Question

In: Finance

Consider the following two projects. The cost of capital for both projects is 15%. Project Year...

  1. Consider the following two projects. The cost of capital for both projects is 15%.

Project

Year 0

1

2

3

4

5

Alpha

-55,000

15,000

14,000

22,000

30,000

35,000

Gamma

-80,000

40,000

30,000

25,000

25,000

20,000

  1. Calculate the IRR for each project and determine which one is better.
  2. Calculate the NPV for each project and determine which one is better.
  3. Based on profitability index method, which project is better?
  4. Overall, which project should be accepted assuming they are mutually exclusive? Why?

Solutions

Expert Solution

Present Value = Future value/ ((1+r)^t)
where r is the interest rate that is 15% and t is the time period in years.
Net present value (NPV) = initial investment + sum of present values of future cash flows.
Use the financial formulas function in excel to find the Internal rate of return (IRR)
Profitability Index (PI) = sum of present values of future cash flows/initial investment
PROJECT ALPHA
Year 0 1 2 3 4 5
cash flow -55000 15000 14000 22000 30000 35000
present value 13043.48 10586.01 14465.36 17152.6 17401.19
NPV 17648.63
Internal rate of return 25.73%
PI 1.32
PROJECT GAMMA
Year 0 1 2 3 4 5
cash flow -80000 40000 30000 25000 25000 20000
present value 34782.61 22684.31 16437.91 14293.83 9943.535
NPV 18142.19
Internal rate of return 25.55%
PI 1.23
a) IRR
PROJECT ALPHA 25.73%
PROJECT GAMMA 25.55%
The IRR is the discount rate for which NPV is zero. Select the project if the cost of capital
is less than the IRR. The higher the IRR, the more profitable is the project.
Project Alpha is better because it has a higher IRR.
b) NPV
PROJECT ALPHA 17648.63
PROJECT GAMMA 18142.19
The higher the NPV, the better the project.
Project Gamma is better because it has a higher NPV.
c) PI
PROJECT ALPHA 1.32
PROJECT GAMMA 1.23
The higher the PI, the more profitable the project.
Project Alpha is better because it has a higher PI.
d) Based on the IRR and PI rule, project Alpha is better.
Based on NPV, project Gamma is better.
Overall, project Alpha is better because project Alpha is
better according to two of the rules. Project Gamma is
only better as per the NPV rule.

Related Solutions

Consider the following two projects, and assume a company's cost of capital is 15 percent. Find...
Consider the following two projects, and assume a company's cost of capital is 15 percent. Find the IRR and NPV of each project. Which projects add value to the company? If the company can choose only a single project, which project should it choose? Please show through excel sheets and equations. Year 1 Year 2 Year 3 Year 4 Project 1 -$40 $130 $19 $26 Project 2 -$80 $36 $36 $36
Consider the following three projects; assume 14 percent cost of capital. Period Project A    Project...
Consider the following three projects; assume 14 percent cost of capital. Period Project A    Project B                   Project C                   T=0                                               ($3,000)                     ($5,000)                     ($2,000)                   T=1                                               $1,000                       $1,500                            $900                   T=2                                               $1,200                      $1,500                            $900                   T=3                                               $1,500                      $2,500                            $700                   T=4                                               $1,500                       $2,500                            $700                          When you have only $5,000 to support the above projects, which project (or projects) should be chosen under the Profitability Index?
Consider the following two projects for Copper Mountain Sports. Both project are projected to produce cash...
Consider the following two projects for Copper Mountain Sports. Both project are projected to produce cash flows for 5 years at which time the equipment will have become technologically obsolete. For these projects, calculate the "cross-over rate". The cross -over rate is the discount rate where both projects would have the same NPV. Year Snow Shoes Snowmobiles 0 -$250,000 -$250,000 1 $25,000 $150,000 2 $80,000 $160,000 3 $200,000 $75,000 4 $190,000 $50,000 5 $150000 $5000 a) 33.67% b) These two...
Consider the following two investment projects: Project A: it has an initial cost of 20,000 euros...
Consider the following two investment projects: Project A: it has an initial cost of 20,000 euros and requires additional investments of 5,000 euros at the end of the first year and 15,000 euros at the end of the second. This project is two years old and generates 20,000 euros per year in income. Project B: it has an initial cost of 20,000 euros and requires an additional investment of 10,000 euros at the end of the first year. This project...
Consider the following projects and assume an opportunity cost of capital of 12%.
Consider the following projects and assume an opportunity cost of capital of 12%. a. Calculate the Net Present Value (NPV) of each project. Which is to be preferred and why?(8 marks)b. If there is a capital constraint in place which limits spending to £10,000, which project or projects should be selected? Support your answer with calculations.
Consider the following two mutually exclusive project. Relevant discount rate for both projects are 12 percent....
Consider the following two mutually exclusive project. Relevant discount rate for both projects are 12 percent. Year CF Project A (Rp) CF Project B (Rp) 0 (2,000,000) (2,300,000) 1 900,000 550,000 2 800,000 650,000 3 950,000 708,000 4 978,000 1,155,000 5 300,000 2,000,000 a. If you apply the discounted payback criterion, which project will you choose? Why? b. If you apply the IRR criterion, which project will you choose? Why? Hint: Range A: 29-31% ; Range B: 24-26% c. If...
Q) Consider the following cash flow on two mutually exclusive projects. Year Project A (Rs) Project...
Q) Consider the following cash flow on two mutually exclusive projects. Year Project A (Rs) Project B(Rs) 0 -40000 -50000 1 20000 10000 2 15000 20000 3 15000 40000 The cash flow of project A are expressed in real terms while those of project B are expressed in nominal terms.The appropriate nominal discount rate is 15% and the inflation rate is 4%. Which project should be choosen.
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0   –$ 68,000   –$ 83,000 1 48,000 47,000 2 43,000 56,000 3 38,000 59,000 The cash flows of Project A are expressed in real terms, whereas those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 5 percent. Calculate the NPV for each project. (Do not round intermediate calculations and round your answers...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0 67000 82000 1 47000 46000 2 42000 55000 3 37000 58000 The cash flows of Project A are expressed in real terms while those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 10 percent and the inflation rate is 2 percent.    Calculate the NPV for each project. (Do not round intermediate calculations and round your answers to...
Consider the following two​ projects: Project    Year 0 Cashflow   Year 1 Cashflow    Year 2 Cashflow    Year...
Consider the following two​ projects: Project    Year 0 Cashflow   Year 1 Cashflow    Year 2 Cashflow    Year 3 Cashflow   Year 4 Cashflow Discount rate A    -100 40 50 60 N/A .15 B -147   50 70 90 5 .15 An incremental IRR of Project B over Project A is _________%. (Please round to two decimal places, write the number only without "%". i.e. if the answer is "5%", write "5.00")
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT