Question

In: Finance

A construction company is evaluating an investment project consisting in developing a new residential building on...

A construction company is evaluating an investment project consisting in developing a new residential building on a plot of land. The cost of the land, to be paid in t=0, is €500K and construction would take 2 years. Construction costs are estimated to be €650K in t=1 and €650K in t=2. The building would then generate an annual cash flow of €250K in perpetuity, starting from t=3. If the cost of capital is 8%, the NPV of this project is closest to:

A. €1,190K B. €1,020K C. €1,466K D. €1,357K

Solutions

Expert Solution

Value of perpetuity in year 2 can be computed using formula for PV of perpetuity as:

PV = C/r

C = Periodic cash flow starting in next year = € 250 K

r = Cost of Capital = 0.08

Value of cash inflow in year 2 = € 250 K/0.08

   = € 3,125 K

Total cash flow in year 2 = € 3,125 K - € 650 K = € 2,475 K

Cash outflow in year 0, 1 are € 500 and € 650 respectively

NPV = PV of cash inflows – PV of cash out flows

Year

Cash Flow (C)

Computation of PV Factor

PV Factor @ 8 % (F)

PV (C x F)

0

-€500 K

1/ (1+0.08)0

1

-€500 K

1

-€650 K

1/ (1+0.08)1

0.925925925925926

-€601.8518519 K

2

€2,475 K

1/ (1+0.08)2

0.857338820301783

€2,121.9135802 K

                             NPV

€1,020.0617283 K

NPV of the project is € 1,020.0617283 K or € 1,020 K

Hence option “B. € 1,020 K” is correct answer


Related Solutions

Beck Construction Company began work on a new building project on January 1, 2020. The project...
Beck Construction Company began work on a new building project on January 1, 2020. The project is to be completed by December 31, 2022, for a fixed price of $171 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years Actual costs incurred in each year Estimated remaining costs to complete the project (measured at Dec. 31 of each year) 2020 $ 47 million $...
Beck Construction Company began work on a new building project on January 1, 2017. The project...
Beck Construction Company began work on a new building project on January 1, 2017. The project is to be completed by December 31, 2019, for a fixed price of $108 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years Actual costs incurred in each year Estimated remaining costs to complete the project (measured at Dec. 31 of each year) 2017 $ 30 million $...
You are the project manager responsible for a new building construction in northern Virginia. The building...
You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections and...
An entrepreneur is considering a new project consisting of an apartment building with 50 units. Each...
An entrepreneur is considering a new project consisting of an apartment building with 50 units. Each unit can be rented for $950/month. It is expected to have an average vacancy rate of 8%. Net operating expenses are budgeted as 30% of the project's gross annual income. What would be the economic value of this project using a cap rate of 8.3%?
Beavis Construction Company was the low bidder on a construction project to build an office building...
Beavis Construction Company was the low bidder on a construction project to build an office building for $8,000,000. The project was begun in 2017 and completed in 2019. Cost and other data are presented below: 2017 2018 2019 Costs incurred during the year $ 1,500,000 $4,500,000 $1,550,000 Estimated costs to complete 4,500,000 1,500,000 -0- Billings during the year 1,400,000 5,200,000 1,400,000 Cash collections during the year 1,000,000 4,000,000 3,000,000 Assume that Beavis recognizes revenue on this contract over time according...
ANACOND is a construction company that is thought of creating a new residential block. Noted that...
ANACOND is a construction company that is thought of creating a new residential block. Noted that the initial investment to buy land and build buildings is amounting to 55 billion. If the project is successful, net income results at the end of the first year amounted to 100 billion and nothing again afterwards. If this project fails, then net income results to be obtained is 20 billion at the end of the first year and 20 billion at the end...
Q2. a. In the construction of a residential building, Explain the five different types of glasses...
Q2. a. In the construction of a residential building, Explain the five different types of glasses used in the fixing of the windows and doors. [5] b. HCT – Muscat will be planning to construct a building near main block, in this building to add the DPC in the above the ground level. 1. Write the name of the materials used for the DPC in ground level. [1]    2. Explain the provision of DPC in above question a neat...
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $500,000 and $700,000 B Normal probability distribution with a mean bid of $600,000 and a standard deviation of $40,000 If required, round your answers to three decimal places. If...
Scenario: You are the project manager responsible for a new building construction in northern Virginia. The...
Scenario: You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections...
As the financial advisor to Beena you are evaluating the following new investment in a project....
As the financial advisor to Beena you are evaluating the following new investment in a project. • The project has a useful life of 12 years. • Land costs $6m and is estimated to have a resale value of $10m at the completion of the project. • Buildings cost $5m, with allowable depreciation of 10% pa reducing balance and a salvage value of $0.9m. • Equipment costs $4m, with allowable depreciation of 20% pa reducing balance and a salvage value...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT