Question

In: Accounting

Beck Construction Company began work on a new building project on January 1, 2017. The project...

Beck Construction Company began work on a new building project on January 1, 2017. The project is to be completed by December 31, 2019, for a fixed price of $108 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff:

Years Actual costs incurred in each year Estimated remaining costs to complete the
project (measured at Dec. 31 of each year)
2017 $ 30 million $ 60 million
2018 $ 45 million $ 45 million
2019 $ 35 million $ 0


Required:

What amount of gross profit (or loss) would Beck record on this project in each year, assuming that Beck recognizes revenue for this project over time according to percentage of completion?

Place answers in the spaces provided below and show supporting computations. (Loss amounts should be indicated with a minus sign. Enter your answers in millions (i.e., 10,000,000 should be entered as 10).)

Solutions

Expert Solution

2017 2018 2019
Opening WIP              -          30.00        75.00
Cost incurred        30.00        45.00        35.00
Total Incurred till date        30.00        75.00     110.00
Estimated cost        60.00        45.00              -  
Total Cost        90.00     120.00     110.00
%age completion 33.33% 62.50% 100.00%
Contract Price     108.00     108.00     108.00
Estimated profit        18.00      (12.00)        (2.00)
Revenue recognizible        36.00        67.50     108.00
Revenue recognized till prev year              -        (36.00)      (67.50)
Revenue for current year        36.00        31.50        40.50
Cost      (30.00)      (49.50)      (30.50)
Gross Profit          6.00      (18.00)        10.00
Total estimated loss less profit recognized till last year

Related Solutions

Beck Construction Company began work on a new building project on January 1, 2020. The project...
Beck Construction Company began work on a new building project on January 1, 2020. The project is to be completed by December 31, 2022, for a fixed price of $171 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years Actual costs incurred in each year Estimated remaining costs to complete the project (measured at Dec. 31 of each year) 2020 $ 47 million $...
Arlington Company is constructing a building. Construction began on January 1 and was completed on December...
Arlington Company is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6,400,000 on March 1, $5,280,000 on June 1, and $8,000,000 on December 31. Arlington Company borrowed $3,200,000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6,400,000 note payable and an 11%, 4-year, $12,000,000 note payable. What is the avoidable interest for Arlington Company?
Sheridan Company is constructing a building. Construction began on January 1 and was completed on December...
Sheridan Company is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6380000 on March 1, $5290000 on June 1, and $8650000 on December 31. Sheridan Company borrowed $3240000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6410000 note payable and an 11%, 4-year, $12850000 note payable. What is the avoidable interest for Sheridan Company?
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 2,020,000 March 1, 2021 1,740,000 June 30, 2021 1,940,000 October 1, 2021 1,740,000 January 31, 2022 441,000 April 30, 2022 774,000 August 31, 2022 1,071,000 On January 1, 2021, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2015, Toby Manufacturing Company began construction of a building to be used as...
On January 1, 2015, Toby Manufacturing Company began construction of a building to be used as its second office. The building is completed on August 31, 2016. Expenditures on the project were as follows: January 3, 2015 $900,000 March 1, 2015 600,000 June 30, 2015 700,000 November 1, 2015 600,000 January 31, 2016 800,000 April 30, 2016 900,000 August 31, 2016 675,000 In order to finance the project, the company obtained a $2 million loan with a 10% interest on...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,710,000 March 1, 2018 1,320,000 June 30, 2018 1,520,000 October 1, 2018 1,320,000 January 31, 2019 378,000 April 30, 2019 711,000 August 31, 2019 1,008,000 On January 1, 2018, the company obtained a $4,200,000 construction loan with a 16% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,050,000 March 1, 2018 870,000 June 30, 2018 390,000 October 1, 2018 690,000 January 31, 2019 675,000 April 30, 2019 990,000 August 31, 2019 1,710,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 900,000 June 30, 2018 1,100,000 October 1, 2018 900,000 January 31, 2019 315,000 April 30, 2019 648,000 August 31, 2019 945,000 On January 1, 2018, the company obtained a $3,500,000 construction loan with a 12% interest rate....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT