Question

In: Finance

You are considering an investment in two projects, A and B. Both projects will cost $115,000,...

You are considering an investment in two projects, A and B. Both projects will cost $115,000, and the projected cash flows are as follows:

YEAR PROJECT A PROJECT B

1 $7,188    $51,750

2 $21,562    $38,812

3 $40,250    $28,750

4 $50,315    $21,563

5    $57,500 $14,375

Using Excel and show formulas

a. Assuming that the WACC is 9.4%, calculate the payback period, discounted payback period, NPV, PI, IRR, and MIRR. If the projects are mutually exclusive, which project should be selected?

b. Create an NPV profile chart for projects A and B. What is the exact crossover rate for these two projects?

Solutions

Expert Solution

(a): The answers are:

Payback Discounted payback NPV PI IRR MIRR
Project A 3.91 4.67 12,145.72 1.11 12.50 11.62
Project B 2.85 3.88 10,916.75 1.09 13.95 11.40

Calculations:

Payback:

Year A's cash flow Cumulative cash flow of A B's cash flow Cumulative cash flow of B
0 -115,000.00 -115,000.00 -115,000.00 -115,000.00
1 7,188.00 -107,812.00 51,750.00 -63,250.00
2 21,562.00 -86,250.00 38,812.00 -24,438.00
3 40,250.00 -46,000.00 28,750.00 4,312.00
4 50,315.00 4,315.00 21,563.00
5 57,500.00 14,375.00

A's payback = 3+(46000/50315) = 3.91 years

B's payback = 2+(24438/28750) = 2.85 years

Discounted payback:

Year A's cash flow 1+r PVIF A's discounted cash flow Cumulative discounted cash flow of A B's cash flow B's discounted cash flow Cumulative discounted cash flow of B
0 -115,000.00 1.094 1.0000 -115,000.00 -115,000.00 -115,000.00 -115,000.00 -115,000.00
1 7,188.00 0.9141 6,570.38 -108,429.62 51,750.00 47,303.47 -67,696.53
2 21,562.00 0.8355 18,015.84 -90,413.78 38,812.00 32,428.84 -35,267.69
3 40,250.00 0.7637 30,740.71 -59,673.07 28,750.00 21,957.65 -13,310.04
4 50,315.00 0.6981 35,125.96 -24,547.11 21,563.00 15,053.58 1,743.55
5 57,500.00 0.6381 36,692.83 12,145.72 14,375.00 9,173.21

A's discounted payback = 4+(24547.11/36692.83) = 4.67 years

B's discounted payback = 3+(13310.04/15053.58) = 3.88 years

NPV:

Year A's cash flow 1+r PVIF A's discounted cash flow B's discounted cash flow
0 -115,000.00 1.094 1.0000 -115,000.00 -115,000.00
1 7,188.00 0.9141 6,570.38 47,303.47
2 21,562.00 0.8355 18,015.84 32,428.84
3 40,250.00 0.7637 30,740.71 21,957.65
4 50,315.00 0.6981 35,125.96 15,053.58
5 57,500.00 0.6381 36,692.83 9,173.21
NPV 12,145.72 10,916.75

PI: PI = present value of cash inflows/present value of cash outflows

A's cash flow 1+r PVIF A's discounted cash flow B's discounted cash flow
-115,000.00 1.094 1.0000 -115,000.00 -115,000.00
7,188.00 0.9141 6,570.38 47,303.47
21,562.00 0.8355 18,015.84 32,428.84
40,250.00 0.7637 30,740.71 21,957.65
50,315.00 0.6981 35,125.96 15,053.58
57,500.00 0.6381 36,692.83 9,173.21
Present value of inflows 127,145.72 125,916.75
Present value of outflow 115,000.00 115,000.00
PI 1.11 1.09

IRR: it is the rate that makes NPV as nil:

A's cash flow 1+r PVIF A's discounted cash flow
-115,000.00 1.1250402 1.0000 -115,000.00
7,188.00 0.8889 6,389.11
21,562.00 0.7901 17,035.43
40,250.00 0.7023 28,265.83
50,315.00 0.6242 31,406.92
57,500.00 0.5548 31,902.72
NPV 0.00

B's IRR:

Year 1+r PVIF B's cash flow B's discounted cash flow
0 1.139537 1.0000 -115,000.00 -115,000.00
1 0.8775 51,750.00 45,413.18
2 0.7701 38,812.00 29,888.84
3 0.6758 28,750.00 19,429.09
4 0.5930 21,563.00 12,787.79
5 0.5204 14,375.00 7,481.10
Total 0.00

MIRR: Present value of cash outflow = Terminal value/(1+MIRR)^5

Terminal value of A = 7188*1.094^4 + 21562*1.094^3 + 40250*1.094^2 + 50315*1.094^1 + 57500 = 199,245.43

or 115,000 = 199245.43/(1+MIRR)^5. Solving this we get MIRR = 11.62%

For B: Terminal value = 51750*1.094^4+38812*1.094^3 + 28750*1.094^2 + 21563*1.094^1 + 14375 = 197,319.56

or 115,000 = 197319.56/(1+MIRR)^5. Solving we get MIRR = 11.40%

(b) Exact cross over rate is the rate at which NPV is same for both the projects. The cross over rate is = 10.1883% or 10.19% (rounded off to 2 decimal place)

Graph:

60,000.00 50,000.00 As NPV 30,000.00 10,000.00 0.00 0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00


Related Solutions

Question We have two investment projects A&B. Both projects cost $250, and we require a 15%...
Question We have two investment projects A&B. Both projects cost $250, and we require a 15% return of the two investments. Year A B 1 $100 $100 2 $100 $200 3 $100 0 4 $100 0 a) Based on the payback period rule, which project would you pick? Explain. b) Based on the NPV rule, which project would you pick? Explain. c) Do a) and b) give you the same conclusion? If not, why? Please elaborate. d) What other methods...
HW 12, Problem 1, parts a and b You are considering an investment in two projects,...
HW 12, Problem 1, parts a and b You are considering an investment in two projects, A and B. Birth projects will cost $115,000, and the projected cash flows are as follows: Year Project A Project B 1 $7,188 $51,750 2 21,562 38,812 3 40,250 28,750 4 50,315 21,563 5 57,500 14,375 Assuming that the WACC is 9.4%, calculate the payback period, discounted payback period, NPV, PI, IRR and MIRR. If the projects are mutually exclusive, which project should be...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects is r. The projects’ expected net cash flows are as follows: Year Project A Project B 0 -42,000 -42,000 1 24,000 16,000 2 20,000 18,000 3 16,000 22,000 4 12,000 26,000 a. If r = 10%, which project should be selected under the NPV method? b. If r = 20%, which project should be selected under the NPV method? c. Calculate each project’s PI...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects is r. The projects’ expected net cash flows are as follows: Year Project A Project B 0 -42,000 -42,000 1 24,000 16,000 2 20,000 18,000 3 16,000 22,000 4 12,000 26,000 a. Calculate each project’s payback (PB) period if r = 10% (up to 2 decimal places). Which project should be accepted? b. Calculate each project’s discounted payback (DPB) period if r = 10%...
You are considering two investment projects each having the same cost. Each project is facing the...
You are considering two investment projects each having the same cost. Each project is facing the following events, probabilities and net profits: ALTERNATIVES:    a1: Newspaper a2: Pamphlet EVENTS: e1 e2 e3 e1 e2 e3 NET PROFITS: 4000 6000 9000 3000 7000 8000 PROBABILITIE: .25 .50 .25 .30 .50 .20 1. Construct a decision tree and show which project you would chose by using the expected value method ()? 2. Calculate the coefficient of variation of each project, and determine...
Pepsico is considering two mutually exclusive projects. Both require an initial investment of $10,000, and their...
Pepsico is considering two mutually exclusive projects. Both require an initial investment of $10,000, and their risks are average for the firm. Project X has an expected life of 2 years with after-tax cash inflows of $5,300 and $7,000 at the end of Years 1 and 2, respectively. Project Y has an expected life of 4 years with after-tax cash inflows of $3,700 at the end of each of the next 4 years. The firm's WACC is 8%. Use the...
The All-Mine Corporation is considering whether to invest in two mutually exclusive projects. Both projects cost...
The All-Mine Corporation is considering whether to invest in two mutually exclusive projects. Both projects cost $100,000. Project A will generate expected cash flow $250,000 in good economy, and $2,500 in bad economy. Project B will generate expected cash flow $300,000 in good economy, but loss $300,000 in bad economy. Each economic outcome is equally likely. a) If All-Mine is an all-equity firm, which project should the company choose? What is the incremental value with Project A or B respectively?...
The All-Mine Corporation is considering whether to invest in two mutually exclusive projects. Both projects cost...
The All-Mine Corporation is considering whether to invest in two mutually exclusive projects. Both projects cost $100,000. Project A will generate expected cash flow $250,000 in good economy, and $2,500 in bad economy. Project B will generate expected cash flow $300,000 in good economy, but loss $300,000 in bad economy. Each economic outcome is equally likely. a) If All-Mine is an all-equity firm, which project should the company choose? What is the incremental value with Project A or B respectively?...
The All-Mine Corporation is considering whether to invest in two mutually exclusive projects. Both projects cost...
The All-Mine Corporation is considering whether to invest in two mutually exclusive projects. Both projects cost $100,000. Project A will generate expected cash flow $250,000 in good economy, and $2,500 in bad economy. Project B will generate expected cash flow $300,000 in good economy, but loss $300,000 in bad economy. Each economic outcome is equally likely. a) If All-Mine is an all-equity firm, which project should the company choose? What is the incremental value with Project A or B respectively?...
Wilson Co. is considering two mutually exclusive projects. Both require an initial investment of $10,000 at...
Wilson Co. is considering two mutually exclusive projects. Both require an initial investment of $10,000 at t = 0. Project X has an expected life of 2 years with after-tax cash inflows of $7,000 and $8,500 at the end of Years 1 and 2, respectively. Project Y has an expected life of 4 years with after-tax cash inflows of $4,600 at the end of each of the next 4 years. Each project has a WACC of 11%. What is the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT