Question

In: Operations Management

Scenario: You are the project manager responsible for a new building construction in northern Virginia. The...

Scenario: You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections and permit processes. You also notice that if you continue with the current cost rate and schedule rate that the total cost to complete this house would be $600,000 and delivered three months late.

Submit a three-page report explaining the reasons for these variances from your original project management plan and the proposed steps on how you are going to control the cost and schedule to achieve the contract threshold of $500,000 to be delivered in two years. Your plan must include the following:

  • Address identifications of impacted activities with their cost and schedule attributes, remembering to account for contingencies.
  • Address explanations of the roles your project management team will play during the execution of your project management plan and how they will help you to control the issues that are arising during the project.

Solutions

Expert Solution

Answer:

Project Management set up

When coming up with the project execution, some problems have to be compelled to be addressed supported the time allotted and therefore the availableness of the resources required. There are things that the project can go the surprising approach whereby the value can go up and therefore the time is less compared to what had been planned. These variations are caused by poor coming up with a schedule that shows what should be done and once to be done. once direction a project, one should please the shopper, your management and therefore the project that aims at keeping the political fireplace in restraint (Burke, 2013). within the completion of the project that was targeted to be finished inside 2 years and to value $500,000, there have been some that are delayed creating the method delay. The delays from the county inspections and allow method ar the beginning of a delayed project whereby the activities that had been planned to be dead at that exact time can have to be compelled to be pushed to a later date. once coming up with the project, the time allotted was 2 years. This was comprehensive of the time that may be taken by the authorities to allow and provides the required documents for the project to travel on (Kerzner, 2013). To be ready to have a transparent read of what would have gone wrong, let’s have a schedule that may involve the value and therefore the activities to be administrated throughout the 2 years.

From the table on top of, that was the budget that the project started with and therefore the time allotted to every activity. This, however, wasn't the case whereby some actions were delayed which meant the project would have to be compelled to extend with a few months. the value incurred doing the activities was going over expected largely because of the length taken to attend for the permissions. in a very project, the longer it takes, a lot of the value. once the authorities withhold the documents that provide the go-ahead for the development, the contractors should have to be compelled to wait until the documents are bestowed. The shopper cannot operate while not having all the small print, and so, there should be a complication between the management and therefore the shopper. The shopper has to see that everything has been done before the project commences.

Poor baseline schedules might are one in all the causes of the variances whereby the projection of the activities failed to replicate the truth. usually, there are issues with the authorities whereby they have a tendency to delay permissions for constructions. This meant that the schedule ought to have enclosed longer allotted to the time taken to receive the permissions from the authorities. Suppose they'd have given 3 months to the method. this might have meant squeeze of the activities that followed to satisfy the 2 years target. The delay by the authorities caused a rise of 3 months to end the development. the opposite cause could also be scarce resources compared to what had been planned. Having to set up a budget of $500,000 then realizing the project can value $600,000, it means that the approximation of the resources was done wrong. this can be a primary drawback once managing a project which suggests there'll be straining of the resources (Reiss, 2013).

The project management team features a massive role to play in guaranteeing that the point is met. this can mean the straining of the resources and to maximize the remaining time. Having a contract of 2 years means that once those 2 years the shopper needs the work done. Failure to having the work finished, the shopper can contemplate that as a breach of contract as made public by the laws of associate degree agreement. The time that was allotted to the assorted activities has to be adjusted. The project management team can have to be compelled to explore for higher ways in which during which to collect the activities to satisfy the time such (Reiss, 2013). for instance, rather than having to construct the house and therefore the garage throughout totally different times, the team might prefer to have each the activities done along. this can facilitate save totally on time and can guarantee higher utilization of the resources. the surplus quantity of cash that the project would have value is reduced once the various activities are done along. there'll be time-saving, and therefore the resources are used to the utmost.

Reflections on My Learning

There is the necessity for a project manager to consult the team to confirm what they set up is accomplishable and real. Project management desires a great deal of attention to create positive that the time and therefore the resources allotted ar real and correct. One could also be drawing a project decide to accomplish inside an amount, however at the top of it, all won't have it succeed. this can be for the rationale of lack of a correct setup and budget. The budget and time allotted are 2 crucial aspects that one ought to be terribly keen once managing the project set up. Project managers WHO don't have a true and possible project set up ar in peril of getting their project fail.

References

Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.

Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.


Related Solutions

You are the project manager responsible for a new building construction in northern Virginia. The building...
You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections and...
You were the project manager in charge of building a house in Ashburn, Virginia. The house...
You were the project manager in charge of building a house in Ashburn, Virginia. The house was a five-bedroom home estimated to cost $1.2 million dollars and had to be completed in 24 months. You have successfully built the house within cost and on time. You created a Project Budget, Project Schedule, Project Communication Plan, and Project Monitoring and Control Processes Plan for some unexpected schedule and cost problems. Now, develop a lessons-learned document for your organization and the project...
You are a project manager at a construction company that specializes in building office buildings. You...
You are a project manager at a construction company that specializes in building office buildings. You were approached by a representative of a company that was interested in your company’s services. He told you that their company was growing and they decided to build a new office building to address their needs. Then he told you that they already started the process with another construction company. They signed a contract with the other construction company and they started the building...
Scenario: you are the manager of this new project and whant to market a home to...
Scenario: you are the manager of this new project and whant to market a home to the future.The year is 2040. The demographics and psychographics have changed since 2017 and so the home industry has had to adapt. What will this house of the future look like? What will it realtors sell? How will it operate? Create a new and unique (not already offered) product or service the company will be launching. Where would be the best places to sell?Identify...
You are the project manager for a new multimillion-dollar building renovation for your organization. The company...
You are the project manager for a new multimillion-dollar building renovation for your organization. The company needs to maximize the space that it has, and the best approach is to do a staggered build-out in order to better maximize the space in the existing building. You feel that the best approach was to negotiate with multiple contractors on a fixed-price contract. Different contractors discussed other contracts with you, particularly ones to address the current market fluctuations in the raw materials...
There is a new amusement park under construction in town and the manager of the project...
There is a new amusement park under construction in town and the manager of the project has hired you to design a "Zero-Gravity" room. (a) Based on your knowledge of nature of electric charge and electric forces, how will you design such a facility? Comment on components of the room, and explain how it will work for walk in customers? What would be the safety concerns and measures? (b) Assume that your design has been approved and facility has been...
Beck Construction Company began work on a new building project on January 1, 2020. The project...
Beck Construction Company began work on a new building project on January 1, 2020. The project is to be completed by December 31, 2022, for a fixed price of $171 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years Actual costs incurred in each year Estimated remaining costs to complete the project (measured at Dec. 31 of each year) 2020 $ 47 million $...
Beck Construction Company began work on a new building project on January 1, 2017. The project...
Beck Construction Company began work on a new building project on January 1, 2017. The project is to be completed by December 31, 2019, for a fixed price of $108 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years Actual costs incurred in each year Estimated remaining costs to complete the project (measured at Dec. 31 of each year) 2017 $ 30 million $...
A construction company is evaluating an investment project consisting in developing a new residential building on...
A construction company is evaluating an investment project consisting in developing a new residential building on a plot of land. The cost of the land, to be paid in t=0, is €500K and construction would take 2 years. Construction costs are estimated to be €650K in t=1 and €650K in t=2. The building would then generate an annual cash flow of €250K in perpetuity, starting from t=3. If the cost of capital is 8%, the NPV of this project is...
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $500,000 and $700,000 B Normal probability distribution with a mean bid of $600,000 and a standard deviation of $40,000 If required, round your answers to three decimal places. If...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT