,200,000 collections of billings to date 250,000. 600,000....
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $594,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $267,300 $463,320 $606,000 Estimated costs to complete 326,700 130,680 –0– Progress billings to date 268,000 547,000 896,000 Cash collected to date...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $597,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $908,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $286,560 $453,720 $609,000 Estimated costs to complete 310,440 143,280 –0– Progress billings to date 273,000 548,000 908,000 Cash collected to date...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $595,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $279,650 $487,900 $606,000 Estimated costs to complete 315,350 107,100 –0– Progress billings to date 272,000 545,000 903,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $246,000 $432,000 $612,000 Estimated costs to complete 354,000 168,000 –0– Progress billings to date 270,000 546,000 901,000 Cash collected to date...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT