In: Finance
Project |
Year 0 |
1 |
2 |
3 |
4 |
5 |
Alpha |
-55,000 |
15,000 |
14,000 |
22,000 |
30,000 |
35,000 |
Gamma |
-80,000 |
40,000 |
30,000 |
25,000 |
25,000 |
20,000 |
Present Value = Future value/ ((1+r)^t) | ||||||||
where r is the interest rate that is 15% and t is the time period in years. | ||||||||
Net present value (NPV) = initial investment + sum of present values of future cash flows. | ||||||||
Use the financial formulas function in excel to find the Internal rate of return (IRR) | ||||||||
Profitability Index (PI) = sum of present values of future cash flows/initial investment | ||||||||
PROJECT ALPHA | ||||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | ||
cash flow | -55000 | 15000 | 14000 | 22000 | 30000 | 35000 | ||
present value | 13043.48 | 10586.01 | 14465.36 | 17152.6 | 17401.19 | |||
NPV | 17648.63 | |||||||
Internal rate of return | 25.73% | |||||||
PI | 1.32 | |||||||
PROJECT GAMMA | ||||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | ||
cash flow | -80000 | 40000 | 30000 | 25000 | 25000 | 20000 | ||
present value | 34782.61 | 22684.31 | 16437.91 | 14293.83 | 9943.535 | |||
NPV | 18142.19 | |||||||
Internal rate of return | 25.55% | |||||||
PI | 1.23 | |||||||
a) | IRR | |||||||
PROJECT ALPHA | 25.73% | |||||||
PROJECT GAMMA | 25.55% | |||||||
The IRR is the discount rate for which NPV is zero. Select the project if the cost of capital | ||||||||
is less than the IRR. The higher the IRR, the more profitable is the project. | ||||||||
Project Alpha is better because it has a higher IRR. | ||||||||
b) | NPV | |||||||
PROJECT ALPHA | 17648.63 | |||||||
PROJECT GAMMA | 18142.19 | |||||||
The higher the NPV, the better the project. | ||||||||
Project Gamma is better because it has a higher NPV. | ||||||||
c) | PI | |||||||
PROJECT ALPHA | 1.32 | |||||||
PROJECT GAMMA | 1.23 | |||||||
The higher the PI, the more profitable the project. | ||||||||
Project Alpha is better because it has a higher PI. | ||||||||
d) | Based on the IRR and PI rule, project Alpha is better. | |||||||
Based on NPV, project Gamma is better. | ||||||||
Overall, project Alpha is better because project Alpha is | ||||||||
better according to two of the rules. Project Gamma is | ||||||||
only better as per the NPV rule. |