Question

In: Accounting

Beck Construction Company began work on a new building project on January 1, 2020. The project...

Beck Construction Company began work on a new building project on January 1, 2020. The project is to be completed by December 31, 2022, for a fixed price of $171 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff:

Years Actual costs incurred in each year Estimated remaining costs to complete the
project (measured at Dec. 31 of each year)
2020 $ 47 million $ 94 million
2021 $ 79 million $ 79 million
2022 $ 52 million $ 0


Required:
What amount of gross profit (or loss) would Beck record on this project in each year, assuming that Beck recognizes revenue for this project upon completion of the project? (Loss amounts should be indicated with a minus sign. Enter your answers in millions (i.e., 10,000,000 should be entered as 10).)

Solutions

Expert Solution

Answer : Calculation of Gross Profit (or loss) Beck record on this project in each year :

Percentage of Completion = Actual cost incurred / (Actual cost incurred + Estimated Cost to be incurred )

Year 2020

Percentage of Completion = $47million / ($47million + $94million)

= $47million / $141million

= 33.33%

Revenue to be recognised = Fixed price X Percentage of Completion

= $171 million X 33.33%

= $57 million

Gross Profit = Revenue recognised - Actual cost incurred

= $57 million - $47million

= $10 million

Year 2021

Percentage of Completion = $79million / ($79million + $79million)

= $79million / $158million

= 50%

Revenue to be recognised = (Fixed price X Percentage of Completion) -  Revenue recognised in earlier period

= ($171 million X 50%) -  $57 million

= $85.5 million - $57 million

= $28.5 million

Gross Profit = Revenue recognised - Actual cost incurred

= $28.5 million - $79million

= ($50.5 million)

Year 2022

Percentage of Completion = $52million / ($52million + 0)

= 100%

Revenue to be recognised = (Fixed price X Percentage of Completion) -  Revenue recognised in earlier period

= ($171 million X 100%) - ($57 million + $28.5 million)

= $171 million - $85.5 million

= $85.5 million

Gross Profit = Revenue recognised - Actual cost incurred

= $85.5 million - $52million

= $33.5 million

Conclusion :

Year 2020 : Gross Profit = $10 million

Year 2021 : Gross Loss =  $50.5 million

Year 2022 : Gross Profit = $33.5 million


Related Solutions

Beck Construction Company began work on a new building project on January 1, 2017. The project...
Beck Construction Company began work on a new building project on January 1, 2017. The project is to be completed by December 31, 2019, for a fixed price of $108 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years Actual costs incurred in each year Estimated remaining costs to complete the project (measured at Dec. 31 of each year) 2017 $ 30 million $...
On January 1, 2020, Lawrence Co. began construction of a building to be used as its...
On January 1, 2020, Lawrence Co. began construction of a building to be used as its office headquarters. The building is expected to be completed on December 31, 2020. Expenditures on this project during 2020 were as follows:                 January 1st          $ 160,000 March 1st               420,000 June 1st                  270,000 October 31st           165,000 On Jan. 1, 2020, the company obtained a $600,000 specific construction loan with a 7% interest rate. The loan was outstanding during the entire construction period. The company’s...
Arlington Company is constructing a building. Construction began on January 1 and was completed on December...
Arlington Company is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6,400,000 on March 1, $5,280,000 on June 1, and $8,000,000 on December 31. Arlington Company borrowed $3,200,000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6,400,000 note payable and an 11%, 4-year, $12,000,000 note payable. What is the avoidable interest for Arlington Company?
Sheridan Company is constructing a building. Construction began on January 1 and was completed on December...
Sheridan Company is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6380000 on March 1, $5290000 on June 1, and $8650000 on December 31. Sheridan Company borrowed $3240000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6410000 note payable and an 11%, 4-year, $12850000 note payable. What is the avoidable interest for Sheridan Company?
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 2,020,000 March 1, 2021 1,740,000 June 30, 2021 1,940,000 October 1, 2021 1,740,000 January 31, 2022 441,000 April 30, 2022 774,000 August 31, 2022 1,071,000 On January 1, 2021, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2015, Toby Manufacturing Company began construction of a building to be used as...
On January 1, 2015, Toby Manufacturing Company began construction of a building to be used as its second office. The building is completed on August 31, 2016. Expenditures on the project were as follows: January 3, 2015 $900,000 March 1, 2015 600,000 June 30, 2015 700,000 November 1, 2015 600,000 January 31, 2016 800,000 April 30, 2016 900,000 August 31, 2016 675,000 In order to finance the project, the company obtained a $2 million loan with a 10% interest on...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,710,000 March 1, 2018 1,320,000 June 30, 2018 1,520,000 October 1, 2018 1,320,000 January 31, 2019 378,000 April 30, 2019 711,000 August 31, 2019 1,008,000 On January 1, 2018, the company obtained a $4,200,000 construction loan with a 16% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,050,000 March 1, 2018 870,000 June 30, 2018 390,000 October 1, 2018 690,000 January 31, 2019 675,000 April 30, 2019 990,000 August 31, 2019 1,710,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT