Question

In: Finance

_______ 1. We have two projects A and B that each have a cost of $10,000....

_______ 1. We have two projects A and B that each have a cost of $10,000. Project A has cash flows of $3,250, $3,250, $3,510, $3,510. Project B has cash flows of $800, $770, $4,600, and $9,000. The payback is: PROJECT A PAYBACK = 2.797 YEARs; PROJECT B PAYBACK = 3.654 YEARs. T OR F

______ 2. Using the information from #1, the NPV is $850.52 for A and -1,363.33 for project B. T OR F

______ 3. Net present value (NPV) is the difference between the present value of cash inflows and the present value of cash outflows. T OR F

    

______ 4. The key assumption behind NPV and IRR is that future cash flows are re-invested at the required rate of return for NPV and at the internal rate of return for the IRR. T OR F

______ 5. The key assumption behind the MIRR model is that cash flows are re-invested at the required rate of return. T OR F. EXPLAIN YOUR ANSWER IN A SENTENCE OR TWO.

Solutions

Expert Solution

(1.) False

Computation of Payback Period:
Project A Project B
Year Cashflows Cummulative Cashflow Cashflows Cummulative Cashflow
0 $   (10,000) $       (10,000)
1 $        3,250 $           3,250 $                800 $           800
2 $        3,250 $           6,500 $                770 $       1,570
3 $        3,510 $         10,010 $            4,600 $       6,170
4 $        3,510 $            9,000 $     15,170
Pay Back Period for Project A
Pay back period is the time taken to recover the initial investment.
Pay Back Period = 2 years + [($10,000 - $ 6,500)/($10,010 - $ 6,500)]
Pay Back Period = 2 years + 0.9972
Pay Back Period = 2.9972 years
Pay Back Period for Project B
Pay back period is the time taken to recover the initial investment.
Pay Back Period = 3 years + [($10,000 - $ 6,170)/($15,170 - $ 6,170)]
Pay Back Period = 3 years + 0.4256
Pay Back Period = 3.4256 years

(2)Answer: False

Computation of NPV :

Computation of NPV
Year Cashflows PVF@ 10 % PV Cashflows PVF@ 10 % PV
A 0 $                  (10,000) 1.0000 $               (10,000) $   (10,000) 1.0000 $           (10,000)
PV of Cash Outflows $               (10,000) $           (10,000)
B 1 $                      3,250 0.9091 $                   2,955 $           800 0.9091 $                   727
2 $                      3,250 0.8264 $                   2,686 $           770 0.8264 $                   636
3 $                      3,510 0.7513 $                   2,637 $       4,600 0.7513 $                3,456
4 $                      3,510 0.6830 $                   2,397 $       9,000 0.6830 $                6,147
PV of Cash Inflows $                 10,675 $             10,967
NPV = B-A $                       675 $                   967

From the above we can observe, on an assumtion of 10% Cost of Capital, NPV is higher for Project B than Project; the result remains same irrespective of cost of Capital. As per the question NPV of Project A is higher than Project B, HEnce the given statement is False.

(3) True.

Net present value is nothing but net off of the present value of cash inflows and outflows by discounting the flows at a specified rate.

NPV is calculated by taking the difference between the present value of cash inflows and present value of cash outflows over a period of time.

(4) True

While Computing NPV of Project, Cash flows arising in every year are discounted using Cost of Capital, considers implied assumption that those cashflows can be reinvested at Cost of Capital for balance life of the project.

While Computing IRR of Project, Cash flows arising in every year are discounted using expected IRR, which considers implied assumption that those cashflows can be reinvested at same IRR for balance life of the project.

(5) True

The key assumption behind the MIRR model is that cash flows are re-invested at the required rate of return.

That is why, while Computing MIRR of Project, Cash flows arising in every year are taken assumed to be reinvested agt cost of capital and that amount is discounted for computing MIRR.


Related Solutions

Question We have two investment projects A&B. Both projects cost $250, and we require a 15%...
Question We have two investment projects A&B. Both projects cost $250, and we require a 15% return of the two investments. Year A B 1 $100 $100 2 $100 $200 3 $100 0 4 $100 0 a) Based on the payback period rule, which project would you pick? Explain. b) Based on the NPV rule, which project would you pick? Explain. c) Do a) and b) give you the same conclusion? If not, why? Please elaborate. d) What other methods...
Projects A and B are mutually exclusive and have an initial cost of $78,000 each. Project...
Projects A and B are mutually exclusive and have an initial cost of $78,000 each. Project A provides cash inflows of $32,000 a year for three years while Project B produces a cash inflow of $44,400 a year for two years. Which project(s) should be accepted if the discount rate is 10 percent? What if the discount rate is 12.5 percent?
We have two independent and mutually exclusive projects, A and B. Project A requires an initial...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial investment of $1500, and will yield $800 of cash inflows for the next three years. Project B requires an initial investment of $5000, and will yield $1,500 of cash inflows for the next five years. The required return on each project is 10%. a. What are the net present values of Project A and Project B? b. What is the problem with using the...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial investment of $1000, and will yield $500 of cash inflows for the next three years. Project B requires an initial investment of $3,500, and will yield $1,000 of cash inflows for the next five years. The required return on both projects is 10%.                                                                                                      (13 marks total) a. What are the net present values of Project A and Project B? b. What is...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial investment of $1500, and will yield $800 of cash inflows for the next three years. Project B requires an initial investment of $5000, and will yield $1,500 of cash inflows for the next five years. The required return on each project is 10%.                                                                                                                                        (13 marks total) a.   What are the net present values of Project A and Project B?                 b.  ...
Question 1 Suppose we have two goods, whose quantities are denoted by A and B, each...
Question 1 Suppose we have two goods, whose quantities are denoted by A and B, each being a real number. A consumer’s consumption set consists of all (A; B) such that A ≥ 0 and B > 4. His utility function is: U (A, B) = ln(A + 5) + ln(B - 4). The price of A is p and that of B is q; total income is I. You have to find the consumer’s demand functions and examine their...
You are considering an investment in two projects, A and B. Both projects will cost $115,000,...
You are considering an investment in two projects, A and B. Both projects will cost $115,000, and the projected cash flows are as follows: YEAR PROJECT A PROJECT B 1 $7,188    $51,750 2 $21,562    $38,812 3 $40,250    $28,750 4 $50,315    $21,563 5    $57,500 $14,375 Using Excel and show formulas a. Assuming that the WACC is 9.4%, calculate the payback period, discounted payback period, NPV, PI, IRR, and MIRR. If the projects are mutually exclusive, which...
The Radford Company is faced with two mutually exclusive investment projects. Each costs $10,000 and each...
The Radford Company is faced with two mutually exclusive investment projects. Each costs $10,000 and each has an expected life of three years. Annual net cash flows from each project begin one year after the initial investment is made and have the following probability distribution. Project A: Probability .3 .5 .2 Cash Flows 5,000 6,000 7,000 Project B: Probability .25 .6 .15 Cash Flows 2,000 5,000 8,000 The Radford company evalutes project A at 10% and project B at 12%...
Suppose we have two goods, whose quantities are denoted by A and B , each being...
Suppose we have two goods, whose quantities are denoted by A and B , each being a real number. A consumer’s consumption set consists of all (A; B ) such that A ≥ 0 and B > 4. His utility function is: U (A, B) = ln(A + 5) + ln(B - 4). The price of A is p and that of B is q; total income is I. You have to find the consumer’s demand functions and examine their...
Heller Airlines is considering two mutually exclusive projects, A and B. The projects have the same...
Heller Airlines is considering two mutually exclusive projects, A and B. The projects have the same risk. Below are the cash flows from each project: Project A Project B Year Cash Flow Cash Flow 0 -$2,000 -$10,000 1 6,000 15,000 a. Graph the NPV profile of each investment. b. Indicate the crossover point and calculate the crossover rate. c. If the cost of capital is 8%, which project should be chosen and why?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT