In: Finance
Question
We have two investment projects A&B. Both projects cost
$250, and we require a 15% return of the two
investments.
Year A B
1 $100 $100
2 $100 $200
3 $100 0
4 $100 0
a) Based on the payback period rule, which project
would you pick? Explain.
b) Based on the NPV rule, which project would you
pick? Explain.
c) Do a) and b) give you the same conclusion? If
not, why? Please elaborate.
d) What other methods can you use to evaluate
proposed investments? Please explain.
Cumulative cash flow | present value | ||||||||||||
year | Project A | Project B | Project A | Project B | PVIF @ 15% | Project A | Project B | ||||||
0 | -250 | -250 | -250 | -250 | 1.0000 | (250.00) | (250.00) | ||||||
1 | 100 | 100 | -150 | -150 | 0.8696 | 86.96 | 86.96 | ||||||
2 | 100 | 200 | -50 | 50 | 0.7561 | 75.61 | 151.23 | ||||||
3 | 100 | 0 | 50 | 50 | 0.6575 | 65.75 | - | ||||||
4 | 100 | 0 | 150 | 50 | 0.5718 | 57.18 | - | ||||||
35.50 | (11.81) | ||||||||||||
ans a) | Payback period A = | =2+(50/100) | |||||||||||
2.5 | year | ||||||||||||
Payback period B = | =1+(150/200) | ||||||||||||
1.75 | year | ||||||||||||
since payback of project B is lower therefore B should be selected | |||||||||||||
ans b) | NPV A = | 35.50 | |||||||||||
NPV B = | (11.81) | ||||||||||||
since NPV of A is positive and higher than B therefore based on NPV project A should be selected. | |||||||||||||
ans C) | a and b does not provide same conclusion. This is because Payback period does not take into account time value of money while NPV does | ||||||||||||
ans d) | NPV should be better approach to evaluate the project. As NPV take into account time value of money. | ||||||||||||
therefore project A should be selected. |