Question

In: Accounting

Beck Construction Company began work on a new building project on January 1, 2020. The project...

Beck Construction Company began work on a new building project on January 1, 2020. The project is to be completed by December 31, 2022, for a fixed price of $171 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff:

Years Actual costs incurred in each year Estimated remaining costs to complete the
project (measured at Dec. 31 of each year)
2020 $ 47 million $ 94 million
2021 $ 79 million $ 79 million
2022 $ 52 million $ 0


Required:
What amount of gross profit (or loss) would Beck record on this project in each year, assuming that Beck recognizes revenue for this project upon completion of the project? (Loss amounts should be indicated with a minus sign. Enter your answers in millions (i.e., 10,000,000 should be entered as 10).)

Solutions

Expert Solution

Answer : Calculation of Gross Profit (or loss) Beck record on this project in each year :

Percentage of Completion = Actual cost incurred / (Actual cost incurred + Estimated Cost to be incurred )

Year 2020

Percentage of Completion = $47million / ($47million + $94million)

= $47million / $141million

= 33.33%

Revenue to be recognised = Fixed price X Percentage of Completion

= $171 million X 33.33%

= $57 million

Gross Profit = Revenue recognised - Actual cost incurred

= $57 million - $47million

= $10 million

Year 2021

Percentage of Completion = $79million / ($79million + $79million)

= $79million / $158million

= 50%

Revenue to be recognised = (Fixed price X Percentage of Completion) -  Revenue recognised in earlier period

= ($171 million X 50%) -  $57 million

= $85.5 million - $57 million

= $28.5 million

Gross Profit = Revenue recognised - Actual cost incurred

= $28.5 million - $79million

= ($50.5 million)

Year 2022

Percentage of Completion = $52million / ($52million + 0)

= 100%

Revenue to be recognised = (Fixed price X Percentage of Completion) -  Revenue recognised in earlier period

= ($171 million X 100%) - ($57 million + $28.5 million)

= $171 million - $85.5 million

= $85.5 million

Gross Profit = Revenue recognised - Actual cost incurred

= $85.5 million - $52million

= $33.5 million

Conclusion :

Year 2020 : Gross Profit = $10 million

Year 2021 : Gross Loss =  $50.5 million

Year 2022 : Gross Profit = $33.5 million


Related Solutions

Beck Construction Company began work on a new building project on January 1, 2017. The project...
Beck Construction Company began work on a new building project on January 1, 2017. The project is to be completed by December 31, 2019, for a fixed price of $108 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years Actual costs incurred in each year Estimated remaining costs to complete the project (measured at Dec. 31 of each year) 2017 $ 30 million $...
On January 1, 2020, Lawrence Co. began construction of a building to be used as its...
On January 1, 2020, Lawrence Co. began construction of a building to be used as its office headquarters. The building is expected to be completed on December 31, 2020. Expenditures on this project during 2020 were as follows:                 January 1st          $ 160,000 March 1st               420,000 June 1st                  270,000 October 31st           165,000 On Jan. 1, 2020, the company obtained a $600,000 specific construction loan with a 7% interest rate. The loan was outstanding during the entire construction period. The company’s...
On January 1, 2015 Costco began construction of a new warehouse in Redmond, WA. The building...
On January 1, 2015 Costco began construction of a new warehouse in Redmond, WA. The building was completed on June 30, 2016. Cash outlays for the $5 million project were as follows: 2015 January 1                        $1,000,000 March 1                          $600,000 June 30                           $800,000 September 30               $750,000 December 1                   $600,000 2016 March 31                        $800,000 June 30                           $450,000 (final payment) Total payments             $5,000,000 On January 1, 2015 Costco obtained a $3 million dollar construction loan with a 5% interest rate. Costco’s other long-term...
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 326,000 September 1, 2021 $ 477,000 December 31, 2021 $ 477,000 March 31, 2022 $ 477,000 September 30, 2022 $ 326,000 Dreamworld had $5,900,000 in 12% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $50,000 None...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 336,000 September 1, 2018 $ 504,000 December 31, 2018 $ 504,000 March 31, 2019 $ 504,000 September 30, 2019 $ 336,000 Dreamworld had $6,800,000 in 10% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows: January 1, 2016 $300,000 September 1, 2016 $450,000 December 31, 2016 $450,000 March 31, 2017 $450,000 September 30, 2017 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. Dreamworld's capitalized interest in 2016 was: a. $72,000 b. $63,000 c. $54,000 d. $36,000
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT