Question

In: Finance

The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves...

The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves a cash outlay of $265,000 at the end of each of the next two years. At the end of the third year the company will receive payment of $625,000. Assume the IRR of this option exceeds the cost of capital.

The company can speed up construction by working an extra shift. In this case, there will be a cash outlay of $575,000 at the end of the first year, followed by a cash payment of $625,000 at the end of the second year. Use the IRR rule to show the (approximate) range of opportunity costs of capital at which the company should work the extra shift. (Enter your answers as a percent rounded to 2 decimal places. Enter the smallest percent first.)

The company should work the extra shift if the cost of capital is between  % and  %

Solutions

Expert Solution

The company should work extra shift if the cost of capital is between 22.46% and 64.64%

Calculations and explanations:

The cash flow scenario for the 2 situations are:

Year Projected schedule Accelerated shift
1 -265,000.00 -575,000.00
2 -265,000.00 625,000.00
3 625,000.00

We can use incremental analysis over here:

c1 c2 c3
Projected schedule -265,000.00 -265,000.00 625,000.00
Accelerated shift -575,000.00 625,000.00
Incremental flows -310,000.00 890,000.00 -625,000.00

We now need to find IRRs of the incremental flows shown above. Let the IRR be x.

Thus -310,000/(1+x) + 890,000/(1+x)^2 - 625,000/(1+x)^3 = 0

Now let 1+x be y

So, -310,000/y + 890,000/y^2 - 625,000/y^3 = 0

or, -310,000y^2 + 890,000y - 625,000 = 0

This is a quadratic equation in which a = -310,000, b = 890,000 and c = -625,000

So, y = [-b+-(b^2 - 4ac)^0.5]/2a

= [-890,000+/(890,000^2 - 4*-310,000*-625,000)^0.5]/2*-310,000

Solving we get y as 1.646398 or 1.224569

Now y = 1+x or x = y-1. So x will be either 0.646398 or 0.224569

The company should work extra shift if the cost of capital is between 22.46% and 64.64%


Related Solutions

The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves a cash outlay of $270,000 at the end of each of the next two years. At the end of the third year the company will receive payment of $620,000. Assume the IRR of this option exceeds the cost of capital. The company can speed up construction by working an extra shift. In this case there will be a cash outlay of $584,000 at the...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves a cash outlay of $268,000 at the end of each of the next two years. At the end of the third year the company will receive payment of $620,000. Assume the IRR of this option exceeds the cost of capital. The company can speed up construction by working an extra shift. In this case there will be a cash outlay of $580,000 at the...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves a cash outlay of $271,000 at the end of each of the next two years. At the end of the third year the company will receive payment of $640,000. Assume the IRR of this option exceeds the cost of capital. The company can speed up construction by working an extra shift. In this case, there will be a cash outlay of $592,000 at the...
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska....
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska. The project timeline is of the highest priority because work can only be completed during summer months due to adverse weather conditions. One of the suppliers of a key component has longer lead time than is required to complete the pipeline, but may be able to deliver if the construction company will pay fees to expedite. There are other suppliers, but these suppliers are...
A construction company has entered into a contract to build a parking complex. It hsa been...
A construction company has entered into a contract to build a parking complex. It hsa been estimated the complex will cost 700,000 and will take three years to construct. The complex will be billed to the purchasing company at 1,200,000. Information is as follows. X1 YEAR. X2 YEAR X3 YEAR cost incurrect to date 350,000 490,000 700,000 estimated cost yet to be incurrect 350,000. 210,000. 0 customer billings to date 300,000. 650,000 1,200,000 collections of billings to date 250,000. 600,000....
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $594,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $267,300 $463,320 $606,000 Estimated costs to complete 326,700 130,680 –0– Progress billings to date 268,000 547,000 896,000 Cash collected to date...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $597,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $908,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $286,560 $453,720 $609,000 Estimated costs to complete 310,440 143,280 –0– Progress billings to date 273,000 548,000 908,000 Cash collected to date...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $595,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $279,650 $487,900 $606,000 Estimated costs to complete 315,350 107,100 –0– Progress billings to date 272,000 545,000 903,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $246,000 $432,000 $612,000 Estimated costs to complete 354,000 168,000 –0– Progress billings to date 270,000 546,000 901,000 Cash collected to date...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT