You are the project manager responsible for a new building construction in northern Virginia. The building...

You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections and permit processes. You also notice that if you continue with the current cost rate and schedule rate that the total cost to complete this house would be $600,000 and delivered three months late.

Submit a three-page report explaining the reasons for these variances from your original project management plan and the proposed steps on how you are going to control the cost and schedule to achieve the contract threshold of $500,000 to be delivered in two years. Your plan must include the following:

Address identifications of impacted activities with their cost and schedule attributes, remembering to account for contingencies.

Address explanations of the roles your project management team will play during the execution of your project management plan and how they will help you to control the issues that are arising during the project.

Solutions

Expert Solution

After going through the given scenario the following are the facts understood:

Facts:

  • The building plan mentioned that the building is worth $500,000,
  • It will be five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years.
  • However, during execution it was determined that cost of materials is increased by 10%.
  • The schedule is running late by 90 days

The impacted activities with their cost and schedule attributes that were identified as follows:

  • The prime reason for project running behind schedule was the delay in county inspections and permit processes.
  • Because of this delay the cost of completing project will be increased from $500,000 to $600,000.
  • It will also delay in completion of project by 3 months.

The reasons for these variances from the original project management plan are as follows:

  • There is lack of planning. While any project is planned such risk are also calculated and then final price and duration of project is calculated.
  • Poor base line schedule is one of the reasons for this variance.
  • Insufficient resources might be there as of what was planned that resulted in this variance.

In order to control the cost and schedule to achieve the contract threshold of $500,000 to be delivered in two years following will be my plan:

  • Staining of resources is one thing that is essential to ensure that project meets the cost,
  • Maximizing the utilization of remaining time is order that will ensure that project completes on scheduled time.
  • The time that was allocated to various activities needs to be adjusted as per the requirement.
  • Teams should club two activities together (building of house and garage can be at simultaneously reducing the time of project).

Once the necessary inspection is done and the permission is gained for further construction the plan could be as follows:

Activities

Duration

Cost

Inspection and permission

3 months

$10,000

Laying foundation

4 months

$90,000

House Construction

1 year 4 months

$240,000

Garage Construction

4 months

$50,000

Labour

$110,000

The roles that project management team will play during the execution of the above project management plan are as following:

  • By inspecting that every step take place as planned,
  • By ensuring that no hurdles interrupt the project completion,
  • By ensuring that budget allocation is appropriate.
  • By taking controlling and preventive measures that ensure project completion is within budget and scheduled time.
  • By maximizing the utilization of time.

Related Solutions

Scenario: You are the project manager responsible for a new building construction in northern Virginia. The...
Scenario: You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections...
You were the project manager in charge of building a house in Ashburn, Virginia. The house...
You were the project manager in charge of building a house in Ashburn, Virginia. The house was a five-bedroom home estimated to cost $1.2 million dollars and had to be completed in 24 months. You have successfully built the house within cost and on time. You created a Project Budget, Project Schedule, Project Communication Plan, and Project Monitoring and Control Processes Plan for some unexpected schedule and cost problems. Now, develop a lessons-learned document for your organization and the project...
You are a project manager at a construction company that specializes in building office buildings. You...
You are a project manager at a construction company that specializes in building office buildings. You were approached by a representative of a company that was interested in your company’s services. He told you that their company was growing and they decided to build a new office building to address their needs. Then he told you that they already started the process with another construction company. They signed a contract with the other construction company and they started the building...
You are the project manager for a new multimillion-dollar building renovation for your organization. The company...
You are the project manager for a new multimillion-dollar building renovation for your organization. The company needs to maximize the space that it has, and the best approach is to do a staggered build-out in order to better maximize the space in the existing building. You feel that the best approach was to negotiate with multiple contractors on a fixed-price contract. Different contractors discussed other contracts with you, particularly ones to address the current market fluctuations in the raw materials...
There is a new amusement park under construction in town and the manager of the project...
There is a new amusement park under construction in town and the manager of the project has hired you to design a "Zero-Gravity" room. (a) Based on your knowledge of nature of electric charge and electric forces, how will you design such a facility? Comment on components of the room, and explain how it will work for walk in customers? What would be the safety concerns and measures? (b) Assume that your design has been approved and facility has been...
Beck Construction Company began work on a new building project on January 1, 2020. The project...
Beck Construction Company began work on a new building project on January 1, 2020. The project is to be completed by December 31, 2022, for a fixed price of $171 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years Actual costs incurred in each year Estimated remaining costs to complete the project (measured at Dec. 31 of each year) 2020 $ 47 million $...
Beck Construction Company began work on a new building project on January 1, 2017. The project...
Beck Construction Company began work on a new building project on January 1, 2017. The project is to be completed by December 31, 2019, for a fixed price of $108 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years Actual costs incurred in each year Estimated remaining costs to complete the project (measured at Dec. 31 of each year) 2017 $ 30 million $...
A construction company is evaluating an investment project consisting in developing a new residential building on...
A construction company is evaluating an investment project consisting in developing a new residential building on a plot of land. The cost of the land, to be paid in t=0, is €500K and construction would take 2 years. Construction costs are estimated to be €650K in t=1 and €650K in t=2. The building would then generate an annual cash flow of €250K in perpetuity, starting from t=3. If the cost of capital is 8%, the NPV of this project is...
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $500,000 and $700,000 B Normal probability distribution with a mean bid of $600,000 and a standard deviation of $40,000 If required, round your answers to three decimal places. If...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT